ID Task Name Duration Start Finish Cost in Pounds 9 Jan ' 23 Jan ' 06 Feb 20 Feb 06 Mar '

Cost in Pounds 9 Jan ' 23 Jan ' 06 Feb 20 Feb 06 Mar ' 20 Mar ' 03 Apr ' 17 Apr ' 01 May 15 May 29 May 12 Jun ' 26 Jun ' 10 Jul ' 24 Jul ' 07 Aug 21 Aug 04 Sep 18 Sep 02 Oct ' 16 Oct ' 3
T SWS T M F T SWS T M F T SWS T M F T SWS T M F T SWS T M F T SWS T M F T SWS T M F T SWS T M F T SWS T M F T SWS T M F T SWS
1 INSTALLATION OF TIDAL TURBINE 240 days Thu 20-01-11 Wed 26-10-11 £ 1,185,500.00

2 Feasibility Study 55 days Thu 20-01-11 Thu 24-03-11 £ 6,500.00

3 Data Collection 15 days Thu 20-01-11 Sat 05-02-11 £ 2,000.00

4 Data Analysis 15 days Mon 07-02-11 Wed 23-02-11 £ 2,000.00

5 Preliminary Survey and design 15 days Thu 24-02-11 Sat 12-03-11 £ 2,000.00

6 Preparation of Feasibility study report 10 days Mon 14-03-11 Thu 24-03-11 £ 500.00

7 Project Execution 178 days Fri 25-03-11 Tue 18-10-11 £ 1,174,000.00

8 Obtaining Licence,Insurance,Lease and 30 days Fri 25-03-11 Thu 28-04-11 £ 120,000.00


Permission

9 Detailed Survey 30 days Fri 25-03-11 Thu 28-04-11 £ 45,000.00


(Bathymetry,Geotechnical,
Environmental)

10 Detailed Design and Specifications 30 days Fri 25-03-11 Thu 28-04-11 £ 14,000.00

11 Resourse Assesment 7 days Fri 29-04-11 Fri 06-05-11 £ 1,000.00

12 Material Procurement and Labour 30 days Sat 07-05-11 Fri 10-06-11 £ 545,000.00
Mobilization

13 Manufacturing of Structural Elements 60 days Sat 11-06-11 Fri 19-08-11 £ 130,000.00

14 Construction 55 days Sat 11-06-11 Sat 13-08-11 £ 40,000.00

15 Construction Material arrival to 7 days Sat 11-06-11 Sat 18-06-11 £ 5,000.00


nearest onshore casting yard

16 Shuttering 7 days Mon 20-06-11 Mon 27-06-11 £ 5,000.00

17 Reinforcement fabrication and 7 days Tue 28-06-11 Tue 05-07-11 £ 5,000.00


fixing

18 Onshore Casting & Curing of 30 days Wed 06-07-11 Tue 09-08-11 £ 10,000.00
Concrete Gravity Base

19 Transporting the Pre-Cast Gravity 2 days Wed 10-08-11 Thu 11-08-11 £ 10,000.00
Base to the site

20 Positioning of Gravity base 2 days Fri 12-08-11 Sat 13-08-11 £ 5,000.00

21 Onshore Assembling of Turbines and 30 days Sat 20-08-11 Fri 23-09-11 £ 10,000.00
Generators with support systems

22 Transporting the Assembly to the site 2 days Sat 24-09-11 Mon 26-09-11 £ 5,000.00

23 Installation and deployment 4 days Tue 27-09-11 Fri 30-09-11 £ 5,000.00

24 Ballasting 1 day Sat 01-10-11 Sat 01-10-11 £ 1,000.00

25 Laying of underwater Electrical cables 30 days Mon 29-08-11 Sat 01-10-11 £ 198,000.00

26 Onshore Electrical 14 days Mon 03-10-11 Tue 18-10-11 £ 60,000.00


Installations/Connections

27 Testing & Commissioning 7 days Wed 19-10-11 Wed 26-10-11 £ 5,000.00

Task Critical Task Progress Rolled Up Task Rolled Up Progress Project Summary
Project: CONSTRUCTION PLAN WIT Task Progress Milestone Rolled Up Critical Task Split
Date: Tue 22-03-11
Critical Task Summary Rolled Up Milestone External Tasks

Page 1