MARINE ELECTRICAL ELECTRONIC TECHNOLOGY
LEB 41303 – SHIP ELECTRICAL INSTALLATION
Name :
Marks
I/D No :
Name :
I/D No :
Group :
Lab Group :
Date :
Lecturer :
Objectives:
1. To install and connect the 3 phase power supply wiring for a Direct On Line (DOL) Forward
Motor Control connection.
Preparation:
1. Safety precaution.
2. Standard operating procedure.
3. Personal Protection Equipment
4. Connector.
5. Tools.
6. Necessary item needed
1. Contactor 1 unit
2. Auxillary contact 1 unit
3. Overload module 1 unit
4. Lamp module 1 unit
5. Switch Module 1 unit
6. 1 wire cutters 1 unit
7. 1 wire strippers 1 unit
8. 1 pliers 1 unit
9. 1 screws 1 unit
10. Cables 1.5 mm2 / 2.5 mm2 As required
11. 1 Multi meter 1 unit
12. Insulation Meter 1 unit
13. Socket Tester 1 unit
14. Earth tester 1 unit
15. Tools When needed
Procedures:
1. Connect the wiring for the 3 phase Direct On Line (DOL) Forward Motor Control. As in figure 1.
2. On completion test the circuit using continuity check and insulation test before testing it with a power
supply.
3. Switch “ON” the supply / motor.
4. Press “FORWARD” button. Verify that the motor turn in “Forward” direction.
5. Press “STOP”. Make sure the motor has “STOP”.
6. Switch “OFF” the supply / motor.
TASK 1
R Y B L N
7. Figure 1
MCB
6A
MCB
32A LITAR KAWALAN
GELUNG M
SESENTUH
UTAMA M M1
B.E.T
LITAR UTAMA
GEGANTI
BEBAN
LAMPAU
Gelung(coil) Contactor
PAGE 3/4
B.E.T
MARINE ELECTRICAL ELECTRONIC TECHNOLOGY
Analysis / Discussion :
Conclusions :