You are on page 1of 63

Return to Index

Electrotorque Plus®

TEST PROCEDURE
1. GENERAL 2. TEST EQUIPMENT
The following test procedure provides a guide for the 2.1 A digital multimeter, oscilloscope, two-chan-
inspection and adjustment of the electrical systems nel chart recorder, clamp-on ammeter, meg-
used on Harnischfeger ELECTROTORQUE-PLUS ger, and laptop PC are required to do the
mining excavators. This is the procedure to be followed
electrical tests outlined in this test proce-
to obtain the required test data and to insure accurate
test documentation.
dure. This same equipment should also be
considered as essential for field testing or
troubleshooting.
1.1 The test procedure is written in a step-by-
step sequence which should be followed dur-
ing the commissioning process. 2.2 The shop tests and start-up tests require
additional equipment to aid in performing
the necessary tests and to provide the nec-
1.2 The control tests for each machine motion
essary test information.
(hoist/propel, crowd/propel, or swing) are
usually sufficiently redundant to allow tests 2.2.1 A laptop PC with Rockwell PLC communica-
to be made for troubleshooting purposes tions hardware and software is required to com-
without starting at the beginning of the municate with the on-board Programmable
entire test procedure. Logic Controller.

1.3 The test procedure with proper interpreta- 2.2.2 A Push-button/Reference Unit is recommended
tion can be used for shop tests at the factory, to simplify control of the individual motions dur-
commissioning tests when the machine is ing testing. See Figure 2.2.2 in Appendix B.
started at the customer's site, start-up after
troubleshooting or replacement of electrical 2.2.3 A large resistor, 12.5 ohm 6000 watt, is
required to limit the armature current during
components, and testing of the control and
the start-up of each converter. See Figure 2.2.3
converter equipment when the entire elec- in Appendix B.
trical system is not complete.
2.2.4 For testing the Reactive Power Compensation,
1.4 The proper schematic diagrams should be a capacitor unit, as shown in Figure 2.2.4, is
utilized and consulted frequently for all required as a test load. See Figure 2.2.4 in
testing procedures. Appendix B.

2.2.5 A voltage divider, such as the one shown in Fig-


ure 2.2.5, should be used to aid in making high
Certain procedures require working on voltage measurements on the RPC. See Figure
live circuits. Proper CAUTION should 2.2.5 in Appendix B.
be observed at all times.
2.2.6 A 15A, 600V, molded case circuit breaker with
#12 wire connected to 1 pole should be used as a
shorting switch for ground fault checks.

2.2.7 Miscellaneous test leads, probes, clips, cables,


auxiliary push-buttons, switches, sealing lac-
quer, etc. should be available.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 1 TEST PROCEDURE
Return to Index
Electrotorque Plus®

2.3 See Appendix A showing a list of recom- 3.2.7 Check that all plug type connectors are
mended test equipment. installed and locked in position. A loose locking
feel on the quarter turn connectors may indicate
the absence of the sealing o-ring.
3. VISUAL INSPECTION

3.1 Check that all electrical connections are


4. CONTINUITY TESTS
tight and that the wiring is properly bun-
4.1 When checking circuits containing
dled and secured. semiconductors, devices such as bells or buzzers
should not be used because of possible voltage
3.1.1 Check that the proper leads are connected to surges developed by these devices. Instead, a
the respective coil terminals on the main, auxil- DVM, continuity tester, ohmmeter, or lamp should
iary, field, lighting etc. transformers and that be used.
the primaries are connected for the correct oper-
ating and test voltage.
4.2 The entire system wiring must be checked
3.1.2 Check that the connections to the dc buswork and compared to the schematic diagrams
on the bottom of the thyristor cabinet are tight for that particular system.
and do not rub against any sharp edges.
4.3 Polarities on all dc circuits should be care-
3.1.3 Check that all overhead bus bar connections fully noted.
are tight and that the proper joint compound,
such as Alcoa No. 2 Electrical Joint Compound
has been used.
5. GROUND CHECKS

3.1.4 Check that the connections to all dc motors are 5.1 The power transformers have a resistance ground
properly made and that all motor brushes are in system connected from the secondary neutrals to
place with the brush springs properly secured. the shovel frame. Any circuit connected to the
transformers secondaries will have a resistance to
ground of approximately 250-500 ohms, therefore,
3.2 Check the electrical cabinets to assure that it is necessary to isolate the transformer neutrals
all components are properly mounted and to make ground checks.
secure.

3.2.1 Plug-in relays should be secured with a hold NOTICE


down spring or clamp.
When checking connections on the trans-
3.2.2 Check that the thermal overload elements on former secondaries, two leads must be dis-
the auxiliaries circuits are of the specified size connected from the transformer to avoid
and that the trip adjustments are set at the reading from phase to phase through the low
specified setting, on the motor starters. resistance transformer windings.

3.2.3 Check the thermal overload relays on the dc This check may also be made before the transformer
motor circuits, and that the overload elements secondaries are wired.
are of the specified size.
All transformers with high voltage primaries should
3.2.4 Check all major components of feedback and be “Megger” checked before high voltage is applied.
metering circuits for proper components. The check should be performed immediately prior to
placing the transformer into service.
3.2.5 Check the oil level in the lubrication system.
Before using the Megger, the primary and secondary
3.2.6 Check that all dc motor brakes are properly must be completely disconnected from all external con-
adjusted and operable. nections. A 1000V Megger with a 2000 megohm scale
is recommended. Readings should be taken between

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 2 CAT312.fm
Return to Index
Electrotorque Plus®

the low voltage winding and ground, low voltage and 6. TRANSFORMER VOLTAGE AND PHASE
high voltage windings, and high voltage winding and
ground.
SEQUENCE CHECKS

A value of 1000 megohms or one half the factory test


values, as posted on the interior of the transformer,
should be considered as the minimum obtained levels The tail cable must be disconnected
before the unit is energized. If a Megger test card is from the machine during the following
not available, all transformers, in general, must test to low voltage tests.
a minimum level of 500 Megohms.
6.1 The phase sequence relationship between
A reading of less than 500 megohms indicates mois- the main transformer, auxiliaries and field
ture or contamination. A proper clean-up procedure secondary windings must be correct. For ini-
and dry out procedure must be initiated to bring the
tial start-ups, a preliminary check-out of
resistance levels above 500 megohms. Refer to P&H
Service Bulletins for proper procedures.
voltages, phasing and possible ground
faults should be done by applying low volt-
age to the transformer primaries according
NOTICE to the following procedure.

If over potential tests are made, they must be 6.1.1 Open all circuit breakers on the main trans-
limited to 75% of the factory test, for a dura- former, auxiliaries and field secondaries to iso-
tion not to exceed 1 minute. Leakage must be late the secondaries from any loads.
controlled or monitored to prevent complete
breakover, tracking, etc., which will destroy 6.1.2 Short across the open power contacts on the
the transformer. Megger checks must always high voltage vacuum contactor.
be done prior to any over potential testing.
6.1.3 Short the neutral terminals on the ground fault
5.2 Circuits separated from the secondaries will circuits together for the main, auxiliaries and
have normal readings to the frame. field transformer secondaries.

5.2.1 500,000 ohms is considered as a low isolation 6.2 TRANSFORMER VOLTAGES.


resistance for average climatic conditions on the
low voltage circuits. 6.2.1 Apply a 3 phase test voltage to the main pri-
mary transformer and the auxiliaries and field
5.2.2 Extreme CAUTION should be observed in the primaries. The test voltage should not exceed
use of the Megger. 600V.

5.3 Proceed now with a systematic ground 6.2.2 Measure the secondary voltages and record the
check of all voltage systems and electrical voltage readings on the test data sheet for the
indicated test points.
equipment.
6.2.3 The following formula is used to determine the
5.4 All dc motor armatures should be checked voltages to be measured on the transformer sec-
using a 500V Megger. Readings should be ondaries when a low test voltage is applied to
in excess of 2 megohms. All leads directly the primary:
connected to the motor must be discon-
nected prior to the Megger check. VSEC = (VS rated / VP rated ) x VPRI
A reading of less than 2 megohms indicates
moisture or contamination. A proper clean-
up procedure and dry-out procedure must
be initiated to bring the resistance level
above 2 megohms.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 3 TEST PROCEDURE
Electrotorque Plus®

Where: 6.3.5 Compare the measured readings to the values


determined using the calculation of step 6.3.4
VS rated = nameplate rated secondary volts These values should not vary more than +/–5%.

VP rated = nameplate rated primary voltage (OPTIONAL TEST)


VSEC = voltage measured at the secondary terminals
6.3.6 (OPTIONAL TEST) A more extensive test to
VPRI = voltage applied to the primary terminals determine the transformer phase relationship
can be made using a two channel oscilloscope.
Example:
VP rated = transformer connected for 4160VAC • 6.3.6.1 Set the trigger mode to LINE.

VS rated = 600VAC • 6.3.6.2 Make sure that the chassis of the


oscilloscope is isolated from the frame of the
VPRI = 460VAC machine, and that the AC line connection to the
VSEC = (VS rated / VP rated ) x VPRI oscilloscope is not grounded.

= 600 / 4160 x 460 = 66VAC • 6.3.6.3 Measure the phase displacement of two
secondary voltages; say A1 - B1 to C1 - B1 by
connecting the ground leads to B1, Channel A to
6.3 TRANSFORMER PHASE RELATION.
A1, and Channel B to C1. See the transformer
connections of Figure 6.3.6.3.
6.3.1 The phase relationship between the main
transformer, auxiliaries and field secondaries is
checked by measuring the voltage difference
between corresponding phases of each trans-
former.

6.3.2 Check that the transformer neutrals are


shorted together for this test.

6.3.3 Record the voltage readings on the test data


sheet for the indicated test points.

6.3.4 To determine the correct voltage difference


between transformer phases, use the formula
found in step 6.2.3 to find the secondary volt-
ages with the test voltage on the primary, then Figure 6.3.6.3 Transformer Connections
use this formula: • 6.3.6.4 Compare the pattern of the waveforms
from one transformer secondary to that of the
Vdiff = (Vsec1 - Vsec2) / 1.732 other taking care to connect the oscilloscope the
same on comparable terminals, i.e. probe on A1,
Example: ground on B1, probe on A2, ground on B2, etc.

Vsec1 (main xfmr) = 66V • 6.3.6.5 Voltages of like phases should give a trace
of the same position on the screen. See waveforms
Vsec2 (aux. xfmr) = 51V of Figure 6.3.6.5.

Vdiff = (66 - 51) / 1.732 = 8.7V

This is the voltage that should be measured between


the corresponding phases of the auxiliaries and main
transformer secondaries.

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 4 CAT312.fm
Return to Index
Electrotorque Plus®

1. All Auxiliary Supplies


2. Control Supply
3. Relay Supply
4. Field Supplies
5. Lower Control Supply
6. Lighting Supply
7. Heater Supplies, etc.

Record these readings on the test data sheet.

NOTICE
Figure 6.3.6.5 Waveforms When the capacitors on the main trans-
former secondaries are energized, the supply
6.3.7 Remove shorting leads from high voltage con- voltage will tend to rise, causing the above
tactor and from the transformer neutral termi- voltages to read proportionately higher.
nals and reconnect the neutrals to the ground
fault circuits.
8. CONTROL SUPPLY VOLTAGES
7. HIGH VOLTAGE TO TRANSFORMER
8.1 Verify that the disconnect switch connected
PRIMARIES to the primary of the main transformer is
open.

8.1.1 Check that the test selector switch is set to


Double check Step 6.3.7. Notify and CONTROL TEST.
warn personnel, and observe all safety
precautions prior to applying high volt- 8.1.2 Open the relay and control supply circuit
age. breakers (RSCB, CSB), and the breaker supply-
ing 120VAC to the PLC power supply.
7.1 Check that all circuit breakers on the auxil-
iaries and field secondaries are open to iso- 8.1.3 Open the circuit to each capacitor charging
late the loads. Open the main transformer relay coil at the diverter circuit terminal board
disconnect switch. for each motion.

8.1.4 Use an ohmmeter to check each PLC input and


7.2 Set the test selector switch to CONTROL
each PLC output for shorts to machinery house
TEST position. ground (01021G). If any input or output is
grounded, troubleshoot and remove the ground
7.3 Check that the main air disconnect switch before applying power to any of the I/O circuits.
in the high voltage cabinet is closed.
8.2 120V Main Supply: 120V (60Hz) - 110V
7.4 Apply rated high voltage power to the (50Hz)
machine and check that the auxiliaries and
field transformer is energized. 8.2.1 If a separate lighting supply transformer is
used, close its primary supply circuit breaker.
7.5 Measure the following voltages on the line
side of the respective circuit breakers: 8.2.2 Close the lighting supply breakers. Check for
proper operation of the various lighting circuits.
(Refer to the schematics for all supplies.)
8.2.3 Close the 120V (110V) main circuit breaker
(MB). Measure the 120V main supply.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 5 TEST PROCEDURE
Electrotorque Plus®

8.2.4 Verify that the PLC is properly wired for a ify proper communication between the PLC
120V supply. Close the branch circuit breaker and operator touch screens.
supplying the PLC constant voltage supply
(CVSB). Measure the PLC CVS supply and ver- 8.7 PLC INPUTS VERIFICATION.
ify that the power on indicator is lit on the PLC
power supplies. Confirm that power is being
Use the PLC I/O screen on the GUI to access the PLC
supplied to the control cabinet touch screen com-
input screens.
puter and the operator’s cab touch screen panel.
8.7.1 Refer to the schematics and data sheets as a
8.2.5 Close the 120V lower control cabinet supply cir-
guide to verifying the various PLC inputs. Actu-
cuit breaker (LSB). Measure the 120V lower
ate each input switch, push- button, etc., or sim-
supply.
ulate actuation of the input component or
device. Check for proper status indication on the
8.2.6 Close the dc contactor supply circuit breaker
touchscreen GUI.
(DCSB). Measure the dc contactor supply.
8.7.2 Verify each of the inputs on the first PLC input
8.2.7 Verify the level of all the ac and dc circuits sup- module. Repeat this procedure for each PLC
plied by the 120V branches. (Use your machine input module.
schematics as a guide).

8.2.8 Check the functions of each of the 120V devices 8.8 PLC OUTPUTS VERIFICATION.
supplied by the individual branch circuit break-
ers. (heaters, dc contactors, etc.)

8.3 120V RELAY SUPPLY When outputs are forced on, the con-
nected device will energize. Double
8.3.1 Close the relay supply circuit breaker (RSCB). check that the test selector switch is set
Measure the 120VAC supply. to the CONTROL TEST position, and the
high voltage disconnect switch is open.
Check that the master control relay (MCR) picks up The machine and motions should be at
when all of the emergency stop push-buttons are rest and not loaded i.e., no hoist ropes,
pulled out, and that MCR drops out when any one no handles, machine on level ground. If
emergency stop push-button is pressed. an output cannot be energized safely,
disconnect the output device and check
for actuation with a 120V test lamp.
8.4 230V CONTROL SUPPLY
Make sure the ground checks called for in Step 8.1.4
8.4.1 Close the 230V supply breaker (SB), and the
have been completed.
control supply breaker. (CSB)
8.8.1 Refer to the schematics and data sheets as a
Measure the 230V control supply.
guide to verifying the various PLC outputs.
Output verification is done by forcing an indi-
8.4.2 Measure the 28VDC diverter power supply.
vidual PLC output address using a laptop PC
and checking for the proper hardware response.
8.4.3 Measure both 120V kVAR transducer supplies.
8.8.2 Verify each of the outputs on the first PLC out-
8.4.4 Close the 120V constant voltage supply breaker
put module, by forcing each of the individual
(CVMSB). Measure the 120V C.V.S. supply.
PLC output addresses either on or off as
required. Repeat this procedure for each PLC
8.5 Check the schematics for all optional equip- output module.
ment and verify their operation.
8.8.3 When finished with PLC outputs verification
8.6 With the 120V main supply breaker (MB), remove all forces!
and PLC supply breaker (CVSB) closed, ver-

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 6 CAT312.fm
Return to Index
Electrotorque Plus®

8.9 If a complete machine commissioning is to 8.12.10 Increase the swing reference to full positive
be performed, install a Reference/ Push-but- (+). Check that the swing operator’s reference
ton Unit at this time. Reference Figure 2.2.2 analog input and output respond correctly as
in Appendix B. seen on the GUI screens.

8.12.11 Repeat with the swing reference set to full


8.10 Close the suppression circuit breakers on
negative (–).
the suppression/capacitor monitor cabinet.
Close the RPC, auxiliary, and lower control 8.12.12 Set the swing brake. Press the STOP push-
cabinet breakers. button.

8.11 Check the crowd/propel transfer circuits. 8.12.13 Again, using the analog I/O screens on the
GUI, check the dc motor and bearing tempera-
8.11.1 Press the START push-button. ture monitoring. These RTD measurements
should read ambient temperatures at this time.
8.11.2 Alternately press the PROPEL and HOIST/
CROWD push-buttons and check that the arma- 8.13 Check that the trip settings on the following
ture and field contactors in transfer cabinet circuit breakers are adjusted to indicated
operate. settings (if adjustable):
8.11.3 Press the STOP push-button. Circuit Breaker Setting

8.12 PLC ANALOG I/O CHECKS. RPC Time Delay = 300mS


Current = 3X
Monitor the Analog I/O using the GUI Analog I/O
screens.
9. AUXILIARIES
8.12.1 Press the START push-button. Press the
HOIST BRAKE RELEASE push-button. 9.1 Set test selector switch to AUXILIARY
TEST.
8.12.2 Increase the hoist reference to full positive (+).
Check that the hoist operator’s reference analog 9.2 Open all auxiliary load breakers and all
input and output respond correctly as seen on motor starter breakers.
the GUI screens.

8.12.3 Repeat with the hoist reference set to full neg-


9.3 Close the main auxiliary breaker.
ative (–).
9.4 Check the auxiliary cabinet voltmeter for
8.12.4 Set the hoist brake. proper readings.

8.12.5 Release the crowd brake. 9.5 AUXILIARY LOADS BREAKER CHECK.

8.12.6 Increase the crowd reference to full positive 9.5.1 Individually close each auxiliary branch circuit
(+). Check that the crowd operator’s reference breaker. Refer to schematic.
analog input and output respond correctly as
seen on the GUI screens. 9.5.2 Check for proper voltage or operation of the
load.
8.12.7 Repeat with the crowd reference set to full neg-
ative (–). 9.5.3 Check the air compressor system.

8.12.8 Set the crowd brake. 9.5.4 Check for proper operation of the pressure
switches.
8.12.9 Release the swing brake.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 7 TEST PROCEDURE
Return to Index
Electrotorque Plus®

9.6 AUXILIARY SYSTEM CHECKS. 9.7.2 Some machines may be equipped with a 30 sec-
ond ground fault shutdown system. See sche-
9.6.1 Set the test selector switch to AUXILIARIES matics. Repeat 9.7 in control test and observe
TEST. 30 second shutdown routine.

9.6.2 Close all relay supply, control and 230V supply 9.8 Check schematics for other auxiliary func-
circuit breakers. tions and supplies; verify for correct opera-
tion.
9.6.3 Close each of the auxiliary motor starter circuit
breakers individually:
10. SWING FIELD CONTROL
9.6.4 Press the START button. Check that the
motors on the closed breaker operate properly 10.1 TEST PREPARATION
and that the direction of rotation is correct.
Transfer to propel. Verify propel blower opera- 10.1.1 Check that all field circuit breakers are open.
tion.
10.1.2 Check that the field cables are connected to the
9.6.5 The instantaneous trip adjustment on the motors.
motor starters is set to nominal the factory. If
tripping occurs due to starting inrush current, 10.1.3 Set the test selector switch to FIELD TEST.
adjust the instantaneous trip setting. Refer to
drawing R31892 for factory settings. 10.1.4 Check the ID on the flash PROM (U8), and on
the EEPROM (U10) to make sure that they
9.6.6 Press the STOP push-button. Open the agree with the shovel documentation.
breaker on the starter just tested, and close the
next. 10.2 SUPPLY VOLTAGES
9.6.7 Close the dipper trip motor starter circuit 10.2.1 Close the following circuit breakers:
breaker(s). Check that the dipper trip circuit
operates properly, and that motor rotation is cor- • 120V Main Breaker (MB)
rect. • Constant Voltage Supply Breaker (CVSB)

9.6.8 It may be necessary to make the final adjust- • DC Contactor Supply (DCSB)
ments on the dipper trip resistors after the • 230V Supply Breaker (SB)
machine is operational to obtain the proper
• Control Supply Breaker (CSB)
slack take up and tripping torque on the motor.
• Relay Supply Circuit Breaker (RSCB)
• Constant Voltage Module Supply Breaker
(CVMSB)
All resistor adjustments must be made
• Synchronizing Supply Breaker (SSB)
with the power off.
10.2.2 Using a DVM, check that the following voltages
9.7 Check the ground fault circuits by pressing are present at the fields drive module (field
the ground fault test push-buttons. Check AFM):
for appropriate fault indication.
120VAC control power at TB1-1 to TB1-2.
9.7.1 The fault indication will remain after the test
230VAC, 3ph, synchronizing voltage at P11-1 to
short is removed. The ground fault reset button
P11-16 to P11-3.
must be used to extinguish the light. See sche-
matics. 42VDC (approx. 50VDC no load) gate voltage at P11-
13 (+) to P11-14 (–).

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 8 CAT312.fm
Electrotorque Plus®

10.3 AFM SOFTWARE 10.4.5 Calculate the expected dc voltage across the
feedback resistor at normal current levels:
10.3.1 When the field AFM is properly powered, its
LCD display should read: Vfb = Ifld / CT Ratio x Rfb

P&H Electrotorque-Plus Example:

Field Control 80A / 150 x 5 ohm = 2.7 VDC

10.4.6 Verify that the test selector switch is set to


This indicates that this AFM most likely has the cor- FIELD TEST, and that the meter selector switch
rect firmware installed. is set to SWING. Close the swing field circuit
breaker.
10.3.2 Use the drive keypad to go to the ACCESS
CODES sub-menu. Enter the sub-menu using 10.4.7 Check that the swing field current remains at 0
the right arrow key and go to E007 SWR VER- amps.
SION. Confirm that the displayed software part
number agrees with the shovel documentation. 10.4.8 Press the START push-button.

10.4 AFM TESTING 10.4.9 Check that the swing field current increases to
the specified level, using the meter panel.
10.4.1 Open the Electrotorque-Plus top door to
expose the microprocessor board (A1) on your 10.5 PERFORMANCE CHECKS
right side.
10.5.1 Check the accuracy of the field current level by
Attach a digital voltmeter across test points TP1 measuring the dc voltage across the test jacks
(ACOM) and TP2 (VREF) which are located on the bot- for the swing field current on the test panel.
tom left side of the microprocessor board. Record the
measured voltage (approx. –7.000 VDC) as a negative The voltage measured should equal that calculated in
number. 10.4.5.

10.4.2 Use the drive keypad to go to the DRIVE CALI- 10.5.2 Swing field control should be documented by
BRATE sub-menu. Enter the sub-menu using connecting a chart recorder across the swing
the right arrow key and set the following param- field test jacks. Alternately START and STOP
eter: the machine while recording. Compare the
recordings to Figure 10.5.2.
X000: I/O V-REF = – VDC (Value measured in
10.4.1 ) 10.5.3 Press the STOP push-button.

Press the S key twice to save the value and exit the 10.5.4 Check the swing field voltage waveform by con-
edit mode. necting an oscilloscope across the dc terminals
of the swing field converter. Press the START
10.4.3 Reset the drive by cycling the drive power. push-button. Compare to Figure 10.5.4.

10.4.4 Verify that the EMERG STOP OK and DRIVE 10.5.5 Press the STOP push-button. Open the swing
READY LED’s are illuminated. field circuit breaker.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 9 TEST PROCEDURE
Electrotorque Plus®

Figure 10.5.2 Swing Field Waveform Chart Recording

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 10 CAT312.fm
Electrotorque Plus®

Figure 10.5.4 Swing Field Waveform Oscilloscope Display

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 11 TEST PROCEDURE
Return to Index
Electrotorque Plus®

11. CROWD / PROPEL FIELD CONTROL 11.3 AFM SOFTWARE

11.3.1 When the field AFM is properly powered, its


11.1 Test Preparation
LCD Display should read:
11.1.1 Check that all field circuit breakers are open.
P&H Electrotorque-Plus
11.1.2 Check that the field cables are connected to the Field Control
motors.

11.1.3 Set the test selector switch to FIELD TEST. This indicates that this AFM most likely has the cor-
rect firmware installed.
NOTE: If you have just commissioned the swing field,
you can skip to step 11.4.4. 11.3.2 Use the drive keypad to go to the ACCESS
CODES sub-menu. Enter the sub-menu using
11.1.4 Check the ID on the flash PROM (U8), and on the right arrow key and go to E007 SWR VER-
the EEPROM (U10) to make sure that they SION. Confirm that the displayed software part
agree with the shovel documentation. number agrees with the shovel documentation.

11.2 SUPPLY VOLTAGES 11.4 AFM TESTING

11.2.1 Close the following circuit breakers: 11.4.1 Open the Electrotorque-Plus top door to
expose the microprocessor board (A1) on your
• 120V Main Breaker (MB)
right side. Attach a digital voltmeter across TP1
• Constant Voltage Supply Breaker (CVSB) (ACOM) and TP2 (VREF) which are located on
• DC Contactor Supply (DCSB) the bottom left side of the microprocessor board.
Record the measured voltage (approx. –7.000
• 230V Supply Breaker (SB) VDC) as a negative number.
• Control Supply Breaker (CSB)
11.4.2 Use the drive keypad to go to the DRIVE CALI-
• Relay Supply Circuit Breaker (RSCB) BRATE sub-menu. Enter the sub-menu using
• Constant Voltage Module Supply Breaker the right arrow key and set the following param-
(CVMSB) eter:
• Synchronizing Supply Breaker (SSB)
X000: I/O V-REF = – VDC (Value measured in
11.4.1 )
11.2.2 Using a DVM, check that the following voltages
are present at the fields AFM:
Press the S key twice to save the value and exit the
edit mode.
120VAC control power at TB1-1 to TB1-2.
11.4.3 Reset the drive by cycling the drive power.
230VAC, 3ph, synchronizing voltage at P11-1 to P11-
16 to P11-3.
11.4.4 Verify that the EMERG STOP OK and DRIVE
READY LED’s are illuminated.
42VDC (approx. 50VDC no load) gate voltage at P11-
13 (+) to P11-14 (–).
11.4.5 Calculate the expected dc voltage across the
feedback resistor at normal current levels:

Vfb = Ifld / CT Ratio x Rfb

Examples:
70A / 150 x 5ohm = 2.3 VDC
150A / 150 x 5ohm = 5.0 VDC

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 12 CAT312.fm
Electrotorque Plus®

11.4.6 Verify that the test selector switch is set to 11.5.4 Force a strong propel field level from the GUI
FIELD TEST, and that the meter selector switch screen called AFM TEST SCREEN. Check that
is set to CROWD. Close the crowd field circuit the propel field current increases to the speci-
breaker. fied level, using the meter panel.

11.4.7 Check that the crowd field current remains at 0 11.5.5 The crowd/propel field control should be docu-
amps. mented by connecting a chart recorder across
the crowd/propel field test jacks. While record-
11.4.8 Press the START push-button. ing, start the machine, then after a few seconds,
transfer to the propel mode, then force a strong
11.4.9 Check that the crowd field current increases to propel field
the specified level, using the meter panel.
Transfer back to crowd, press the STOP push-button.
11.5 PERFORMANCE CHECKS Compare the recordings to Figures 11.5.5a, 11.5.5b,
and 11.5.5c.
11.5.1 Check the accuracy of the field current level by
measuring the dc voltage across the test jacks 11.5.6 Press the STOP push-button.
for the crowd field current on the test panel.
11.5.7 Check the crowd/propel field Voltage waveform
The voltage measured should equal that calculated in by connecting an oscilloscope across the dc ter-
11.4.5. minals of the crowd/propel field converter. Press
the START push-button. Compare to Figure
11.5.2 Press the PROPEL push-button. 11.5.7.

11.5.3 Check that the propel field current increases to 11.5.8 Press the STOP push-button. Open the crowd/
the specified level, using the meter panel. propel field circuit breaker.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 13 TEST PROCEDURE
Electrotorque Plus®

Figure 11.5.5a Crowd Field Current Recording

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 14 CAT312.fm
Electrotorque Plus®

Figure 11.5.5b Propel Field Current Recording

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 15 TEST PROCEDURE
Electrotorque Plus®

Figure 11.5.5c Crowd/Propel Transfer Recording

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 16 CAT312.fm
Electrotorque Plus®

Figure 11.5.7 Crowd/Propel Field Voltage Oscilloscope Display

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 17 TEST PROCEDURE
Return to Index
Electrotorque Plus®

12. HOIST FIELD CONTROL 12.3 AFM SOFTWARE

12.3.1 When the field AFM is properly powered, its


12.1 TEST PREPARATION
LCD Display should read:
12.1.1 Check that all field circuit breakers are open.
P&H Electrotorque-Plus
12.1.2 Check that the field cables are connected to the Field Control
motors.

12.1.3 Set the test selector switch to FIELD TEST. This indicates that this AFM most likely has the cor-
rect firmware installed.
NOTE: If you have just commissioned the swing or
crowd/propel field, you can skip to step 12.4.4. 12.3.2 Use the drive keypad to go to the ACCESS
CODES sub-menu. Enter the sub-menu using
12.1.4 Check the ID on the flash PROM (U8), and on the right arrow key and go to E007 SWR VER-
the EEPROM (U10) to make sure that they SION. Confirm that the displayed software part
agree with the shovel documentation. number agrees with the shovel documentation.

12.2 SUPPLY VOLTAGES 12.4 AFM TESTING

12.2.1 Close the following circuit breakers: 12.4.1 Open the Electrotorque-Plus top door to
• 120V Main Breaker (MB) expose the microprocessor board (A1) on your
right side. Attach a digital voltmeter across TP1
• Constant Voltage Supply Breaker (CVSB) (ACOM) and TP2 (VREF) which are located on
• DC Contactor Supply (DCSB) the bottom left side of the microprocessor board.
Record the measured voltage (approx. –7.000
• 230V Supply Breaker (SB) VDC) as a negative number.
• Control Supply Breaker (CSB)
12.4.2 Use the drive keypad to go to the DRIVE CALI-
• Relay Supply Circuit Breaker (RSCB)
BRATE sub-menu. Enter the sub-menu using
• Constant Voltage Module Supply Breaker the right arrow key and set the following
(CVMSB) parameter:
• Synchronizing Supply Breaker (SSB)
X000: I/O V-REF = – VDC (Value measured in
12.2.2 Using a DVM, check that the following voltages 12.4.1 )
are present at the fields AFM:
Press the S key twice to save the value and exit the
120VAC Control Power at TB1-1 to TB1-2. edit mode.

230VAC, 3ph, Synchronizing Voltage at P11-1 to 12.4.3 Reset the drive by cycling the drive power.
P11-16 to P11-3.
42VDC (approx. 50VDC no load) gate voltage at 12.4.4 Verify that the EMERG STOP OK and DRIVE
P11-13 (+) to P11-14 (–). READY LED’s are illuminated.

12.4.5 Calculate the expected dc voltage across the


feedback resistor at normal current levels:

Vfb = Ifld / CT Ratio x Rfb

Examples:
50A / 150 x 5ohm = 1.7 VDC
140A / 150 x 5ohm = 4.7 VDC

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 18 CAT312.fm
Return to Index
Electrotorque Plus®

12.4.6 Verify that the test selector switch is set to 13. HOIST ARMATURE CONTROL
FIELD TEST, and that the meter selector switch
is set to HOIST. Close the hoist field circuit
breaker.
13.1 TEST PREPARATION

12.4.7 Check that the hoist field current remains 13.1.1 Set the test selector switch to CONTROL TEST.
at 0 amps.
13.1.2 Open the circuit breakers on the RPC cabinet.
12.4.8 Press the START push-button. Open the constant voltage module supply circuit
breaker (CVMSB), and the control supply
12.4.9 Check that the hoist field current increases to breaker (CSB).
the specified level, using the meter panel.
13.1.3 Connect a 12.5 ohm current limiting resistor in
series with hoist motor armature, H2.
12.5 PERFORMANCE CHECKS
13.1.4 Install a reference/push-button unit.
12.5.1 Check the accuracy of the field current level by Reference: Figure 2.2.2 in Appendix B.
measuring the dc voltage across the test jacks
for the hoist field current on the test panel. 13.1.5 Check the ID on the flash PROM (U8), and on
the EEPROM (U10) to make sure that they
The voltage measured should equal that calculated in agree with the shovel documentation.
12.4.5.
13.1.6 Check for open or shorted thyristor firing pulse
12.5.2 Force a weak hoist field level from the GUI cables by measuring between the bridge inter-
screen called AFM TEST SCREEN. Check that face connector pins. A reading of 50 ohms is to
the hoist field current increases to the specified be expected between the following pins:
level, using the meter panel.
P9-1 to P9-2, P9-3 to P9-4,
12.5.3 The hoist field control should be documented by
connecting a chart recorder across the hoist field P9-5 to P9-6, P9-9 to P9-10,
test jacks. While recording, start the machine, P9-11 to P9-12, P9-13 to P9-14,
then after a few seconds force a strong hoist
P9-15 to P9-16, P9-17 to P9-18,
field, then a weak hoist field When completed
press the STOP push-button. Compare the P9-19 to P9-20, P9-23 to P9-24,
recordings to Figure 12.5.3. P9-25 to P9-26, P9-27 to P9-28
P10-1 to P10-2, P10-3 to P10-4,
12.5.4 Press the STOP push-button.
P10-5 to P10-6, P10-9 to P10-10,
12.5.5 Check the hoist field voltage waveform by con- P10-11 to P10-12, P10-13 to P10-14,
necting an oscilloscope across the dc terminals
P10-15 to P10-16, P10-17 to P10-18,
of the hoist field converter. Press the START
push-button. Compare to Figure 12.5.5. P10-19 to P10-20, P10-23 to P10-24,
P10-25 to P10-26, P10-27 to P10-28
12.5.6 Press the STOP push-button. Open the hoist
field circuit breaker.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 19 TEST PROCEDURE
Electrotorque Plus®

Figure 12.5.3 Hoist Field Current Chart Recording

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 20 CAT312.fm
Electrotorque Plus®

Figure 12.5.5 Hoist Field Voltage Waveform Display

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 21 TEST PROCEDURE
Electrotorque Plus®

13.2 SUPPLY VOLTAGES 13.4 13.4 AFM TESTING

13.2.1 Close the following circuit breakers: 13.4.1 Open the Electrotorque-Plus top door to
• 120V Main Breaker (MB) expose the microprocessor board (A1) on your
right side. Attach a digital voltmeter across TP1
• Constant Voltage Supply Breaker (CVSB) (ACOM) and TP2 (VREF) which are located on
• DC Contactor Supply (DCSB) the bottom left side of the microprocessor board.
Record the measured voltage (approx. –7.000
• 230V Supply Breaker (SB)
VDC) as a negative number.
• Control Supply Breaker (CSB)
• Relay Supply Circuit Breaker (RSCB) 13.4.2 Use the drive keypad to go to the DRIVE CALI-
BRATE sub-menu. Enter the sub-menu using
• Constant Voltage Module Supply Breaker the right arrow key and set the following
(CVMSB) parameter:
• Synchronizing Supply Breaker (SSB)
X000: I/O V-REF = – VDC (Value measured in
13.2.2 Using a DVM, check that the following voltages 13.4.1 )
are present at the hoist AFM:
Press the S key twice to save the value and exit the
120VAC Control Power at TB1-1 to TB1-2. edit mode.

230VAC, 3ph, Synchronizing Voltage at P11-1 to 13.4.3 Reset the drive by cycling the drive power.
P11-16 to P11-3.
13.4.4 Verify that the EMERG STOP OK and DRIVE
42VDC (approx. 50VDC no load) gate voltage at READY LED’s are illuminated.
P11-13 (+) to P11-14 (–).
13.5 AUTOCAL PROCEDURE (Operator’s Ref-
13.3 AFM SOFTWARE erence Calibration)

13.3.1 When the hoist AFM is properly powered, its 13.5.1 On the GUI, go to the AFM TEST SCREEN.
LCD Display should read:
13.5.2 Verify that the test selector switch is set to
CONTROL TEST. Press the START push-but-
P&H Electrotorque-Plus ton, and the HOIST BRAKE RELEASE push-
Armature Control button.

13.5.3 Turn the hoist reference potentiometer to full


This indicates that this AFM most likely has the cor-
positive (+). At the AFM TEST SCREEN, press
rect firmware installed.
the HOIST AUTOCAL ON touch button.
13.3.2 Use the drive keypad to go to the ACCESS
13.5.4 After the GUI touch button turns green, press
CODES sub-menu. Enter the sub-menu using
the HOIST AUTOCAL OFF touch button.
the right arrow key and go to E007 SWR VER-
SION. Confirm that the displayed software part
13.5.5 When the touch button turns red, turn the hoist
number agrees with the shovel documentation.
reference potentiometer to full negative (–).

13.5.6 Press the HOIST AUTOCAL ON touch button.


After the GUI touch button turns green, press
the HOIST AUTOCAL OFF touch button.

13.5.7 Confirm that the reference signals are properly


calibrated by checking that the adjusted refer-
ence at A066 is +100% with the reference full

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 22 CAT312.fm
Electrotorque Plus®

positive, and –100% with the reference full neg- 13.7.4 Set the test selector switch to ARMATURE
ative. Use the drive keypad to go to the OPER- TEST, and close the high voltage disconnect
ATE sub-menu. Enter the sub-menu using the switch.
right arrow key. Arrow up to reach the
BLOCKS ANALOG sub-menu, and enter it with 13.7.5 Set the reference to 0V.
the right arrow key. Arrow up to A066.

13.5.8 The hoist AUTOCAL procedure is complete. NOTICE


Press the STOP push-button. Press the drive S
key twice to exit the sub-menus. With a series armature resistor installed, a
nuisance ground fault indication may occur
13.6 THYRISTOR PULSE SEQUENCE after the firing pulses are phased advanced
in armature test. The series resistor is the
13.6.1 Verify that the test selector switch is set to cause of this indication, and the indication
can be ignored until the resistor is removed,
CONTROL TEST. Press the START push-but-
if:
ton, and the HOIST BRAKE RELEASE button.
1. The ground fault only occurs after the brake has been
13.6.2 With the reference in the full negative (lower) released.
position, use an oscilloscope to check the firing 2. The MSN to ground voltage is less than 60VAC.
pulse sequence of both hoist lower converters, (A true line-to-ground fault would be approximately
Figure 13.6. 350VAC)
3. Prior ground checks have proved negative.
13.6.3 Place the reference in the full positive (hoist)
position, and check the firing pulse sequence of 13.7.6 Press the START push-button.
both hoist Converters, Figure 13.6.
13.7.7 Check that the dc voltage across the series
13.6.4 Press the PROPEL push-button. Check that armature resistor is approximately 0VDC. (A
the firing pulses to the H1 converter remains higher voltage would indicate the possibility of a
present while the firing pulses to the H2 con- phasing error on the main transformer second-
verter are blocked. ary or on the synchronizing supply voltage.)
Reference: Figure 13.7.7 in Appendix B.
13.6.5 Press the HOIST/CROWD push-button, and
the HOIST BRAKE RELEASE push-button. 13.7.8 Press the HOIST BRAKE RELEASE push-but-
Firing pulses should again be present on both ton. Slowly increase the reference in the posi-
the H1 and H2 converters. tive (+) direction.

13.6.6 Press the STOP push-button. The voltage across the feedback resistor should
increase directly in proportion to the reference.
13.7 VOLTAGE CONTROL, HOIST
13.7.9 Slowly increase the reference in the negative
13.7.1 Disable OPEN SCR TEST. At the Hoist AFM (–) direction.
keypad, change Y058 from D149 TEST ARM to
D087 ZERO BIT. Reset drive. The voltage across the feedback resistor should
increase directly in proportion to the reference and
13.7.2 Connect a digital voltmeter (1kV range) across should have changed polarity.
the series armature resistor.

13.7.3 Remove the relay from the differential voltage


NOTICE
module (DVAH) to prevent a shutdown due to
The P1 propel armature circuit must be
unbalanced armature voltages.
intact for proper operation of the voltage
feedback circuit. See Figure 13.7.7 in Appen-
dix B.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 23 TEST PROCEDURE
Electrotorque Plus®

Figure 13.6 Thyristor Pulse Sequence

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 24 CAT312.fm
Electrotorque Plus®

13.8 CURRENT FEEDBACK, HOIST 13.10.2 Connect a digital voltmeter across the hoist
current feedback (IAFB) test jacks.
13.8.1 With the reference close to fully positive, check
that the current feedback signal at the AFM 13.10.3 Calculate the dc voltage to be expected across
connector P11 - terminal 10 to terminal 8 the IAFB test jack resistor:
(08351 to 01021C) is positive. This signal will
be very small, 0.1V or less, so use care in read- Istall / 300 = Vtest jack
ing the meter. Use of a strip chart recorder will
insure that the feedback polarity is correct. Example:

13.8.2 With the reference close to fully negative, check 2625A / 300 = 8.75 VDC
that the current feedback signal at the AFM
connector P11 - terminal 10 to terminal 8 13.10.4 Set the meter selector switches to monitor the
(08351 to 01021C) remains positive. hoist motion parameters.

13.8.3 Reduce the REFERENCE to 0V. Press the 13.10.5 Set the hoist reference potentiometer to 0
STOP push-button. VDC. Press the START push-button.

13.8.4 Remove the series armature resistor.

13.9 ARMATURE CURRENT RESPONSE, The motors should not be run at maxi-
HOIST mum stall current for more than 5 sec-
onds at a time. Longer periods will
13.9.1 Connect a strip chart or memory recorder cause localized commutator heating.
(Ch. 1) across the hoist current feedback (IAFB)
test jacks. 13.10.6 Press the HOIST BRAKE RELEASE push-
button.
13.9.2 Press the START push-button. Press the
HOIST BRAKE RELEASE push-button. 13.10.7 Increase the hoist reference to full positive
Increase the hoist operators reference until the (hoist). Check the current value shown on the
armature current ammeter reads 500A. drive LCD display. Record the voltage seen
across the IAFB test jacks.
13.9.3 On the GUI, at the AFM TEST SCREEN, press
the HOIST CURRENT REGULATOR MODE 13.10.8 Press the HOIST BRAKE SET push-button.
touch button then press the START HOIST
STEP REFERENCE touch button. The PLC 13.10.9 Verify that values recorded in 13.10.7, agree
will cause the AFM to pulse the output current with the I-A2 level shown In the Specified Elec-
for a 10 Sec. period. During this period, record trical Data sheet.
the IAFB output, and compare the recording to
Figure 13.9. Overshoots or undershoots should 13.10.10 After the commutators have been allowed to
not be present. cool for at least one full minute, again, Press the
HOIST BRAKE RELEASE push-button and
13.9.4 Press the HOIST CURRENT REGULATOR increase the hoist reference to full negative
MODE touch button to disable. (lower).

13.9.5 Press the STOP push-button. 13.10.11 Verify that values recorded in 13.10.10, agree
with the I-A3 level shown in the Specified Elec-
13.10 STALL CURRENT, HOIST trical Data sheet. Press the HOIST BRAKE SET
push-button.
13.10.1 Use the drive keypad to go to the DRIVE
ANALOG sub-menu. Enter the sub-menu using 13.10.12 After the commutators have been allowed to
the right arrow key , then go to parameter A004: cool for at least one full minute, again, Press the
I ARM AMP. HOIST BRAKE RELEASE push-button and

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 25 TEST PROCEDURE
Electrotorque Plus®

Figure 13.9 IAFB Chart Recording

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 26 CAT312.fm
Electrotorque Plus®

increase the hoist reference to full positive 13.11.9 Press the STOP push-button. Reduce the
(hoist). hoist reference to 0 VDC.

13.10.13 Check that the analog armature current 13.12 VOLTAGE CONTROL - RUN MODE,
panel meter also reads the stall level +/– 50A. HOIST
13.10.14 Press the HOIST BRAKE SET push-button. 13.12.1 Set the test selector switch to RUN.

13.11 STALL CURRENT, PROPEL (Hoist) 13.12.2 Deactivate the RPC shutdown by forcing off
the RPC circuit breaker inputs.
13.11.1 Calculate the dc voltage to be expected across (Alternative: Disconnect the RPC circuit
the hoist IAFB test jack resistor when in the breaker interlock input to the PLC.)
propel mode:
13.12.3 Close the hoist field circuit breaker.
Istall / 300 = Vtest jack
13.12.4 With the reference set to 0 VDC, press the
Example: START push-button.

1450A / 300 = 4.8 VDC 13.12.5 Press the HOIST BRAKE RELEASE
push-button and check that the armature
13.11.2 Press the PROPEL push-button. current is approximately 0 A.

13.12.6 Check that the motors can be controlled with


the reference by accelerating, decelerating and
changing direction. Do not exceed 50% of full
The motors should not be run at maxi- speed.
mum stall current for more than 5 sec-
onds at a time. Longer periods will 13.12.7 Set the hoist brakes. Press the STOP push-
cause localized commutator heating. button.
13.11.3 Increase the hoist reference to full positive
(forward). Check the current value shown on 13.13 FUSE FAULT DETECTION, HOIST
the drive LCD display. Record the voltage seen
across the IAFB test jacks. 13.13.1 Remove a fuse monitor lead from the hoist
armature converter.
13.11.4 Press the HOIST/CROWD push-button.
13.13.2 Press the START button.
13.11.5 Verify that values recorded in 13.11.3, agree
with the I-A2 level shown in the Specified Elec- 13.13.3 Check that the machine shuts down and that
trical Data sheet. a hoist fuse fault is indicated.

13.11.6 After the commutators have been allowed to 13.13.4 Replace the fuse lead.
cool for at least one full minute, again, press the
PROPEL push-button and increase the hoist 13.13.5 Repeat the test for the opposite hoist con-
reference to full negative (reverse). Check the verter.
current value shown on the drive LCD display.
Record the voltage seen across the IAFB test
jacks.

13.11.7 Press the HOIST/CROWD push-button.

13.11.8 Verify that values recorded in 13.11.6, agree


with the I-A2 level shown in the Specified Elec-
trical Data sheet.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 27 TEST PROCEDURE
Electrotorque Plus®

13.14 DIVERTER CIRCUIT CHECKS. 13.16 DIVERTER CAPACITOR CHECKS, HOIST

13.14.1 Check that the relay and control supply cir- 13.16.1 Reconnect the wire to the capacitor charging
cuit breakers are closed. relay at the terminal board on the hoist diverter
circuit panels in the converter cabinet to acti-
13.14.2 Set the test selector switch to CONTROL vate the capacitor charging power supply.
TEST.

13.14.3 Connect a voltmeter to (TB1-1) on the hoist


diverter control module and check that the sup- Use extreme caution when making volt-
ply voltage is +28VDC. age measurements in this section of the
test procedure. Voltages of approxi-
13.14.4 Press the START button. mately 1300V will be measured.
13.14.5 Check that the READY light on the diverter 13.16.2 Connect a digital voltmeter (1kV range) across
module is on. the H1 hoist diverter capacitor.
13.14.6 Check that the DE-BLOCK LED on the AFM 13.16.3 Manually depress the hoist capacitor charging
is on. relay armature to close its contacts.
13.14.7 Check the gate block circuit by shorting TB2- 13.16.4 The voltage across the diverter capacitor
10 to TB2-9 on the diverter module. should begin to climb at the capacitor charges.
Ultimately this voltage should be about 1300
13.14.8 The DE-BLOCK LED on the AFM should not VDC, but to avoid overvoltage on the DVM, we
be illuminated. will stop charging (release the relay armature)
at about 900 VDC. Check schematics for polar-
13.14.9 Press STOP button. Remove the short on the ity, and verify that the charging polarity is cor-
diverter module. rect.

13.15 DIVERTER CURRENT SENSOR 13.16.5 When you release the charging relay, the volt-
CHECKS, HOIST age across the diverter capacitor must decay to
less than 50 VDC in less than 30 Sec.
13.15.1 Connect a digital voltmeter to TP2 (–) and
TP3 (+) on the hoist diverter control module. 13.16.6 Repeat these tests for the H2 diverter capaci-
tor.
13.15.2 Set the test selector switch to ARMATURE
TEST. 13.17 CHECK DIVERTER CIRCUIT OPERA-
TION, HOIST
13.15.3 Press START button, press HOIST BRAKE
RELEASE button and check that the meter 13.17.1 Connect a digital voltmeter to TP1(+) and
reads at full hoist: TP2(–) on the diverter control module.

Volts = Iarmstall/300 (+/–0.5VDC) 13.17.2 Adjust the current trip adjust potentiometer
so that the meter reads +2.1VDC.
13.15.4 Record this in the test data sheet.
13.17.3 Set the test selector switch to ARMATURE
13.15.5 Press STOP button. Disconnect the meter. TEST.

13.17.4 Reconnect the meter to TP3(+) and TP2(–) on


the diverter control module.

13.17.5 Press the START button. Press the HOIST


BRAKE RELEASE button.

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 28 CAT312.fm
Electrotorque Plus®

13.17.6 Slowly increase the hoist reference to the full 13.18.5 Move the hoist controller potentiometer to full
hoist position. positive (+). On the GUI, press the AUTOCAL
HOIST ON touch button.
13.17.7 Check that the machine shuts down when the
meter reads about 3.5VDC. 13.18.6 After the GUI touch button turns green for a
few moments, press the AUTOCAL HOIST OFF
13.17.8 Check that the capacitor voltage on the hoist touch button.
converter bridge drops instantly to approxi-
mately 0 volts. 13.18.7 When the touch button turns red, move the
hoist controller potentiometer to full negative
13.17.9 Press the STOP button. (–).

13.17.10 Adjust the current trip for normal operation. 13.18.8 On the GUI, press the AUTOCAL HOIST ON
touch button. After the GUI touch button turns
13.17.11 Reconnect the meter to TP1(+) and TP2(–) on green for a few moments, press the AUTOCAL
the control module. HOIST OFF touch button.

13.17.12 Readjust the current trip adjust potentiome- 13.18.9 Confirm that the reference signals are prop-
ter to its maximum clockwise position. erly calibrated by checking that the ADJUSTED
REFERENCE at A066 is +100% with the refer-
13.17.13 Press the START push-button. Press the ence full positive, and –100% with the reference
HOIST BRAKE RELEASE push-button. full negative. Use the drive keypad to go to the
OPERATE sub-menu. Enter the sub-menu
13.17.14 Stall the hoist and turn down the current using the right arrow key. Arrow up to reach
trip potentiometer until the module trips. Do the BLOCKS ANALOG sub-menu, and enter it
not stall motor for more than 5 seconds. with the right arrow key. Arrow up to A066.

13.17.15 Check and read voltage at TP1-TP2. 13.18.10 The hoist AUTOCAL procedure is complete.
Press the STOP push-button. Press the drive S
13.17.16 Readjust level as follows. key twice to exit the sub-menus.

Volts = (VTP1-VTP2) x 1.4 13.18.11 Set the test selector switch to RUN. Start
the machine and release the hoist brakes.
Where:
13.18.12 Check that full control of the hoist motion is
VTP1 to VTP2 is from 13.17.15 obtained by the operator's controller.

13.18.13 Check that the hoist motion runs in the


13.18 OPERATE FROM THE OPERATOR’S proper direction in relation to the controller
COOP, HOIST position.

13.18.1 Remove the reference/push-button unit. If the motor rotation is wrong, check that the reference
Reconnect the PLC/coop cables. is of the proper polarity.

13.18.2 REPEAT THE AUTOCAL PROCEDURE The motor rotation may be reversed by reversing the
(Operator’s Reference Calibration) motor field connections.

13.18.3 On the GUI, go to AFM TEST SCREEN.

13.18.4 Verify that the test selector switch is set to


CONTROL TEST. Press the START push-but-
ton, and the HOIST BRAKE RELEASE button.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 29 TEST PROCEDURE
Electrotorque Plus®

13.19 VOLTAGE RESPONSE, HOIST. (With 13.19.7 Set the dipper on the ground and press the
Hoist Ropes and Dipper attached) STOP push-button.

13.19.1 Connect a chart recorder to record across the 13.20 FIELD WEAKENING, HOIST
hoist armature voltage feedback (VAFB) test
jacks (Ch. 1), and the hoist armature current 13.20.1 Connect channel 2 of the recorder to the
feedback (IAFB) test jacks (Ch. 2). HOIST FIELD FEEDBACK (IFFB) test jacks
and check that field weakening occurs when
13.19.2 Press the START push-button. Press the lowering with an empty dipper at full speed.
HOIST BRAKE RELEASE button. Compare with Figure 13.20.1.

13.19.3 Check that the armature voltage of each 13.20.2 Set the dipper on the ground and press the
motor is correct for both full hoist and full lower STOP push-button.
directions as spelled out in the Specified Electri-
cal Data sheet. 13.21 DIVERTER VAFB SIGNAL CHECKS,
• 13.19.3.1 If the terminal voltage is significantly
HOIST
lower than the voltage read at the AFM (A012
13.21.1 Connect a digital voltmeter from TB1-4 to
ARM VOLTS) then change the X003 parameter
TB1-5 on the hoist diverter control module.
from 100 to something less. For example: If the
measured terminal voltage is 500V and A012
13.21.2 With the test selector switch set to RUN, press
reads 550V then change X003 from 100 to 91
the START push-button and HOIST BRAKE
(500/550 x 100 = 91). Changes made to X
RELEASE push-button.
parameters are activated immediately after
pressing the S key. Note: X004 is used for right
13.21.3 Operate the hoist motion, and check that the
propel.
voltage is –9.7V +/–1V at full speed in the hoist
direction and +8.9V +/–1V at full speed in the
13.19.4 Operate the hoist by alternately applying full
lower direction.
positive and full negative reference and compare
the recordings of VAFB and IAFB with Figure
13.21.4 Set the dipper on the ground and press STOP
13.19.4.
button.
13.19.5 Voltage response recordings will require two
participants; an operator in the operator’s coop, 13.22 DIVERTER CIRCUIT OPERATION
and a technician in the control room. Have the
operator slowly raise the empty dipper at a con- 13.22.1 If nuisance tripping occurs during normal
stant speed. operation, use the procedure of 13.17.11 and
increase the trip setting by increments of 0.1V
13.19.6 As the dipper is slowly rising, press the until nuisance tripping does not occur. (It should
HOIST STEP REFERENCE touch button on the not be necessary to increase this setting more
GUI. The PLC will pulse the output voltage for than 0.5VDC. )
a 10 second time period. During this period,
record the VAFB and IAFB signals and compare 13.23 THIS COMPLETES TESTING OF THE
with Figure 13.19.6. The VAFB signal should HOIST ARMATURE CONTROL
have minimum response time without over-
shoot. At any time during this procedure, the 13.23.1 Press the STOP push-button.
operator has the ability to override the step ref-
erence, should safety require it. In case satisfac- 13.23.2 Remove all PLC forces.
tory recordings are not obtained on the first run,
you can instruct the operator to quickly lower 13.23.3 Open the field circuit breakers.
the dipper before it reaches the upper limit, and
then begin raising it again at a slow and steady 13.23.4 Enable OPEN SCR TEST. At the hoist AFM
rate. keypad, change Y058 from D087 ZERO BIT to
D149 TEST ARM. Reset the drive.

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 30 CAT312.fm
Electrotorque Plus®

Figure 13.19.4 VAFB and IAFB Chart Recording

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 31 TEST PROCEDURE
Electrotorque Plus®

Figure 13.19.6 VAFB and IAFB Chart Recording

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 32 CAT312.fm
Electrotorque Plus®

Figure 13.20.1 Hoist Field Weakening Chart Recording

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 33 TEST PROCEDURE
Return to Index
Electrotorque Plus®

14. CROWD ARMATURE CONTROL 14.2.2 Using a DVM, check that the following voltages
are present at the crowd armature AFM:
14.1 TEST PREPARATION A) 120VAC control power at TB1-1 to TB1-2.
14.1.1 Set the test selector switch to CONTROL TEST. B) 230VAC, 3ph, synchronizing voltage at P11-1 to
P11-16 to P11-3.
14.1.2 Open the circuit breakers on the RPC cabinet. C) 42VDC (approx. 50VDC no load) gate voltage at
Open the constant voltage module supply circuit P11-13 (+) to P11-14 (–).
breaker (CVMSB), and the control supply
breaker (CSB).
14.3 AFM SOFTWARE
14.1.3 Connect a 12.5 ohm current limiting resistor in
series with crowd motor armature. 14.3.1 When the crowd AFM is properly powered, its
LCD display should read:
14.1.4 Install a reference/push-button unit. See Fig-
ure 2.2.2 in Appendix B. P&H Electrotorque-Plus
Armature Control
14.1.5 Check the ID on the flash PROM (U8), and on
the EEPROM (U10) to make sure that they
agree with the shovel documentation. This indicates that this AFM most likely has the cor-
rect firmware installed.
14.1.6 Check for open or shorted thyristor firing pulse
cables by measuring between the bridge inter- 14.3.2 Use the drive keypad to go to the ACCESS
face connector pins. A reading of 50 ohms is to CODES sub-menu. Enter the sub-menu using
be expected between the following pins: the right arrow key and go to E007 SWR VER-
SION. Confirm that the displayed software part
P9-1 to P9-2, P9-3 to P9-4, number agrees with the shovel documentation.
P9-5 to P9-6, P9-9 to P9-10,
14.4 AFM TESTING
P9-11 to P9-12, P9-13 to P9-14,
P9-15 to P9-16, P9-17 to P9-18, 14.4.1 Open the Electrotorque-Plus top door to
expose the microprocessor board A1 on your
P9-19 to P9-20, P9-23 to P9-24, right side. Attach a digital voltmeter across TP1
P9-25 to P9-26, P9-27 to P9-28 (ACOM) and TP2 (VREF) which are located on
the bottom left side of the microprocessor board.
14.2 SUPPLY VOLTAGES Record the measured voltage (approx. –7.000
VDC) as a negative number.
14.2.1 Close the following circuit breakers:
14.4.2 Use the drive keypad to go to the DRIVE CALI-
• 120V Main Breaker (MB) BRATE sub-menu. Enter the sub-menu using
• Constant Voltage Supply Breaker (CVSB) the right arrow key and set the following
parameter:
• DC Contactor Supply (DCSB)
• 230V Supply Breaker (SB) X000: I/O V-REF = – VDC (value measured in
14.4.1 )
• Control Supply Breaker (CSB)
• Relay Supply Circuit Breaker (RSCB) Press the S key twice to save the value and exit the
• Constant Voltage Module Supply Breaker edit mode.
(CVMSB)
14.4.3 Reset the drive by cycling the drive power.
• Synchronizing Supply Breaker (SSB)
14.4.4 Verify that the EMERG STOP OK and DRIVE
READY LED’s are illuminated.

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 34 CAT312.fm
Electrotorque Plus®

14.5 AUTOCAL PROCEDURE 14.6.3 Place the reference in the full positive (+)
(Operator’s Reference Calibration) (crowd) position, and check the firing pulse
sequence of the crowd converter, Figure 14.6
14.5.1 On the GUI, go to the AFM TEST SCREEN.
14.6.4 Press the STOP push-button.
14.5.2 Verify that the test selector switch is set to
CONTROL TEST. Press the START push-but- 14.7 VOLTAGE CONTROL, CROWD
ton, and the CROWD BRAKE RELEASE but-
ton. 14.7.1 Disable OPEN SCR TEST. At the crowd AFM
keypad, change Y058 from D149 TEST ARM to
14.5.3 Turn the crowd reference potentiometer to full D087 ZERO BIT. Reset drive.
positive (+). On the GUI, press the AUTOCAL
CROWD ON touch button. 14.7.2 Connect a digital voltmeter (1kV range) across
the series armature resistor.
14.5.4 After the touch button turns green for a few
moments, press the AUTOCAL CROWD OFF 14.7.3 Set the test selector switch to ARMATURE
touch button. TEST, and close the high voltage disconnect
switch.
14.5.5 When the touch button turns red, turn the
crowd reference potentiometer to full negative 14.7.4 Set the reference to 0V.
(–).
14.7.5 Press the START push-button.
14.5.6 On the GUI, press the AUTOCAL CROWD ON
touch button. After the touch button turns 14.7.6 Check that the dc voltage across the series
green for a few moments, press the AUTOCAL armature resistor is approximately 0VDC. (A
CROWD OFF touch button. higher voltage would indicate the possibility of a
phasing error on the main transformer second-
14.5.7 Confirm that the reference signals are properly ary, or on the synchronizing supply voltage.)
calibrated by checking that the ADJUSTED
REFERENCE at A066 is +100% with the refer- 14.7.7 Press the CROWD BRAKE RELEASE push-
ence full positive, and –100% with the reference button. Slowly, increase the crowd reference in
full negative. Use the drive keypad to go to the the positive direction.
OPERATE sub-menu. Enter the sub-menu
using the right arrow key. Arrow up to reach The voltage across the feedback resistor should
the BLOCKS ANALOG sub-menu, and enter it increase directly in proportion to the reference.
with the right arrow key. Arrow up to A066.
14.7.8 Slowly, increase the crowd reference in the neg-
14.5.8 The crowd AUTOCAL procedure is complete. ative direction.
Press the STOP push-button. Press the drive S
key twice to exit the sub-menus. The voltage across the feedback resistor should
increase directly in proportion to the reference, and
14.6 THYRISTOR PULSE SEQUENCE should have changed polarity.

14.6.1 Verify that the test selector switch is set to


CONTROL TEST. Press the START push-but-
ton, and the CROWD BRAKE RELEASE but-
ton.

14.6.2 With the reference in the full negative (–)


(retract) position, use an oscilloscope to check
the firing pulse sequence of the retract con-
verter, Figure 14.6.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 35 TEST PROCEDURE
Electrotorque Plus®

Figure 14.6 Firing Pulse Sequence Oscilloscope Recording

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 36 CAT312.fm
Electrotorque Plus®

14.8 CURRENT FEEDBACK, CROWD 14.9 ARMATURE CURRENT RESPONSE,


CROWD
14.8.1 With the reference close to fully positive, check
that the current feedback signal at the AFM 14.9.1 Connect a strip chart or memory recorder (Ch.
connector P11- terminal 10 to terminal 8 (12251 1 ) across the crowd current feedback (IAFB)
to 01021C) is positive. This signal will be very test jacks.
small, 0.1V or less so use care in reading the
meter, or better still, use a strip chart recorder 14.9.2 Press the START push-button. Press the
to assure that the feedback polarity is correct. CROWD BRAKE RELEASE push-button.
Increase the crowd Operators Reference until
14.8.2 With the reference close to fully negative, the armature current ammeter reads 500A.
check that the current feedback signal at the
AFM connector P11- terminal 10 to terminal 8 14.9.3 On the GUI, press the CROWD CURRENT
(12251 to 01021C) remains positive. REGULATOR MODE touch button then press
the CROWD STEP REFERENCE touch but-
14.8.3 Reduce the reference to 0V. Press the STOP ton. The PLC will cause the AFM to pulse the
push-button. output current for a 10 sec. period. During this
period, record the IAFB output, and compare
14.8.4 Remove the series armature resistor. the recording to Figure 14.9. Overshoots or
undershoots should not be present.

14.9.4 Press the CROWD CURRENT REGULATOR


MODE touch button to disable.

14.9.5 Press the STOP push-button.

Figure 14.9 Crowd IAFB Chart Recording

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 37 TEST PROCEDURE
Electrotorque Plus®

14.10 STALL CURRENT, CROWD 14.10.11 Verify that values recorded in 14.10.7, agree
with the I-A3 level shown in the Specified Elec-
14.10.1 Use the drive keypad to go to the DRIVE trical Data sheet. Press the CROWD BRAKE
ANALOG sub-menu. Enter the sub-menu using SET push-button.
the right arrow key , then go to parameter
A004: I ARM AMP. 14.10.12 After the commutators have been allowed to
cool for at least one full minute, again, Press the
14.10.2 Connect a digital voltmeter across the crowd CROWD BRAKE RELEASE push-button and
current feedback (IAFB) test jacks. increase the crowd reference to full positive
(crowd).
14.10.3 Calculate the dc voltage to be expected across
the IAFB test jack resistor: 14.10.13 Check that the analog armature current
panel meter also reads the stall level +/–50A.
Istall / 300 = Vtest jack
14.10.14 Press the CROWD BRAKE SET push-but-
Example: ton. Reduce the crowd reference to 0 VDC.

1650A / 300 = 5.5 VDC 14.11 STALL CURRENT, PROPEL (CROWD)

14.10.4 Set the meter selector switch to monitor the 14.11.1 Calculate the dc voltage to be expected across
crowd motion parameters. the crowd IAFB test jack resistor when in the
propel mode:
14.10.5 Set the crowd reference potentiometer to 0
VDC. Press the START push-button. Istall / 300 = Vtest jack

Example:

The motors should not be run at maxi- 1450A / 300 = 4.8 VDC
mum stall current for more than 5 sec-
onds at a time. Longer periods will 14.11.2 Press the PROPEL button.
cause localized commutator heating.

14.10.6 Press the CROWD BRAKE RELEASE push-


button. The motors should not be run at maxi-
mum stall current for more than 5 sec-
14.10.7 Increase the crowd reference to full positive onds at a time. Longer periods will
(crowd). Check the current value shown on the cause localized commutator heating.
drive LCD Display. Record the voltage seen
across the IAFB test jacks. 14.11.3 Increase the crowd reference to full positive
(forward). Check the current value shown on
14.10.8 Press the CROWD BRAKE SET push-button. the drive LCD display. Record the voltage seen
across the IAFB test jacks.
14.10.9 Verify that values recorded in 14.10.7, agree
with the I-A2 level shown in the Specified Elec- 14.11.4 Press the HOIST/CROWD button.
trical Data sheet.
14.11.5 Verify that values recorded in 14.11.3, agree
14.10.10 After the commutators have been allowed to with the I-A2 level shown in the Specified Elec-
cool for at least one full minute, again, Press the trical Data sheet.
CROWD BRAKE RELEASE push-button and
increase the crowd reference to full negative 14.11.6 After the commutators have been allowed to
(retract). cool for at least one full minute, again, press the
PROPEL push-button and increase the crowd
reference to full negative (reverse). Check the

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 38 CAT312.fm
Electrotorque Plus®

current value shown on the drive LCD Display. 14.14 DIVERTER CIRCUIT CHECKS.
Record the voltage seen across the IAFB test
jacks. 14.14.1 Check that the relay and control supply cir-
cuit breakers are closed.
14.11.7 Press the HOIST/CROWD button.
14.14.2 Set the test selector switch to CONTROL
14.11.8 Verify that values recorded in 14.11.6, agree TEST.
with the I-A2 level shown in the Specified Elec-
trical Data sheet. 14.14.3 Connect a voltmeter to (TB1-1) on the crowd
diverter control module and check that the sup-
14.11.9 Press the STOP push-button. Reduce the ply voltage is +28VDC.
crowd reference to 0 VDC.
14.14.4 Press the START button.
14.12 VOLTAGE CONTROL - RUN MODE,
CROWD 14.14.5 Check that the READY light on the diverter
module is ON.
14.12.1 Set the test selector switch to RUN.
14.14.6 Check that the DE-BLOCK LED on the AFM
14.12.2 Deactivate the RPC shutdown by forcing the is on.
RPC circuit breaker inputs, off. (Alternative:
Disconnect the RPC circuit breaker interlock 14.14.7 Check the gate Block Circuit by shorting TB2-
input to the PLC.) 10 to TB2-9 on the diverter module.

14.12.3 Close the crowd field circuit breaker. 14.14.8 The DE-BLOCK LED on the AFM should not
be illuminated.
14.12.4 With the reference set to 0 VDC, press the
START button. 14.14.9 Press STOP button. Remove the short on the
diverter module.
14.12.5 Press the CROWD BRAKE RELEASE push-
button and check that the armature current is 14.15 DIVERTER CURRENT SENSOR
approximately 0 A. CHECKS, CROWD

14.12.6 Check that the motors can be controlled with 14.15.1 Connect a digital voltmeter to TP2 (–) and
the reference by accelerating, decelerating and TP3 (+) on the crowd diverter control module.
changing direction. Do not exceed 50% of full
speed. 14.15.2 Set the test selector switch to ARMATURE
TEST.
14.12.7 Set the crowd brakes. Press the STOP push-
button. 14.15.3 Press START button, press CROWD BRAKE
RELEASE button and check that the meter
14.13 FUSE FAULT DETECTION, CROWD reads at full crowd:

14.13.1 Remove a fuse monitor lead from the crowd Volts = Iarmstall/300 (+/–0.5VDC)
armature converter.
14.15.4 Record this in the test data sheet.
14.13.2 Press the START button.
14.15.5 Press STOP button. Disconnect the DVM.
14.13.3 Check that the machine shuts down and that
a crowd fuse fault is indicated.

14.13.4 Replace the fuse lead.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 39 TEST PROCEDURE
Electrotorque Plus®

14.16 DIVERTER CAPACITOR CHECKS, 14.17.5 Press the START button. Press the CROWD
CROWD BRAKE RELEASE button.

14.16.1 Reconnect the wire to the capacitor charging 14.17.6 Slowly increase the crowd reference to the full
relay at the terminal board on the crowd crowd position.
diverter circuit panels in the converter cabinet
to activate the capacitor charging power supply. 14.17.7 Check that the machine shuts down when the
meter reads about 3.5VDC.

14.17.8 Check that the capacitor voltage on the crowd


converter bridge drops instantly to approxi-
Use extreme caution when making volt-
mately 0 volts.
age measurements in this section of the
test procedure. Voltages of approxi-
14.17.9 Press the STOP button.
mately 1300V will be measured.
14.17.10 Adjust the current trip for normal operation.
14.16.2 Connect a digital voltmeter (1kV range) across
the crowd diverter capacitor for the forward
14.17.11 Reconnect the meter to TP1(+) and TP2(–) on
bridge.
the control module.
14.16.3 Manually depress the crowd capacitor charg-
14.17.12 Readjust the current trip adjust potentiome-
ing relay armature to close its contacts.
ter to its maximum clockwise position.
14.16.4 The voltage across the diverter capacitor
14.17.13 Press the START push-button. Press the
should begin to climb at the capacitor charges.
CROWD BRAKE RELEASE button.
Ultimately this voltage should be about 1300
VDC, but to avoid overvoltage on the DVM, we
14.17.14 Stall the crowd and turn down the current
will stop charging (release the relay armature)
trip potentiometer until the module trips. Do
at about 900 VDC. Check schematics for polar-
not stall motor for more than 5 seconds.
ity, and verify that the charging polarity is cor-
rect.
14.17.15 Check and read voltage at TP1-TP2.
14.16.5 When you release the charging relay, the volt-
14.17.16 Readjust level as follows.
age across the diverter capacitor must decay to
less than 50 VDC in less than 30 Sec.
Volts = (VTP1-VTP2) x 1.4
14.16.6 Repeat these tests for the reverse bridge
crowd diverter capacitor. Where:

14.17 CHECK DIVERTER CIRCUIT OPERA- VTP1 to VTP2 is from 14.17.15


TION, CROWD
14.18 OPERATE FROM THE OPERATOR’S
14.17.1 Connect a digital voltmeter to TP1(+) and COOP, CROWD
TP2(–) on the diverter control module.
14.18.1 Remove the reference/push-button unit.
14.17.2 Adjust the current trip adjust potentiometer Reconnect the PLC/coop cables.
so that the meter reads +2.1VDC.
14.18.2 REPEAT THE AUTOCAL PROCEDURE
14.17.3 Set the test selector switch to ARMATURE (Operator’s reference Calibration)
TEST.
14.18.3 On the GUI, go to the AFM TEST SCREEN.
14.17.4 Reconnect the meter to TP3(+) and TP2(–) on
the diverter control module. 14.18.4 Verify that the test selector switch is set to
CONTROL TEST. Press the START push-but-

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 40 CAT312.fm
Electrotorque Plus®

ton, and the CROWD BRAKE RELEASE but- 14.19 VOLTAGE RESPONSE, CROWD. (With
ton. crowd Ropes and Dipper attached)

14.18.5 Move the crowd controller potentiometer to 14.19.1 Connect a chart recorder to record across the
full positive (+). On the GUI, press the AUTO- crowd armature voltage feedback (VAFB) test
CAL CROWD ON touch button. jacks (Ch. 1), and the crowd armature current
feedback (IAFB) test jacks (Ch. 2).
14.18.6 After the GUI touch button turns green for a
few moments, press the AUTOCAL CROWD 14.19.2 Press the START push-button. Press the
OFF touch button. CROWD BRAKE RELEASE button.

14.18.7 When the touch button turns red, move the 14.19.3 Check that the armature voltage of each
crowd controller potentiometer to full negative motor is correct for both full crowd and full
(–). lower directions as spelled out in the Specified
Electrical Data sheet.
14.18.8 On the GUI, press the AUTOCAL CROWD
ON touch button. After the GUI touch button • 14.19.3.1 If the terminal voltage is significantly
turns green for a few moments, press the AUTO- lower than the voltage read at the AFM (A012
CAL CROWD OFF touch button. ARM VOLTS) then change the X003 parameter
from 100 to something less. For example: If the
14.18.9 Confirm that the reference signals are prop- measured terminal voltage is 500V and A012
erly calibrated by checking that the ADJUSTED reads 550V then change X003 from 100 to 91 (500/
REFERENCE at A066 is +100% with the refer- 550 x 100 = 91). Changes made to X parameters
ence full positive, and –100% with the reference are activated immediately after pressing the S key.
full negative. Use the drive keypad to go to the Note: X003 is used for left propel.
OPERATE sub-menu. Enter the sub-menu
using the right arrow key. Arrow up to reach 14.19.4 Operate the crowd by alternately applying full
the BLOCKS ANALOG sub-menu, and enter it positive and full negative reference and compare
with the right arrow key. Arrow up to A066. the recordings of VAFB and IAFB with Figure
14.19.4.
14.18.10 The crowd AUTOCAL procedure is complete.
Press the STOP push-button. 14.19.5 Voltage response recordings will require two
participants; an operator in the operator’s coop,
Press the drive S key twice to exit the sub-menus. and a technician in the control room. Have the
operator place the dipper handle (sticks) at a
14.18.11 Set the test selector switch to RUN. Start position that is about 90 degrees to the boom
the machine and release the crowd brakes. with the handle fully extended. The operator
should then very slowly retract the empty dip-
14.18.12 Check that full control of the crowd motion is per at a constant speed.
obtained by the operator’s controller.
14.19.6 As the dipper is slowly retracting, press the
14.18.13 Check that the crowd motion runs in the CROWD STEP REFERENCE touch button on
proper direction in relation to the controller the GUI. The PLC will pulse the output voltage
position. If the motor rotation is wrong, check for a 10 second time period. During this period,
that the reference is of the proper polarity. record crowd VAFB and IAFB signals and com-
pare them with Figure 14.19.6. The VAFB sig-
The motor rotation may be reversed by reversing the nal should have minimum response time
motor field connections. without overshoot. At any time during this pro-
cedure, the operator has the ability to override
the step reference, should safety require it. In
case satisfactory recordings are not obtained on
the first run, you can instruct the operator to
quickly crowd the dipper before it reaches the

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 41 TEST PROCEDURE
Electrotorque Plus®

Figure 14.19.4 Crowd VAFB and IAFB Chart Recording

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 42 CAT312.fm
Electrotorque Plus®

Figure 14.19.6 Crowd VAFB and IAFB Chart Recording

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 43 TEST PROCEDURE
Electrotorque Plus®

retract limit, and then begin retracting it again 14.22 DIVERTER CIRCUIT OPERATION
at a slow and steady rate.
14.22.1 If nuisance tripping occurs during normal
14.19.7 Set the dipper on the ground and press the operation, use the procedure of 14.17.11 and
STOP push-button. increase the trip setting by increments of 0.1V
until nuisance tripping does not occur. (It should
14.20 VOLTAGE RESPONSE, PROPEL. not be necessary to increase this setting more
than 0.5VDC. )
14.20.1 Connect channel 1 of the chart recorder across
Propel #1 armature voltage feedback (Hoist 14.23 THIS COMPLETES TESTING OF THE
VAFB) test jacks, and channel 2 to Propel #2 CROWD ARMATURE CONTROL
(Crowd VAFB).
14.23.1 Press the STOP push-button.
Operate the machine from the operator’s seat.
14.23.2 Remove all PLC forces.
14.20.2 Press the START push-button. Press the
PROPEL transfer button. 14.23.3 Open the field circuit breakers.

14.20.3 Record VAFB while alternately applying full 14.23.4 Enable OPEN SCR TEST. At the crowd AFM
positive and full negative reference and compare keypad, change Y058 from D087 ZERO BIT to
the recordings with Figure 14.20.3. D149 TEST ARM. Reset drive.

14.20.4 Press the STOP push-button.

14.21 DIVERTER VAFB SIGNAL CHECKS,


CROWD

14.21.1 Connect a digital voltmeter from TB1-4 to


TB1-5 on the crowd diverter control module.

14.21.2 With the test selector switch set to RUN, press


START button and CROWD BRAKE RELEASE
button.

14.21.3 Operate the crowd motion, and check that the


voltage is –8.9V"1V at full speed in the crowd
direction and +8.9V"1V at full speed in the lower
direction.

14.21.4 Set the dipper on the ground and press STOP


button.

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 44 CAT312.fm
Electrotorque Plus®

Figure 14.20.3 Propel VAFB and IAFB Chart Recording

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 45 TEST PROCEDURE
Return to Index
Electrotorque Plus®

15. SWING ARMATURE CONTROL 15.2.2 Using a DVM, check that the following voltages
are present at the swing armature AFM:
15.1 TEST PREPARATION A) 120VAC Control Power at TB1-1 to TB1-2.
15.1.1 Set the test selector switch to CONTROL TEST. B) 230VAC, 3ph, synchronizing voltage at P11-1 to
P11-16 to P11-3.
15.1.2 Open the circuit breakers on the RPC cabinet. C) 42VDC (approx. 50VDC no load) gate voltage at
Open the constant voltage module supply circuit P11-13 (+) to P11-14 (–).
breaker (CVMSB), and the control supply
breaker (CSB).
15.3 15.3 AFM SOFTWARE
15.1.3 Connect a 12.5 ohm current limiting resistor in
series with the swing motor armature. 15.3.1 When the swing AFM is properly powered, its
LCD Display should read:
15.1.4 Install a reference/push-button unit. See Fig-
ure 2.2.2 in Appendix B. P&H Electrotorque-Plus
Armature Control
15.1.5 Check the ID on the flash PROM (U8), and on
the EEPROM (U10) to make sure that they
agree with the shovel documentation. This indicates that this AFM most likely has the cor-
rect firmware installed.
15.1.6 Check for open or shorted thyristor firing pulse
cables by measuring between the bridge inter- 15.3.2 Use the drive keypad to go to the ACCESS
face connector pins. A reading of 50 ohms is to CODES sub-menu. Enter the sub-menu using
be expected between the following pins: the right arrow key and go to E007 SWR VER-
SION. Confirm that the displayed software part
P9-1 to P9-2, P9-3 to P9-4, number agrees with the shovel documentation.
P9-5 to P9-6, P9-9 to P9-10,
15.4 AFM TESTING
P9-11 to P9-12, P9-13 to P9-14,
P9-15 to P9-16, P9-17 to P9-18, 15.4.1 Open the Electrotorque-Plus top door to
expose the microprocessor board A1 on your
P9-19 to P9-20, P9-23 to P9-24, right side. Attach a digital voltmeter across TP1
P9-25 to P9-26, P9-27 to P9-28 (ACOM) and TP2 (VREF) which are located on
the bottom left side of the microprocessor board.
15.2 SUPPLY VOLTAGES Record the measured voltage (approx. –7.000
VDC) as a negative number.
15.2.1 Close the following circuit breakers:
15.4.2 Use the drive keypad to go to the DRIVE CALI-
• 120V Main Breaker (MB) BRATE sub-menu. Enter the sub-menu using
• Constant Voltage Supply Breaker (CVSB) the right arrow key and set the following
parameter:
• DC Contactor Supply (DCSB)
• 230V Supply Breaker (SB) X000: I/O V-REF = – VDC (value measured in
15.4.1 )
• Control Supply Breaker (CSB)
• Relay Supply Circuit Breaker (RSCB) Press the S key twice to save the value and exit the
• Constant Voltage Module Supply Breaker edit mode.
(CVMSB)
15.4.3 Reset the drive by cycling the drive power.
• Synchronizing Supply Breaker (SSB)
15.4.4 Verify that the EMERG STOP OK and DRIVE
READY LED’s are illuminated.

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 46 CAT312.fm
Electrotorque Plus®

15.5 AUTOCAL PROCEDURE (Operator’s refer- 15.6.3 Place the reference in the full positive (+)
ence Calibration) (swing right) position, and check the firing pulse
sequence of the swing right converter, Figure
15.5.1 On the GUI, go to the AFM TEST SCREEN. 15.6.

15.5.2 Verify that the test selector switch is set to 15.6.4 Press the STOP push-button.
CONTROL TEST. Press the START push-but-
ton, and the SWING BRAKE RELEASE button. 15.7 VOLTAGE CONTROL, SWING

15.5.3 Turn the swing reference potentiometer to full 15.7.1 Disable OPEN SCR TEST. At the Swing AFM
positive (+). On the GUI, press the AUTOCAL keypad, change Y058 from D149 TEST ARM to
SWING ON touch button. D087 ZERO BIT. Reset drive.

15.5.4 After the GUI touch button turns green for a 15.7.2 Connect a digital voltmeter (1kV range) across
few moments, press the AUTOCAL SWING OFF the series armature resistor.
touch button.
15.7.3 Remove the relay from the differential voltage
15.5.5 When the touch button turns red, turn the module (DVAS) to prevent shutdown due to
swing reference potentiometer to full negative unbalanced armature voltage.
(–).
15.7.4 Set the test selector switch to ARMATURE
15.5.6 On the GUI, press the AUTOCAL SWING ON TEST, and close the high voltage disconnect
touch button. After the GUI touch button turns switch.
green for a few moments, press the AUTOCAL
SWING OFF touch button. 15.7.5 Set the reference to 0V.

15.5.7 Confirm that the reference signals are properly 15.7.6 Press the START push-button.
calibrated by checking that the ADJUSTED
REFERENCE at A066 is +100% with the refer- 15.7.7 Check that the dc voltage across the series
ence full positive, and –100% with the reference armature resistor is approximately 0VDC. (A
full negative. Use the drive keypad to go to the higher voltage would indicate the possibility of a
OPERATE sub-menu. Enter the sub-menu phasing error on the main transformer second-
using the right arrow key. Arrow up to reach ary, or on the synchronizing supply voltage.)
the BLOCKS ANALOG sub-menu, and enter it
with the right arrow key. Arrow up to A066. 15.7.8 Press the SWING BRAKE RELEASE push-but-
ton. Slowly, increase the swing reference in the
15.5.8 The swing AUTOCAL procedure is complete. positive direction.
Press the STOP push-button.
The voltage across the feedback resistor should
Press the drive S key twice to exit the sub-menus. increase directly in proportion to the reference.

15.6 THYRISTOR PULSE SEQUENCE 15.7.9 Slowly, Increase the swing reference in the neg-
ative direction.
15.6.1 Verify that the test selector switch is set to
CONTROL TEST. Press the START push-but- The voltage across the feedback resistor should
ton, and the SWING BRAKE RELEASE button. increase directly in proportion to the reference, and
should have changed polarity.
15.6.2 With the reference in the full negative (–)
(swing left) position, use an oscilloscope to check
the firing pulse sequence of the swing left con-
verter, Figure 15.6.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 47 TEST PROCEDURE
Electrotorque Plus®

Figure 15.6 Firing Pulse Sequence Oscilloscope Recording

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 48 CAT312.fm
Electrotorque Plus®

15.8 CURRENT FEEDBACK, SWING 15.10.3 Calculate the dc voltage to be expected across
the IAFB test jack resistor:
15.8.1 With the reference close to fully positive, check
that the current feedback signal at the AFM Istall / 300 = Vtest jack
connector P11 - terminal 10 to terminal 8 (10251
to 01021C) is positive. This signal will be very Example:
small, 0.1V or less so use care in reading the
meter, or better still, use a strip chart recorder 2250A / 300 = 7.5 VDC
to assure that the feedback polarity is correct.
15.10.4 Set the meter selector switch to monitor the
15.8.2 With the reference close to fully negative, check swing motion parameters.
that the current feedback signal at the AFM
connector P11 - terminal 10 to terminal 8 (10251 15.10.5 Set the swing reference potentiometer to 0
to 01021C) remains positive. VDC. Press the START push-button.

15.8.3 Reduce the reference to 0V. Press the STOP


push-button.

15.8.4 Remove the series armature resistor. The motors should not be run at maxi-
mum stall current for more than 5 sec-
onds at a time. Longer periods will
15.9 ARMATURE CURRENT RESPONSE, cause localized commutator heating.
SWING
15.10.6 Press the SWING BRAKE RELEASE push-
15.9.1 Connect a strip chart or memory recorder button.
(Ch. 1 ) across the Swing current feedback
(IAFB) test jacks. 15.10.7 Increase the swing reference to full positive
(swing right). Check the current value shown
15.9.2 Press the START push-button. Press the on the drive LCD Display. Record the voltage
SWING BRAKE RELEASE push-button. seen across the IAFB test jacks.
Increase the swing operator’s reference until the
armature current ammeter reads 500A. 15.10.8 Press the SWING BRAKE SET push-button.

15.9.3 On the GUI, press the SWING STEP REFER- 15.10.9 Verify that values recorded in 15.10.7, agree
ENCE touch button. The PLC will cause the with the I-A2 level shown in the Specified Elec-
AFM to pulse the output current for a 10 sec. trical Data sheet.
period. During this period, record the IAFB out-
put, and compare the recording to Figure 15.9. 15.10.10 After the commutators have been allowed to
Overshoots or undershoots should not be cool for at least one full minute, again, Press the
present. SWING BRAKE RELEASE push-button and
increase the swing reference to full negative
15.9.4 Press the STOP push-button. (SW. LEFT).

15.10 STALL CURRENT, SWING 15.10.11 Verify that values recorded in 15.10.7, agree
with the I-A3 level shown in the Specified Elec-
15.10.1 Use the drive keypad to go to the DRIVE trical Data sheet. Press the SWING BRAKE
ANALOG sub-menu. Enter the sub-menu using SET push-button.
the right arrow key, then go to parameter A004:
I ARM AMP. 15.10.12 After the commutators have been allowed to
cool for at least one full minute, again, press the
15.10.2 Connect a digital voltmeter across the swing SWING BRAKE RELEASE push-button and
current feedback (IAFB) test jacks. increase the swing reference to full positive
(swing right).

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 49 TEST PROCEDURE
Electrotorque Plus®

Figure 15.9 Swing VAFB and IAFB Chart Recording

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 50 CAT312.fm
Electrotorque Plus®

15.10.13 Check that the analog armature current 15.13.3 Connect a voltmeter to (TB1-1) on the swing
panel meter also reads the stall level +/–50A. diverter control module and check that the sup-
ply voltage is +28VDC.
15.10.14 Press the SWING BRAKE SET push-button.
Reduce the swing reference to 0 VDC. 15.13.4 Press the START button.

15.11 VOLTAGE CONTROL - RUN MODE, 15.13.5 Check that the READY light on the diverter
SWING module is on.

15.11.1 Set the test selector switch to RUN. 15.13.6 Check that the DE-BLOCK LED on the AFM
is on.
15.11.2 Deactivate the RPC shutdown by forcing off
the RPC circuit breaker inputs. 15.13.7 Check the gate block circuit by shorting TB2-
10 to TB2-9 on the diverter module.
(Alternative: Disconnect the RPC circuit breaker inter-
lock input to the PLC.) 15.13.8 The DE-BLOCK LED on the AFM should not
be illuminated.
15.11.3 Close the swing field circuit breaker.
15.13.9 Press STOP button. Remove the short on the
15.11.4 With the reference set to 0 VDC, press the diverter module.
START button.
15.14 DIVERTER CURRENT SENSOR
15.11.5 Press the SWING BRAKE RELEASE push- CHECKS, SWING
button and check that the armature current is
approximately 0. 15.14.1 Connect a digital voltmeter to TP2 (–) and
TP3 (+) on the swing diverter control module.
15.11.6 Check that the motors can be controlled with
the reference by accelerating, decelerating and 15.14.2 Set the test selector switch to ARMATURE
changing direction. Do not exceed 50% of full TEST.
speed.
15.14.3 Press START button, press SWING BRAKE
15.11.7 Set the swing brakes. Press the STOP push- RELEASE button and check that the meter
button. reads at full swing:

15.12 FUSE FAULT DETECTION, SWING Volts = Iarmstall/300 (+/–0.5VDC)

15.12.1 Remove a fuse monitor lead from the swing 15.14.4 Record this in the test data sheet.
armature converter.
15.14.5 Press the STOP button. Disconnect the DVM.
15.12.2 Press the START button.
15.15 DIVERTER CAPACITOR CHECKS,
15.12.3 Check that the machine shuts down and that SWING
a swing fuse fault is indicated.
15.15.1 Reconnect the wire to the capacitor charging
15.12.4 Replace the fuse lead. relay at the terminal board on the swing
diverter circuit panels in the converter cabinet
15.13 DIVERTER CIRCUIT CHECKS. to activate the capacitor charging power supply.

15.13.1 Check that the relay and control supply cir-


cuit breakers are closed.
Use extreme caution when making volt-
15.13.2 Set the test selector switch to CONTROL age measurements in this section of the
TEST.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 51 TEST PROCEDURE
Electrotorque Plus®

test procedure. Voltages of approxi- 15.16.9 Press the STOP button.


mately 1300V will be measured.
15.16.10 Adjust the current trip for normal operation.
15.15.2 Connect a digital voltmeter (1kV range)
across the swing diverter capacitor for the for- 15.16.11 Reconnect the meter to TP1(+) and TP2(–) on
ward bridge. the control module.

15.15.3 Manually depress the swing capacitor charg- 15.16.12 Readjust the current trip adjust potentiome-
ing relay armature to close its contacts. ter to its maximum clockwise position.

15.15.4 The voltage across the diverter capacitor 15.16.13 Press the START push-button. Press the
should begin to climb at the capacitor charges. SWING BRAKE RELEASE button.
Ultimately this voltage should be about 1300
VDC, but to avoid overvoltage on the DVM, we 15.16.14 Stall the swing and turn down the current
will stop charging (release the relay armature) trip potentiometer until the module trips. Do
at about 900 VDC. Check schematics for polar- not stall motor for more than 5 seconds.
ity, and verify that the charging polarity is cor-
rect. 15.16.15 Check and read voltage at TP1-TP2.

15.15.5 When you release the charging relay, the volt- 15.16.16 Readjust level as follows.
age across the diverter capacitor must decay to
less than 50 VDC in less than 30 sec. Volts = (VTP1-VTP2) x 1.4
15.15.6 Repeat these tests for the reverse bridge Where:
swing diverter capacitor.
VTP1 to VTP2 is from 15.16.15
15.16 CHECK DIVERTER CIRCUIT OPERA-
TION, SWING 15.17 OPERATE FROM THE OPERATOR’S
COOP, SWING
15.16.1 Connect a digital voltmeter to TP1(+) and
TP2(–) on the diverter control module. 15.17.1 Remove the reference/push-button unit.
Reconnect the PLC/coop cables.
15.16.2 Adjust the current trip adjust potentiometer
so that the meter reads +2.1VDC. 15.17.2 REPEAT THE AUTOCAL PROCEDURE
(Operator’s Reference Calibration)
15.16.3 Set the test selector switch to ARMATURE
TEST. 15.17.3 On the GUI, go to the AFM TEST SCREEN.
15.16.4 Reconnect the meter to TP3(+) and TP2(–) on 15.17.4 Verify that the test selector switch is set to
the diverter control module. CONTROL TEST. Press the START push-but-
ton, and the SWING BRAKE RELEASE button.
15.16.5 Press the START button. Press the SWING
BRAKE RELEASE button. 15.17.5 Move the swing controller potentiometer to
full positive (+). On the GUI, press the AUTO-
15.16.6 Slowly increase the swing reference to the full CAL SWING ON touch button.
swing right position.
15.17.6 After the GUI touch button turns green for a
15.16.7 Check that the machine shuts down when the few moments, press the AUTOCAL SWING OFF
meter reads about 3.5VDC. touch button.
15.16.8 Check that the capacitor voltage on the swing 15.17.7 When the touch button turns red, move the
converter bridge drops instantly to approxi- swing controller potentiometer to full negative
mately 0 volts. (–).

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 52 CAT312.fm
Electrotorque Plus®

15.17.8 On the GUI, press the AUTOCAL SWING ON from 100 to something less. For example: If the
touch button. After the GUI touch button turns measured terminal voltage is 500V and A012
green for a few moments, press the AUTOCAL reads 550V then change X003 from 100 to 91 (500/
SWING OFF touch button. 550 x 100 = 91). Changes made to X parameters
are activated immediately after pressing the S key.
15.17.9 Confirm that the reference signals are prop-
erly calibrated by checking that the ADJUSTED 15.18.4 Operate the swing by alternately applying full
REFERENCE at A066 is +100% with the refer- positive and full negative reference and compare
ence full positive, and –100% with the reference the recordings of VAFB and IAFB with 15.18.4.
full negative. Use the drive keypad to go to the
OPERATE sub-menu. Enter the sub-menu 15.18.5 Set the dipper on the ground and press the
using the right arrow key. Arrow up to reach STOP push-button.
the BLOCKS ANALOG sub-menu, and enter it
with the right arrow key. Arrow up to A066. 15.19 DIVERTER VAFB SIGNAL CHECKS,
SWING
15.17.10 The swing AUTOCAL procedure is complete.
Press the STOP push-button. Press the drive S 15.19.1 Connect a digital voltmeter from TB1-4 to
key twice to exit the sub-menus. TB1-5 on the swing diverter control module.

15.17.11 Set the test selector switch to RUN. START 15.19.2 With the test selector switch set to RUN, press
the machine and RELEASE the Swing brakes. START button and SWING BRAKE RELEASE
button.
15.17.12 Check that full control of the swing motion is
obtained by the operator’s controller. 15.19.3 Operate the swing motion, and check that the
voltage is –9.7V+/–1V at full speed in the swing
15.17.13 Check that the swing motion runs in the direction and +9.7V+/–1V at full speed in the
proper direction in relation to the controller lower direction.
position.
15.19.4 Set the dipper on the ground and press STOP
If the motor rotation is wrong, check that the reference button.
is of the proper polarity.

The motor rotation may be reversed by reversing the


15.20 DIVERTER CIRCUIT OPERATION
motor field connections.
15.20.1 If nuisance tripping occurs during normal
operation, use the procedure of 15.16.11 and
15.18 VOLTAGE RESPONSE, SWING increase the trip setting by increments of 0.1V
until nuisance tripping does not occur. (It should
15.18.1 Connect a chart recorder to record across the not be necessary to increase this setting more
swing armature voltage feedback (VAFB) test than 0.5VDC. )
jacks (Ch. 1), and the swing armature current
feedback (IAFB) test jacks (Ch. 2).
15.21 THIS COMPLETES TESTING OF THE
SWING ARMATURE CONTROL
15.18.2 Press the START push-button. Press the
SWING BRAKE RELEASE button.
15.21.1 Press the STOP push-button.
15.18.3 Check that the armature voltage of each
15.21.2 Remove all PLC forces.
motor is correct for both full swing right and full
swing left directions as spelled out in the Speci-
15.21.3 Open the field circuit breakers.
fied Electrical Data sheet.

• 15.18.3.1 If the terminal voltage is significantly 15.21.4 Enable OPEN SCR TEST. At the Swing AFM
lower than the voltage read at the AFM (A012 keypad, change Y058 from D087 ZERO BIT to
ARM VOLTS) then change the X003 parameter D149 TEST ARM. Reset drive.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 53 TEST PROCEDURE
Electrotorque Plus®

Figure 15.18.4 Swing VAFB and IAFB Chart Recording

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 54 CAT312.fm
Return to Index
Electrotorque Plus®

16. REACTIVE POWER COMPENSATOR, 16.1.6 Check for open or shorted thyristor firing pulse
cables by measuring between the bridge inter-
(RPC). face connector pins. A reading of 50 ohms is to
be expected between the following pins:
The RPC utilizes banks of tuned capacitors/reactors,
which are automatically switched in and out of the P9-1 to P9-2, P9-3 to P9-4,
600V power circuit. The number of banks used,
depends on the individual shovel model served. A P9-5 to P9-6, P9-9 to P9-10,
combination of 1/2 and full banks are used for compen- P9-11 to P9-12, P9-13 to P9-14,
sation. As can be seen in the following chart, the 1/2
bank is brought in to add compensation of smaller P9-15 to P9-16, P9-17 to P9-18,
increments between the full banks. P9-19 to P9-20, P9-23 to P9-24,
P9-25 to P9-26, P9-27 to P9-28

16.2 SUPPLY VOLTAGES


STEP # 1 2 3 4 5 6 7

1/2 BANK | O | O | O | 16.2.1 Close the following circuit breakers:

BANK 1 O | | | | | | • 120V Main Breaker (MB)


• Constant Voltage Supply Breaker (CVSB)
BANK 2 O O O | | | |
• DC Contactor Supply (DCSB)
BANK 3 O O O O O | |
• 230V Supply Breaker (SB)
TOTAL # OF 1/2 1 1 1/2 2 2 1/2 3 3 1/2
BANKS ON • Control Supply Breaker (CSB)
• Relay Supply Circuit Breaker (RSCB)
| = Bank is ON O = Bank is OFF • Constant Voltage Module Supply Breaker
(CVMSB)
16.1 TEST PREPARATION • Synchronizing Supply Breaker (SSB)

16.1.1 Set the test selector switch to CONTROL TEST. 16.2.2 Using a DVM, check that the following voltages
are present at the RPC AFM:
16.1.2 Open the constant voltage module supply cir-
cuit breaker (CVMSB), and the control supply A) 120VAC control power at TB1-1 to TB1-2.
breaker (CSB).
B) 230VAC, 3ph, synchronizing voltage at P11-1 to
16.1.3 Open the circuit breakers on the cabinet for the P11-16 to P11-3.
Reactive Power Compensator.
C) 42VDC (approx. 50VDC no load) gate voltage at
16.1.4 Install a reference/push-button unit. See Figure P11-13 (+) to P11-14 (–).
2.2.2 in Appendix B.

16.1.5 Check the ID on the flash PROM (U8), and on


the EEPROM (U10) to make sure that they
agree with the shovel documentation.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 55 TEST PROCEDURE
Electrotorque Plus®

16.3 AFM SOFTWARE 16.5.2 Set the test selector switch to CONTROL TEST.
Press the START push-button. On the GUI,
16.3.1 When the RPC AFM is properly powered, its press the RPC MANUAL MODE touch button.
LCD Display should read:
16.5.3 Slowly increase the manual kVAR reference
until the first green LED (STEP 1) on the AFM
P&H Electrotorque-Plus illuminates. The voltmeter reading the kVAR
RPC Control reference should now read V-LEV1 as docu-
mented in the Specified Electrical Data sheet.
This indicates that this AFM most likely has the cor-
16.5.4 Increase the manual kVAR reference until each
rect firmware installed.
successive LED on the AFM illuminates. As
each LED first turns on, the kVAR reference
16.3.2 Use the drive keypad to go to the ACCESS
should read the appropriate V-LEV as docu-
CODES sub-menu. Enter the sub-menu using
mented in the Specified Electrical Data sheet.
the right arrow key and go to E007 SWR VER-
SION. Confirm that the displayed software part
16.5.5 Reduce the manual kVAR reference to 0VDC.
number agrees with the shovel documentation.

16.6 RPC FIRING CHECKS


16.4 AFM TESTING
16.6.1 Slowly increase the manual kVAR reference
16.4.1 Open the Electrotorque-Plus top door to until the first green LED (STEP 1) on the AFM
expose the microprocessor board A1 on your illuminates. Verify that the red LED’s for the
right side. Attach a digital voltmeter across TP1 1/2 BANK pulse transformers are illuminated
(ACOM) to TP2 (VREF) which are located on the (dimly).
bottom left side of the microprocessor board.
Record the measured voltage (approx. –7.000 16.6.2 Connect an oscilloscope to the gate (G) and
VDC) as a negative number. cathode (K) of each pulse transformer. Firing
pulses should be similar to that shown in Figure
16.4.2 Use the drive keypad to go to the DRIVE CALI- 16.6.2.
BRATE sub-menu. Enter the sub-menu using
the right arrow key and set the following param-
eter:

X000: I/O V-REF = – VDC (value measured in


16.4.1 )

Press the S key twice to save the value and exit the
edit mode.

16.4.3 Reset the drive by cycling the drive power. Figure 16.6.2 Thyristor Pulse Waveform

16.4.4 Verify that the EMERG STOP OK and DRIVE 16.6.3 As required, continue increasing the manual
READY LED’s are illuminated. kVAR reference until STEP 2 LED on the AFM
illuminates. Verify that the red LED’s for the
BANK 1 pulse transformers are illuminated.
16.5 LEVEL DETECTOR CHECKS
Check firing pulses.
16.5.1 Connect a digital voltmeter to the manual
Continue to the next bank by increasing the reference
kVAR reference input to the RPC AFM at con-
to STEP 4 for BANK 2, and to STEP 6 for BANK 3.
nector P9-16 (+) to P9-17 (–). Set the Manual
Check firing pulses after each bank.
kVAR potentiometer to 0.00.

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 56 CAT312.fm
Electrotorque Plus®

16.6.4 Reduce the manual kVAR reference to 0VDC. 16.7.2 Connect each leg of the capacitor test unit (Fig-
On the GUI, press the RPC MANUAL MODE ure 2.2.5 in Appendix B) across the open con-
OFF touch button. tacts of the breaker on the 1/2 bank. Figure
16.7.2 shows the typical connections.
16.7 RPC OPERATION WITH CAPACITOR
TEST UNIT. 16.7.3 Short circuit each capacitor bank on this step
with jumper wires. (The reactors need not be
16.7.1 Verify that the manual kVAR reference is set to shorted for this test.)
0VDC. Verify that all of the RPC circuit break-
ers are open on the RPC cabinets.

Figure 16.7.2 Capacitor Test Typical Connections

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 57 TEST PROCEDURE
Electrotorque Plus®

16.7.4 Set the test selector switch to ARMATURE setpoint, and back with the kVAR reference
TEST. potentiometer. Compare the recording to Figure
16.7.13.
16.7.5 Connect a digital (dc setting) voltmeter (1kV
range) between terminals MS1 and RBC of the Check that the first half cycle has the same amplitude
capacitor unit to measure approximately as the subsequent cycles.
800VDC.
16.7.14 These tests should be performed on all three
resistors of the capacitor unit. The recorder
must be run at high speed for these tests. Chart
The recorder or oscilloscope being used paper can be saved by rapidly changing the ref-
should be isolated from its power sup- erence signal before starting the recorder.
ply through an isolation transformer
because of the high voltage to ground 16.7.15 Press the STOP button.
(approximately 1000V).
16.7.16 Connect each leg of the capacitor test unit
DO NOT TOUCH the instrument frames when power across the open contacts of the breaker on
is on the RPC. BANK 1. Repeat the tests of 16.7.1 through
16.7.15.
DO NOT TOUCH live parts when obtaining measure-
ments on the RPC equipment when power is on the 16.7.17 Connect the capacitor unit across the open
RPC. contacts of the breaker on BANK 2. Repeat the
tests of 16.7.1 through 16.7.15.
16.7.6 Press the START button.
16.7.18 Connect the capacitor unit across the open
16.7.7 Check that the voltmeter indicates approxi- contacts of the breaker on BANK 3. Repeat the
mately 800V with reference set at 0. tests of 16.7.1 through 16.7.15.

16.7.8 Connect voltmeter between terminals MS2 and 16.7.19 Remove the capacitor unit, jumper wires, and
RCC and check that voltage is approximately all test instruments.
800V.
16.8 TESTING RPC POWER CIRCUITS
16.7.9 Connect the voltmeter to MS3 and RAC, repeat
the above tests. 16.8.1 Check that the test selector switch is set to
ARMATURE TEST.
16.7.10 Press the STOP push-button.
16.8.2 Connect a recorder, using a voltage divider,
16.7.11 Connect a stripchart recorder across one of the across phase A of the 1/2 BANK to measure the
10 ohm resistors on the capacitor unit. The capacitor voltage (approximately 850V).
recorder should be isolated from its power sup-
ply through an isolation transformer, or be bat-
tery operated, because of the high voltage to
ground (approximately 1000V). The recorder or oscilloscope being used
should be battery powered or isolated
DO NOT TOUCH the frame of the recorder while from its ac power supply through an iso-
power is on the RPC. lation transformer because of the high
voltage to ground (approximately
16.7.12 Press the START push-button. 1000V).

16.7.13 Record the voltage across the resistor when DO NOT TOUCH the instrument frames when power
the output voltage from the manual kVAR refer- is on the RPC.
ence is changed rapidly from a setting just below
the switching setpoint to a setting just above the

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 58 CAT312.fm
Electrotorque Plus®

Figure 16.7.13 RPC Chart Recording

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 59 TEST PROCEDURE
Electrotorque Plus®

DO NOT TOUCH live parts when obtaining measure- !! OBSERVE WARNINGS !!


ments on the RPC equipment when power is on the
RPC. 16.8.15 As required, close the circuit breaker succes-
sively for BANK 2, and BANK 3, and open the
16.8.3 Close the RPC circuit breaker for the 1/2 BANK breaker for the previous bank.
only.
Repeat the tests of 16.8.5 through 16.8.12 for each
16.8.4 Start the recorder (5 sec/div). Press the phase of each bank.
START push-button.

16.8.5 Check that the voltage across the capacitors NOTICE


corresponds to the recording of Figure 16.8.5.
Check the schematics for polarity. Check that Do not energize more than one bank at a
overshoots at the start, do not exceed those time.
shown in Figure 16.8.5.
16.8.16 Press the STOP Push-button.
16.8.6 Using the following procedure, check the RPC
capacitor switching. 16.9 REACTIVE POWER MEASUREMENT

16.8.7 Increase the recorder speed to 100ms/div and These tests are made to check operation of the reactive
record the voltage across the capacitors when power measurement circuits.
the output voltage from the kVAR reference
potentiometer is changed rapidly from a setting 16.9.1 Open all RPC Circuit Breakers. Check that the
just below the switching setpoint to a setting test selector switch is set to ARMATURE TEST.
just above the setpoint, and back with the RPC Connect two digital voltmeters. One between
reference potentiometer. terminals 1 and 2 on the kVAR transducer to
measure its output voltage, VQ, and another to
16.8.8 Check that the capacitors have been switched measure the ac voltage (115V) between termi-
on by noting if an ac voltage appears across the nals 3 and 4, or 5 and 6 on the kVAR transducer.
terminals as shown in Figure 16.8.8.
16.9.2 Press the START push-button. Press the
16.8.9 Check that no overshoots occur when the capac- HOIST BRAKE RELEASE push-button.
itors are switched on or off.

16.8.10 Press the STOP push-button.

16.8.11 Connect the recorder across the capacitors of The motors should not be run at maxi-
phase B of the 1/2 BANK, and repeat the tests of mum stall current for more than 5 sec-
16.8.5 through 16.8.10. onds at a time. If repeated stall tests are
required the motors should be operated
in the RUN position occasionally to
!! OBSERVE WARNINGS !! eliminate the possibility of localized
16.8.12 Connect the recorder across the capacitors of heating on the commutators.
phase C of the 1/2 BANK, and repeat the tests of
16.8.5 through 16.8.10. 16.9.3 Set the hoist reference to the full positive (+)
position to give the specified stall armature cur-
rent I-A2.
!! OBSERVE WARNINGS !!
16.8.13 Open the circuit breaker for the 1/2 BANK, 16.9.4 Using two digital voltmeters, measure the out-
and close the breaker for BANK 1. put voltage, VQ, of the kVAR transducer at ter-
minals 1 and 2, and simultaneously, the ac
16.8.14 Repeat the tests of 16.8.5 through 16.8.12 for voltage (115V) between terminals 3 and 4, or 5
BANK 1. and 6.

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 60 CAT312.fm
Electrotorque Plus®

Figure 16.8.5 RPC Switching Chart Recording

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 61 TEST PROCEDURE
Electrotorque Plus®

Figure 16.8.8 RPC Capacitor Chart Recording

Copyright © 1999 Harnischfeger Corporation


TEST PROCEDURE 62 CAT312.fm
Electrotorque Plus®

16.9.5 Return the hoist reference voltage to 0V. Set 16.10.3 While someone is monitoring the RPC indica-
the hoist brake, and press the STOP push-but- tors, the RPC steps can be successively brought
ton. in slowly by stalling the hoist and then adding
the crowd.
16.9.6 Verify that the output voltage, V Q, measured is:

VQ = (0.00000141 x VAC x Iarmstall) +/–0.02VDC


Stall test must not exceed 10 seconds.
Where: VAC is the AC voltage measured in step
16.10.3. 16.10.4 Reduce both the hoist and crowd reference
voltages to 0V. Set both brakes. Press the
Example: STOP push-button.

VQ = (0.00000141 x 105 x 2650A) +/– 0.02VDC 16.10.5 Refer to the RPC indicator decals to verify
proper operation.
= 0.392 VDC +/– 0.02 VDC
16.11 Remove test equipment.
16.10 CHECK THE RPC UNDER FULL POWER
CONDITIONS 16.11.1 Remove all PLC forces if any exist. Discon-
nect and remove the PLC terminal.
16.10.1 Set the test selector switch to ARMATURE
TEST. Close all RPC circuit breakers. 16.11.2 Remove the reference/push-button unit and
reconnect the appropriate PLC cables. Remove
16.10.2 Press the START push-button. Press the any and all external connections made to the
HOIST and CROWD BRAKE RELEASE push- control circuits.
buttons.

Copyright © 1999 Harnischfeger Corporation


CAT312.fm 63 TEST PROCEDURE

You might also like