Quick Start Guide

POWERLINK™ CONNECT

Version 9.5

December 2016

1
Disclaimer of Warranties and Liability

The information contained in this manual is believed to be accurate and reliable. However, GE Intelligent Platforms,
Inc. assumes no responsibilities for any errors, omissions or inaccuracies whatsoever. Without limiting the foregoing,
GE Intelligent Platforms, Inc. disclaims any and all warranties, expressed or implied, including the warranty of
merchantability and fitness for a particular purpose, with respect to the information contained in this manual and the
equipment or software described herein. The entire risk as to the quality and performance of such information,
equipment and software, is upon the buyer or user. GE Intelligent Platforms, Inc. shall not be liable for any damages,
including special or consequential damages, arising out of the use of such information, equipment and software,
even if GE Intelligent Platforms, Inc. has been advised in advance of the possibility of such damages. The use of the
information contained in the manual and the software described herein is subject to GE Intelligent Platforms, Inc.
standard license agreement, which must be accepted by the buyer or user before the use of such information,
equipment or software.

Trademark Notices

© 2016 General Electric Company. All rights reserved.

Microsoft® is a registered trademark of Microsoft Corporation, in the United States and/or other countries.
All other trademarks are the property of their respective owners.

All other product names and marks identified throughout this book are trademarks or registered trademarks of their
respective companies. They are used throughout this book in editorial fashion only. No such use, or the use of any
trade name, is intended to convey endorsement or affiliation.

No part of this publication may be reproduced in any form, or stored in a database or retrieval system, or
transmitted or distributed in any form by any means, electronic, mechanical photocopying, recording or otherwise,
without the prior written permission of GE Intelligent Platforms. Information contained herein is subject to change
without notice.

We want to hear from you. If you have comments, questions, or suggestions about our documentation, send them to
the following email address:
doc@ge.com

2
Table of Contents

About this Quick Start Guide ............................................................................................................................................. 4

Installation Prerequisites..................................................................................................................................................... 5

Installing the Software ......................................................................................................................................................... 5

Running the Demo Project ................................................................................................................................................. 5

iPower Overview ...................................................................................................................................................................... 6

Creating an iPower/Powerlink Connect Project ...................................................................................................... 7

Creating an iPower/Powerlink Connect Screen ...................................................................................................... 8

Configuring DNP and IEC 61850 Drivers ..................................................................................................................... 9

Configuring Sample DNP Points ................................................................................................................................... 10

Configuring Sample IEC 61850 Points....................................................................................................................... 16

Running the Project............................................................................................................................................................. 18

Getting Started with dbArchitect ................................................................................................................................. 19

Exporting and Importing DNP-Based Projects ..................................................................................................... 21

Useful Components for a Complete Solution ........................................................................................................ 22

3
About this Quick Start Guide
This guide describes how to build a iPower or Powerlink Connect implementation for
CIMPLICITY. The Readme file that accompanies the software contains release notes, including
system requirements. The following figure shows the process flow described in the document.

Installing Software
- CIMPLICITY
- iPower
- DNP

Running iPower Demo


- Familiarize
- Demo Guide

Creating
iPower\Powerlink
Connect Project
- Link to DNP
- Link to IEC 61850

Running Project

Importing & Exporting

4
Installation Prerequisites
Before installing the software, review these prerequisites:

1. Have the CIMPLICITY Server license ready, including the iPower (Powerlink
Connect) license option.

2. Obtain and install the latest GE Licensing Software.

3. Activate the software license.

4. Review the CIMPLICITY Secure Deployment Guide.

Installing the Software


Install the following software, referring to the respective installation guides:

1. Install CIMPLICITY Server 9.5 from the DVD media.


2. Install Latest CIMPLICITY 9.5 sim or later from the GE Support website.
3. Install iPower for CIMPLICITY from the DVD media (selecting the Typical install).
4. Install the Distributed Network Protocol (DNP) driver.
5. If not already installed, install a PDF reader to allow the viewing of iPower help
files.
6. Restart the computer.

Running the Demo Project


Follow these steps to run the iPower for CIMPLICITY demo project:

1. Click the iPower (Powerlink Connect) shortcut from the desktop.

5
2. Select and start the CiPowerDemo.gef project in the Select CIMPLICITY Project dialog.
3. Log in when prompted using these credentials:
Username: Admin
Password: admin
4. Review the iPower for CIMPLICITY demo project.

NOTE: You can access the demonstration guide under Help in the iPower for CIMPLICITY menu or
directly from the default installation folder: C:\Program Files (x86)\Proficy\Proficy
CIMPLICITY\iPower\Help.

iPower Overview
iPower is an application suite that runs with CIMPLICITY. iPower provides operator
runtime and system configuration facilities that are integrated with the standard
SCADA features provided by CIMPLICITY.

For the electric industry sector, CIMPLICITY, iPower, DNP, and IEC-61850 drivers are
bundled together and delivered as Powerlink Connect.

For additional information, see the following:

 CIMPLICITY Help

 iPower Configuration Guide (CHM format) in the iPower Help

 DNP Configuration Guide (CHM format) in the DNP Configuration Manager


Help provides details on the DNP driver

 Proficy Driver Help for details on the IEC 61850 driver

6
Creating an iPower/Powerlink Connect Project
You can create a new project (for example, MyProject) by opening the template project in the
CIMPLICITY Workbench and using the File>Copy To Project menu item, and selecting a
location and name for the new project. You then open the new project in the Workbench,
being mindful that the template project remains open in the Workbench after running the
File>Copy To Project command. The iPower for CIMPLICITY template project has class
definitions but does not have a sample database or screens. You can find the project at:

C:\Program Files (x86)\Proficy\Proficy


CIMPLICITY\projects\iPowerTemplate

When you create a new project, update the Proficy for Power SCADA background services
with the new project information as follows:

1. Open the following configuration file:

C:\Program Files (x86)\Proficy\Proficy


CIMPLICITY\data\ipower.ini

2. Add the new project details:

[Project Connection]

ProjectList=CIPOWERDEMO,IPOWERTEST,MYPROJECT

You can also view and edit connected projects on the Connection Projects tab, which you
access through the MOA Manager Configuration dialog.

The template project is configured with a default admin/admin for user and password. Using
the CIMPLICITY Workbench, change the admin password.

7
Creating an iPower/Powerlink Connect Screen
The iPower template project includes a sample screen called iPowerDefaultScreen.cim that
you can use as a common starting point to develop iPower and Powerlink Connect screens.
The sample screen includes the events, variables, and interfaces required by iPower.

Follow these steps to create iPower screens using the sample screen:

1. In Workbench, select iPowerDefaultScreen.cim from the available screens.

2. Right click and select Edit. Under the CimEdit file menu, select SaveAs to save the
screen under the required screen name.

3. To insert and display an iPower object on the screen, select Class Object from the
Drawing (Illustrations) menu.

Note that the iPower template project does not have any configured database
objects. You must first create them before you can perform screen editing.

You can manually create database objects (see Configuring Sample DNP
Points), or automatically create them (see Getting Started with dbArchitect or
Exporting and Importing DNP-Based Projects).

4. To insert an iPower list control on the screen, select iPower List Control from the
Drawing (Objects) menu.
For a description of the screen development process, see the CIMPLICTY Help and iPower
Configuration Guide.

8
Configuring DNP and IEC 61850 Drivers
NOTE: When running under CIMPLICITY, the driver runs as a service and there is no visible tray icon.

The DNP driver option installs the Catapult DNP driver, which supports DNP 3.0 master
communications for up to 1,000 slave devices across serial and/or IP channels.

The DNP installer creates shortcuts to the DNP driver and documentation in the Windows
Start menu at All Programs | Proficy | ProficyDrivers | Catapult DNP3.

Follow these steps to configure the DNP driver:

1. Open the DNP3 Help, and find the section in the contents that describes DNP
configuration steps for CIMPLICITY:

SCADA configuration | CIMPLICITY Configuration | CIMPLICITY Driver Configuration

2. Follow the steps to add the DNP driver and to configure a port and device.

Add a DNP port:

Add a DNP device:

9
Proficy Driver Server IEC 61850 protocol is installed with CIMPLICITY. Follow these steps to
configure the IEC 61850 Driver:

1. Access CIMPLICITY Help and go to the following section in the contents:

Communications Equipment | Native Device Communications | Proficy Driver


Server Client

2. Follow the steps to configure the driver.

Configuring Sample DNP Points


Follow these steps to configure sample DNP points:

1. After the iPower project is started, launch the DNP client from the desktop DNP
icon (or if DNP Configuration is enabled in the Project Properties, you can launch
the DNP client configuration from that location).

10
a. Configure a test channel (port) by referring to DNP Help documentation at:
DNP3 driver configuration | Channel Configuration

11
b. Configure a test device (for example, TestRTU) as described in:
DNP3 driver configuration | Device Configuration | Device Configuration

c. Connect the device to the channel as described in:

DNP3 driver configuration | Configuring Connections

2. In Workbench, browse to view points, and select a representative object from the
demo project as follows (for example, you can associate a DNP analog point with
a feeder current):

a. Select the object (for example, POW_SUB_CB37_AI_AMPSA).

12
b. Update the device ID details on the General tab.

13
c. Update the address details on the Address tab.

NOTE: The DNP address syntax is DeviceName.Obj.Var.Address, where DeviceName is the


name configured in the DNP driver client. For information about addressing, see the
following topic in the DNP Help:

SCADA Configuration | CIMPLICITY Configuration | Configuring a CIMPLICITY Database


Point

3. Browse to view points in Workbench, and select a representative object from the
demo project. For example, you can associate a DNP digital point with an alarm
point.
a. Select the object (for example, POW_SUB_CB37_DI_ALARM).
b. Update the device ID on the General tab.

14
c. Update the address details on the Input Address tab.

NOTE: The DNP address syntax is DeviceName.Obj.Var.Address, where DeviceName is


the name configured in the DNP driver client. For information on addressing, see the
following topic in the DNP Help:

SCADA Configuration | CIMPLICITY Configuration | Configuring a CIMPLICITY Database


Point

15
Configuring Sample IEC 61850 Points
iPower includes dbArchitect, a tool used for automatic configuration of the CIMPLICITY iPower
database and Proficy Driver configuration, based on customer 61850 definition files (SCD and
ICD).

Configuration details of the Proficy Driver and IEC 61850 protocol are described in the Proficy
Driver Server documentation in the Proficy Driver Server user interface:

16
Follow these steps to configure sample IEC 61850 points:

1. In the Proficy Driver Server Help, access IEC 61850 Protocol under Supported
Drivers:

2. As outlined in the help, add an IEC 61850 Device by right clicking on the Devices
node and adding an IEC 61850 device.

17
3. Configure the appropriate communication properties and data sets in the device
and access paths, as explained in the help.

NOTE: If you connected devices, you can use the Protocol Device scan at the project level
to find communicating devices and automatically set up device representations.

Running the Project


If test RTUs are available, you can run the project to test DNP / IEC 61850 communications.
For DNP communication problems, use the Messages Log window in the DNP client for
outgoing messages to the device/channel. For remote assistance, enable logging in the DNP
driver as set in the client under Server | Options | Log options. Enable all log options, and then
send the following file through your support contact:

 *.DNP configuration file


 Log file

For Proficy Driver Server IEC 61850 communication issues, use the statistics and logging tabs
as well as the properties of the pre-defined data blocks (for IEC 61850 data sets) and aliases in
the Proficy Driver Server client. You can access them from the CIMPLICITY device dialog or
from the Windows Start menu.

18
CIMPLICITY Help and iPower for CIMPLICITY Help is available describing the class, object, and
screen configuration process through the iPower for CIMPLICITY menu Help button. Refer to
the items under the Configuration Guides.

Getting Started with dbArchitect


dbArchitect is an iPower engineering tool used to configure the SCADA database using IEC
61850 SCL files (SCD and ICD) as the source. dbArchitect automatically imports database
objects and Proficy Driver Server configuration settings from the IEC 61850 SCL files. The
project database is built using iPower’s IEC 61850 classes.

Follow these steps to use dbArchitect to import SCL file items and SCADA objects into a
project:

1. Copy your project’s SCL files into the default dbArchitect SCL folder:

C:\Program Files (x86)\Proficy\Proficy CIMPLICITY\iPower\dbArchitect\SCL

2. While the project is running, open the CIMPLICITY Workbench and select dbArchitect
from the system tree:

19
3. In the dbArchitect user interface, you can browse the project’s SCD files:

4. Right click a SCL file and select Load to view it.

5. Check the box next to the loaded SCL file to select all its objects, and then
right click to select Generate SCADA Database from Selected.

6. Select the project in which to generate the objects, and click OK.

If you are not already logged in, CIMPLICITY displays a login window for you to enter
your credentials. The import starts.

7. When the import completes, exit dbArchitect.

8. Perform a Configuration Update from Workbench.

20
9. Refresh the list of objects in the project. The selected items from the SCL file and
generated SCADA objects now appear in your project.

Exporting and Importing DNP-Based Projects


To build projects without using imported IEC 61850 SCL files, you can use scripts to import and
export projects after manually configuring an initial sample of representative objects.

You can use these import and export scripts for bulk database production.

Follow these steps to export a project:

1. When the project is not running, execute the script Obj_Imp_exp_timed.bcl.


2. Select Export.
3. Select the project.

The output file contains a single line per entry, containing:

 Class name
 Object name
 Attribute name and value pairs

The ‘|’ separator is used rather than a comma to reduce possible conflicts in the object
descriptions. You can add additional lines using a text editor, such as Notepad.

Follow these steps to import a project:

1. Run the script Obj_Imp_exp_timed.bcl.


2. Select Import.
3. Select the project.

Existing objects are overwritten to apply all changes. New objects are created as required.

21
When the import completes, follow these steps:

1. Restart Workbench.
2. Run the project, and apply configuration changes when prompted.

Useful Components for a Complete Solution


These components assist in creating a complete iPower software solution,

Remote Viewing

 GE WebSpace provides remote access for managing and troubleshooting


real-time data, improving analytical and planning abilities, and improving
time to action.

 Microsoft Terminal Services provides access to iPower systems from anywhere


at anytime, and offers a single point of maintenance.

Logging Solutions

The logging solutions store data and alarms to use for trend charts and historical alarm
displays. These include:

 GE Historian logs information that enable you to quickly view KPIs, real-time
trends, history, and alerts from any device.

 Microsoft SQL Server 2014 Microsoft SQL server 2014 can log historical data
and alarms from CIMPLICITY. You can use SQL Server Express that is included
with CIMPLICITY or one of the SQL Server editions. For more information on
these capabilities, see the CIMPLICITY Help file at C:\Program Files
(x86)\Proficy\ProficyDoc\1033\CIMPLICITY\Dlcfgui.chm. You can use this
logged data for historical trends and historical alarm review.

22
Communication with Other Devices

GE IGS (Industrial Gateway Server) enables you to connect to a variety of


devices to consolidate data from different hardware and instruments to view,
analyze, and control data in iPower.

23

You might also like