Notice of Valuation

To KPK Quantity Surveyors Sdn Bhd NOV No 1111500-WD-NOV26

Attention Mr Zazali Date 08 March 2018

From Mr M.C. Kwang Subject Contractor’s Interim Claim No.26 - M&E


PRO

Project The Westin Desaru Project No SIN1111500


Contract Main Contract – M&E Services No. of pages 2
Copies TAR&H – Mr. Chew, Mr. Hakim, Mr. Megat

Statement of MRCB – Contractor Interim Claim No.31 (No.26 - M&E) as of 28 Feb 2018
Extract from Prime Cost and Provisional Sums – Interim Claim No. 26
Contract Amount Work Previous Current Total Claim
(RM) Done % (RM)

PRIME COST SUM


B Lift Services
2,478,465.00 62% 1,536,648.30 - 1,536,648.30
Profit 49,569.30 62% 30,732.97 - 30,732.97
Attendance 35,000.00 62% 21,700.00 - 21,700.00

Sub-Total for Item B 2,552,818.95 1,589,081.27 - 1,589,081.27

Interim Claim No. 26 – Summary


Contract Amount Work Done Previous Current Total Claim
(RM) % (RM)

1 PC and Provisional Sum 82,711,218.95 1.92% 1,589,081.27 - 1,589,081.27

2 Main Summary of M&E Works 35,043,800.00 89.48% 30,678,714.32 677,474.69 31,356,189.01

3 Material on Site

Total Claims for M&E 32,945,270.28

MC Kwang
Project Leader’s Name Signature Date

This document may contain confidential and legally privileged information, neither of which are intended to be waived, and must be used only for its intended purpose. Any
unauthorised copying, dissemination or use in any form or by any means other than by the addressee, is strictly prohibited. If you have received this document in error or by any
means other than as authorised addressee, please notify us immediately and we will arrange for its return to us.
WSP Ng Assessment of Work Completed as at 28 Feb 2018
Under Prime Cost and Provisional Sums – Interim Claim No. 26
Contract Amount Work Previous Current Total Claim
(RM) Done % (RM)

PRIME COST SUM


B Lift Services
2,478,465.00 62% 1,536,648.30 - 1,536,648.30
Profit 49,569.30 62% 30,732.97 - 30,732.97
Attendance 35,000.00 62% 21,700.00 - 21,700.00

Sub-Total for Item B 2,563,034.30 1,589,081.27 - 1,589,081.27

Interim Claim No. 26 – Summary


Contract Amount Work Previous Current Total Claim
(RM) Done % (RM)

1 PC and Provisional Sum 82,711,218.95 1.92% 1,589,081.27 - 1,589,081.27


2 Main Summary M&E Works 35,043,800.00 88.79% 30,678,714.32 435,197.64 31,113,911.96
3 Material on Site

Total Claims for M&E 32,702,993.23

Notes:
1. WSP Assessment excludes GST.

MC Kwang
Project Leader’s Name Signature Date

This document may contain confidential and legally privileged information, neither of which are intended to be waived, and must be used only for its intended purpose. Any
unauthorised copying, dissemination or use in any form or by any means other than by the addressee, is strictly prohibited. If you have received this document in error or by any
means other than as authorised addressee, please notify us immediately and we will arrange for its return to us.