You are on page 1of 4

International Conference on Electrical Engineering 2002

Providing Effective Transmission Substation Earthing


for CLP Power System Network

F.C. Chan Y.H. Choi


Substation Implementation Manager Senior Substation Design Engineer
CLP Power Hong Kong Limited
147 Argyle Street, Kowloon, Hong Kong SAR, China

Abstract load centre. In most cases, CLP Power has to accept


“restricted choice” land that is available in the planned
The purpose of substation earthing is to safeguard life, load area. Since many urban areas in Hong Kong are in
minimize interference to neighborhood during earth hilly area, the soil resistivity of 132kV substation site
fault and facilitate the prompt fault clearance and has a wide range of values and the underground water
system restoration. An ideal earthing system for an table level also fluctuates seasonally. These impose
electrical installation controls the resultant step, touch, some degree of constraints in designing an effective
transfer and rise of earth potentials during the most 132kV substation earthing grid in the present substation
onerous earth fault condition to be well within the site environment.
permissible levels. Given the hilly terrain and deep
water-table in CLP Power’s supply area, the provision 1.2 Effective Substation Earthing
of an effective substation earthing is a challenge to
substation design engineers, in particular when the Effective earthing is essential for the CLP Power’s
substation (equipped with compact gas insulated 132kV substation supplying areas of a high load density.
switchgear) site is relatively small in size. In this paper, The objectives are:
the difficulties and viable means to design a safe
earthing grid for CLP Power transmission substation • To safeguard life.
under these constraints are reviewed. • To minimize damage to electrical equipment during
the flow of fault currents to earth
• To provide a low impedance path for the passage of
1.0 Introduction fault current to earth to ensure the operation of power
system protection devices
CLP Power supplies electricity to over 2 million
customers in Kowloon, the New Territories and most of An ideal earthing system for an electrical installation
the outlying islands with a service area covering about under all circumstances including earth fault current
1,000 square kilometers. The system maximum demand flow is to effectively maintain an equipotential surface
was 5,844 MW in 2001. Electricity power is transmitted level over the entire ground area. In the case when a
from CLP Power’s Castle Peak and Black Point Power fault current is generated, it could be effectively
Station to its major load centres through its 400kV grid conducted into the lower ground layers back to the
system. The electrical power is stepped down to 132kV current source, thus enabling rapid protection clearing of
for area transmission to over two hundred 132kV the fault.
substations.

1.1 CLP Power 132kV Substations 2.0 Earth Grid System Design

CLP Power 132kV substations can be classified into The following basic parameters are adopted for the
132kV bulk and primary substations. These substations earthing system design.
normally accommodate up to four 132/11kV 50 MVA
transformers and eighty 11kV switchgear panels. A 2.1 Soil and Weather Parameters
typical 132kV bulk substation has a maximum of
twenty-eight bays of 132kV Gas Insulated Switchgear. Soil composition: most decomposed granite in hilly area
On the other hand, a typical 132kV primary substation is with thin layer of organic top soil and
equipped with a maximum of four SF6 Ring Main Units, sand filled in reclamation area
teeing off from the radial circuit connected to the 132kV Soil resistivity: 20 - 2200 ohm-meter
bulk substation. The typical 132kV bulk and primary Soil temperature: 24.9 oC (yearly average)
substation sizes are approximately 2,500 and 2,000 18.9–30.1 oC (monthly average,
square metres respectively. unfrozen)

As land is one of the precious resources in Hong Kong, Climate: Subtropical


it is difficult to acquire an appropriate substation site that Relative humidity: 77 % (yearly average)
is rectangular in shape, standard in size, and located in 68%- 83% (monthly average)

2557
International Conference on Electrical Engineering 2002

Brought out spur of 4 x


70 mm2 stranded copper
Mechanical coupler conductor at selected
location

2 x 70 mm2 stranded
copper conductor at
500mm below soil

13mmØ copper
clad steel cored earthing rod at
Perimeter of the substation grid

Figure 1 Typical Layout of Earthing System at 132kV Substation

2.2 Electrical Parameters


The horizontal grid conductors, the vertical earthing rod
Short time current (132kV): 31.5kA 3 seconds to the horizontal grid and brought out spur to 300/ 75
Maximum ROEP: 650V mm2 bonding copper tapes (for connection to substation
Maximum design conductor temperature: 375oC equipment) are coupled together by exothermic weld
utilizing the high temperature reaction of powdered
3.0 CLP Power Earthing Practices copper oxide and aluminum which when ignited
produces aluminum oxide and superheated copper.
3.1 Typical 132kV Substation Earthing Grid
CLP Power’s substation earthing grid is not directly
Typical CLP Power 132kV substation earthing grid connected to the metallic underground piling structure
comprises a horizontal grid and vertical earthing rods. aiming to avoid corrosion to the structural steel due to
The horizontal earthing grid is more effective in galvanic action of copper / steel in a moist soil condition
reducing the potential gradient generated by the earth and the potential drying up of the encased concrete
fault current. It is mainly made of 2 x 70 mm2 stranded during a earth fault condition. The generally acceptable
copper conductor in grid pattern. Brought-out spur is 132kV substation earthing resistance is around 0.2 ohm.
formed by looping the two copper conductors (i.e. 4 x 70
mm2 conductor) at selected locations such as cable 3.2 Typical Engineering Process
trench in equipment room, plant bay, main gate, cable
chase for earthing risers to equipment earthing on upper The soil composition and underground water level of the
floors. The horizontal copper conductor is usually buried substation site are collected from the site investigation
at 0.5 m below soil. A typical layout of this earthing report prepared by civil engineering staff. The top soil
system is shown in Figure1. resistivity of the substation site is also measured by a
typical Wenner Method as shown in Figure 2.
Vertical earthing rods are mainly used for reducing
Array Centre
substation earthing resistance and thus controlling the
rise of both earth potential and transfer potentials. It is 3a/2 a/2
usually installed at the perimeter of the earthing grid to a a a Soil Surface
control the step potential gradient. The vertical earthing
d
rod is made of copper clad steel cored rod (outer
diameter 13 mm, unit length 2.4m). Such type of Probe

earthing rod is selected because of its higher


conductivity, mechanical strength and practical
corrosion resistance over other metals in moist soil. The C1 P1 P2 C2
earthing rod is driven into the soil. It is extended to the Earth Tester
required depth (usually below the water table in dry
season) by jointing unit length together by a screw type Fig 2 Wenner Soil Resistivity measurement
mechanical coupler.

2558
International Conference on Electrical Engineering 2002

The test is normally carried out using a four-terminal If the permanent water table is over 10 m deep or with
composite earth test. The outer two probes are connected the presence of boulders or rock, the earthing rod cannot
to the current terminals C1 and C2 and the inner probes be effectively driven below the water table in the soil,
to voltage terminals P1 and P2. small bore holes ranging from 20-40m are drilled for
installing the earthing rod. After earthing rod installation,
However under certain circumstances, if the accurate the borehole is then filled up with bentonite (typical soil
measurement of the resistivity may not be possible, an resistivity: 2.5 ohm-metre at 300% moisture) to maintain
empirical value can be determined by making reference good electrical contact between the earthing rod and the
to the book “Thermal and Electrical Properties of Hong earth mass. To minimize the maintenance requirement
Kong Soils” by N.A. Halfter and S.Y. King. and potential contamination of underground water,
chemical filled earthing rod (i.e. specially design porous
After the resistivity of the soil is measured or estimated, metallic rod filled with soluble organic salt to increase
the earth grid is then designed with reference to the the conductivity of the surrounding soil until the salt is
following documents: consumed) is not used.

Electricity Council Engineering Recommendation Some countries use “blasting method” to increase the
S5/1; Earthing Installations in Substations cracks in soil or rock underground aiming to increase
IEEE standard 80; Guide for Safety in an AC current dispersion after this cracks are filled up with
Substation water/ conductive slit. This method is not practicable for
British Standard 6651; Protection of Structures a densely populated environment like Hong Kong where
against Lighting blasting will likely cause large damage to the existing
IEC 60364-5-54; Earthing of Electrical Installation building and structure in the vicinity of the substation
in Buildings site as well as the stability of rock bed and foundation of
the future substation building. Furthermore, there are
Special considerations are given to the layout and stringent regulations on the use of blasting in
physical arrangement of the substation site, vicinity of construction.
metallic underground facilities (e.g. water and gas main)
in and near the site and relative location of the Based on the above considerations, bore holes are widely
underground structures (e.g. foundation, oil interceptor, adopted, more than 40% of total, in CLP Power’s
etc). The preliminary earth grid design is then analyzed earthing rod installation to achieve a low substation
by computer based on ‘multiple soil layer model’. If the earthing resistance of approximately 0.2 ohm.
calculated touch voltage, step voltage and the rise of
earth potential exceed the Standards, the earth mat is 4.2 Segregation of True Earth and Substation Floors
reinforced by adding the number of and / or extending
the vertical earthing electrodes deeper into the moist All substation floors in direct contact the earth mass (i.e.
layer, as far as practical, or making closer the space of ground and basement floor) are covered with concrete
the grid conductor to increase the grid density. The for easy maintenance and limiting the step and touch
reinforced earth mat is then re-analyzed. If it is within potential during earth fault condition. To enhance the
the safety limit, the design will be passed on to the civil landscape of the substation and/ or fulfilling land grant
contractor for installation during the civil construction conditions of the substation site, reinforced concrete tree
stage of the substation building. planter with few small openings at bottom separating the
soil for trees or shrub from the earth mass to control the
The substation resistance after installation of the earth potential hazard.
grid is measured by “Fall of Potential Method” on site
and the result is then re-assessed by the computer 4.3 Remote Bonding
program to confirm its compliance with the designed
safety limit or necessity for further reinforcement. Due to the high load density of CLP Power supply area,
most substations have approximate eighty to ninety
11kV and 132kV cables running in and out of the
4. Some Special Practices in CLP Power substation which help to disperse the earth fault current.
However, in some special purpose substations (e.g.
To overcome the compactness of the 132kV substation, traction and water supply pumping station), the number
wide range of soil resistivity of substation sites in most of cables running in and out of the substation is relative
CLP Power supply area and the stringent safety and low, says 5 to 10. Unfortunately, size of these
interference requirements, the following means are substations are relatively smaller (ranging from 500 to
selectively adopted by CLP Power to achieve a 1600 m2), these constraints impose challenges in
satisfactory design. substation earthing. In the cases that substation’s
earthing grid cannot effectively disperse the earth fault
4.1 Bore Hole for Installation of Vertical Earthing current, the grid will be bonded to the customer’s lower
Rod voltage earthing grid (for 11 to 33kV voltage equipment)

2559
International Conference on Electrical Engineering 2002

at more than two points by minimum two single core existing lower voltage earthing grid to 132kV level
240 mm2 copper bonding cables. Removable links adopted successfully in CLP Power thus resolve the site
housed in a lockable box with adequate warning label of & system constraints and provide a safe and effective
‘not disconnecting in normal operating condition’ are earthing system for CLP Power’s new or upgraded
provided for these bonding cable for testing purpose. transmission substations.

If this coupling is still not effective, as a last resort, the


substation will be connected through similar bonding ACKNOWLEDGMENTS
cable (laid together with the incoming cables in the same
cable trench) to the earthing grid(s) of the nearest 132kV The authors wish to thank the Management of CLP
feeding substation(s). The number of bonding cables Power for the support and permission to publish this
depends on the separating distance of the two substations paper.
and the target overall earthing resistance to be achieved .

4.4 Substation Upgrading


Reference
CLP Power is implementing a program to upgrade the 33
and 66kV substations to 132kV voltage level. Most of 1. Monthly Metrological Normals and Extremes for
these old substations are upgraded in stages and in-situ. Hong Kong, Hong Kong Observatory
Such upgrading imposes extreme difficulties in 2. Code of Practice for Transmission Substation
substation earthing design particularly when, Design, CLP Power Issue 3, Jan 2002, 8.1-8.11
The old earthing records are no longer available. 3. Li Cheng Guo, Decreasing Grounding Resistance of
The condition of existing earthing grid is unknown Urban Substation by Utilizing Peripheral
unless the whole substation is shut down for safe Geographical Conditions, Electric Power, 2001, 34
assessment, which is not practical. (11): 50-53.
Soil resistivity cannot be accurately and safely 4. Halfter N.A. and King S.Y., “Thermal and Electrical
measured due to the presence of large number of in- Properties of Hong Kong Soils”
service cables in or around the substation.
Soil investigation can only be carried out if the site
condition permits (e.g. existing plant and
underground facilities can be timely vacated ). If
not, soil resistivity is estimated based on the
available soil composition or similar site
investigation of adjacent buildings (if available) and
the reference book mentioned in section 3.2.
Earthing grid installation is confined to a very small
working area particularly in the early stage of the
redevelopment but the grid has to be capable of
safely dispersing the 132kV fault current.

With these constraints and uncertainties, new deeply


bored earthing rods (20-40m) and new horizontal grid
are usually designed & installed in the available space
(preferably at the perimeter and corners of the substation)
and redeveloped area, and are extended in stages. The
computer simulation is based on the assumed absence of
the existing earthing grid. But, the new earthing mat is
solidly connected to the existing one at minimum two
points by exothermic weld. Surface run conductors are
also used to link up the existing bonding conductors to
the new earth mat through unmodified area.

5.0 Conclusion

Designing and installing an effective earthing grid for


compact 132kV substation in high soil resistivity areas
to comply with the stringent safety requirements is a
very challenging work for the design engineers. This
paper outlines the special earthing practices including
deep bore hole, remote bonding and staged upgrading of

2560

You might also like