Stage 1 - Application for ABS

S/N Documents required by BCA (where applicable)

1 Request for site inspection date under the advance booking system (Form BCA-CSC-RQSI)
2 Certificate of Supervision of Building Works (Form BCA-CSC-CSPBW or BPD_CSC02)
3 As-built Plans, Test Reports and Certificate of Supervision of Lightning Protection System
4 Certificate of Supervision of Installation of Escalators/ Lifts/ Stair lift/ Platform lift
5 Certificate of Supervision of Mechanical Ventilation/ Air-conditioning System
6 Declaration by Qualified Person (Form BCA-CSC-TOPCSCDQP or BPD_CSC07)
7 Form BCA-BFAChecklist.doc
8 QP's declaration on compliance with daylight reflectance for external surfaces

Stage 2 - Application for TOP/CSC

S/N Documents required by BCA (where applicable)

1 The application form (Form BCA-CSC-TOPCSC01)


2 Certificate of Supervision of Piling Works and Notice of Completion (Form BCA-BE-QPCTPW
3 Certificate of Supervision of Structural Works (Form BCA-BE-QPCTSSW or BEV C2)
4 Certificate of Record Structural Plans/Calculations (Form BCA-BE-CTASST or BEV C3)
5 A copy of “Annex A” (listing of safety barrier submissions) of BCA circular BC 15.0.03 dated 0
6 Builder's Certificate of Completion of Building Works (Form BCA-BE-BRCTBW or BC-BC)
7 Certificate of Lift Maintenance and Testing to be submitted and lodged with Commissioner of
8 Submission of Record Plan (Form BCA-BP-BPRP01)
9 Compliance to Written Advice issued after site inspection
10 Clearance on the as-built Buildability/ Constructability score (Form BCA-BP-BS03 or BPD_BS

11 Clearance on the as-built GM score (Forms BPD_GM02 + BPD_GM02_Appendix 2)

12 Commissioning approval for the CD shelters (Form BCA-CD-COMM01)

S/N Clearances required from the other technical departments (where applicable)

Technical departments
1 PUB(Sanitary) & NEA(Environmental Health)
2 PUB (drainage)
3 FSSD - Fire Safety
4 LTA - Road & Transport
5 LTA - Vehicle Parking
6 LTA - MRTC line
7 NPARKS - Greenery
8 Cable Readiness Certificate
9 CAAS and DSTA - Height Control
10 URA - Planning (for conservation projects)
11 URA - Planning (for foreshore works)
12 Any other clearances specified in the WP from URA
m (Form BCA-CSC-RQSI)
BW or BPD_CSC02)
ning Protection System (Form BCA-CSC-CSPLP or BPD-CSC03)
t/ Platform lift (Form BCA-CSC-CSPLE or BPD-CSC04)
g System (Form BCA-CSC-CSPACMVS or BPD_CSC05)
r BPD_CSC07)

nal surfaces

n (Form BCA-BE-QPCTPW or BEV C1)


TSSW or BEV C2)
-CTASST or BEV C3)
ircular BC 15.0.03 dated 04/08/2011
E-BRCTBW or BC-BC)
ged with Commissioner of Buildings (Form BPMV_BMD_BMS/C1)

BCA-BP-BS03 or BPD_BS03, Form BEV-CS01)

M02_Appendix 2)

here applicable)

for TOP application for CSC application


TOP CSC
BP CSC
TFP FSC
BP CSC
BP CSC
BP CSC
BP CSC
Yes
Yes
TOP CSC
BP CSC

You might also like