Professional Documents
Culture Documents
6, NOVEMBER/DECEMBER 2005
Abstract—The recent popularity of distributed generation (DG) to be tripped for a system disturbance that would not cause the
has caused an increasing number of small generators (rated be- generator to fall out of step or to trip and damage equipment not
tween 100 kVA and 12.5 MVA) to be connected to the power system rated to trip in an out-of-step condition. An out-of-step relay
at the distribution level (480 V to 12.47 kV). Some utilities require
that out-of-step relays be installed by the generation owner at can be employed to block the action of other relays to allow a
the point of common coupling (PCC). This paper will examine large generator to ride-through disturbances that do not cause
out-of-step relaying practices as they apply to small generation the generator to fall out of step, but which might cause other
protection. It will consider the value, purpose, and applicability types of relaying to trip the generator. This relay is also used to
and provide guidelines for setting of this type of relay when block the tripping of breakers when conditions due to an out-
employed.
of-step condition are too severe to allow the breaker to open
Index Terms—Device 78, distributed generation, generator pro- until the machine swing has progressed to the point where safe
tection, out-of-step relay. interruption is possible.
Proper setting of an out-of-step relay requires a detailed
I. I NTRODUCTION transient stability study of the power system. This is a perfectly
valid reason to perform the transient stability studies for large
I N AN EFFORT to accommodate the connection of dis-
tributed generation (DG) on their systems, some utilities
have adopted simplified interconnection requirements for these
generators (say 500 MVA and larger). On a small generation
project, however, sufficient funds are seldom available to pay
for, nor is there any real need to perform, such a study.
generators (often limited to 5 MVA or less). These require-
Methods for calculating “preliminary” settings are available
ments are implemented to protect the system by automatically
from most relay manufacturers and other sources [1]. Since
disconnecting the generator in the event of a system fault or
sufficient system information to properly set this relay is seldom
unusual generator operating conditions that may cause voltage
available on a small generation project, the engineer may have
or current disturbances on the system. Safeguards are also
to rely on these “preliminary” settings, even though the lack
required to disconnect the generator in the event the utility
of system information makes it impossible to determine how
deenergizes the distribution line being fed by the generator.
closely these settings are to the optimum values or if the
In addition, protective relaying is also installed to protect the
“preliminary” settings actually accomplish the desired result.
generator from damage due to system-originated disturbances
Furthermore, the practice of allowing the out-of-step relay to
and faults.
trip the generator, instead of block tripping, may be discovered
Included in these protection requirements is the need to
to be undesirable if a complete transient stability study was
automatically disconnect the generator from the power system
performed.
if the generator loses synchronism, or goes out of step, with
Recently published IEEE Std. 1547-2003 [13], however,
the system. Some utilities have interpreted this requirement by
does not require the “loss-of-synchronism” protection for such
including an out-of-step relay (ANSI/IEEE Device 78) in the
generators. ANSI/IEEE Std. 242 (Buff Book) suggests the
interconnection protection package.
protective relays (Table I) for use on generators of the sizes
This requirement when applied can present a challenge for
indicated [10].
the protection engineer trying to set this relay correctly. The
If electromechanical relays are used, each of these functions
traditional use of the no. 78 relay was to block inadvertent
is typically provided by a separate relay. With modern micro-
generator tripping. It is undesirable to allow a large generator
processor based relays, however, one “box” may be installed
to perform all of these functions and offer other functions
including out-of-step relay.
Paper ICPSD-04-07, presented at the 2004 IEEE Rural Electric Power
Conference, Scottsdale, AZ, May 23–25, and approved for publication in the It is up to the protection engineer to decide which of the
IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS by the Rural Electric many offered functions are valuable in protecting the generator
Power Committee of the IEEE Industry Applications Society. Manuscript and the system, and care must be exercised in deciding which
submitted for review June 30, 2004 and released for publication August 4, 2005.
K. Malmedal and J. P. Nelson are with the NEI Electric Power Engineering functions to employ. The easy availability of many functions at
Inc., Wheat Ridge, CO 80001 USA (e-mail: kmalmedal@neiengineering.com; no additional hardware cost may tempt the protection engineer
jnelson@neiengineering.com). into using functions that add little, if any, value to system
P. K. Sen is with the Colorado School of Mines, Golden, CO 80402 USA
(e-mail: psen@mines.edu). or generator protection. Keep in mind that more does not
Digital Object Identifier 10.1109/TIA.2005.857470 necessarily mean better. Keep it simple.
TABLE I
SUGGESTED RELAY FUNCTIONS FOR GENERATORS
Fig. 12. Generator terminal phase voltage for a bolted three-phase fault.
Fig. 10. Rotor angle for a bolted three-phase fault at generator terminals. IV. O UT - OF -S TEP R ELAY O PERATION
There are several methods by which out-of-step relays at-
fall out of step. This is depicted in Fig. 9, which shows the tempt to detect a swing condition. They all utilize positive
power angle diagram for a three-phase fault. sequence impedance measuring elements. One common type
The critical clearing angle is 118◦ . If the fault were to clear uses the “two-blinder method,” which will be discussed here.
when the rotor was less than 118◦ , “area B” in Fig. 9 would Three impedances are defined in this relay—a mho circle
exceed “area A” and the decelerating energy would exceed and two blinder impedances. The impedances calculated by the
the accelerating energy, and the machine would not fall out “preliminary” method recommended by one relay manufacturer
of step. for the example of Fig. 3 result in the diagram shown in Fig. 13.
The rotor angle during a three-phase fault at the generator These are secondary values where (CT ratio)/(PT ratio) = 4.
terminals when the fault is not cleared is shown in Fig. 10. The relay measures the impedance at its point of application.
If the fault clears after the rotor reaches 118◦ , the swing If the swing impedance crosses into the mho circle, crosses one
will continue and the machine will lose synchronism with the of the blinders, remains between the blinders for a preset time,
system. The rotor swing calculation shows that the fault must then crosses the other blinder, the relay determines that an out-
clear in 0.11 s (6.6 cycles) or less to prevent a swing exceeding of-step condition has occurred and initiates a trip. If all of these
the 118◦ angle. If the three-phase fault occurred at the center criteria are not met, the relay determines that a stable swing has
of the system (splitting the reactance in half), the current occurred and does not trip.
magnitude from the generator would be 1.2 kA, the voltage The swing trajectories for the faults already considered plus
magnitude at the generator terminals would be 991 V, and the a three-phase fault that was not cleared in time to prevent an
current angle during the machine swing would lag the voltage out-of-step swing are shown in Fig. 14.
by 90◦ . The line-to-line-to-ground fault and three-phase fault cleared
If the fault cleared in 6.5 cycles, the voltage angle would have at a rotor angle of 90◦ did not cause an unstable swing. Fig. 14
reached 90◦ . The swing would continue to an angle of 108◦ shows that these trajectories do enter the mho circle, however,
and eventually settle around the new voltage angle of 10.1◦ . they do not cross any of the blinders, so the relay will not trip.
Ignoring the subtransient effects, the current during this fault The three-phase fault cleared at 130◦ does cause an unstable
and after the fault is cleared is shown in Fig. 11 and the swing. The trajectory of this fault does cross both blinders.
corresponding voltage is shown in Fig. 12. The calculated time the impedance remains between the two
MALMEDAL et al.: OUT-OF-STEP RELAYING FOR SMALL GENERATORS IN DISTRIBUTED GENERATION 1511
shown in Figs. 7 and 11, would have tripped for any of the
faults, regardless of whether or not the generator underwent an
unstable swing.
The next relay to pick up would be the interconnection
undervoltage relay (27) that had settings of 10 cycles and
0.5 p.u. V. This relay would have tripped for all of the faults
considered here.
In the case of the line-to-line-to-ground fault, the third relay
to trip would be the generator voltage restrained overcurrent
relay (51 V), which would pick up and time out for this voltage
and current level in 0.2 s. This relay would also trip for a three-
phase fault that was not cleared by another element.
The out-of-step (78) relay would have no opportunity to trip
unless these three elements failed to operate. This would be true
regardless of whether the generator actually lost synchronism
with the system or not. In the case where the swing was stable,
the Device 78 would properly not trip since the machine will not
lose synchronism. However, this is irrelevant since other relays
would have already tripped the generator off.
If it is decided that the out-of-step relay will trip the generator
and not block other elements from tripping, then to have any
Fig. 14. Impedance trajectories. meaningful place in protection of the generator or the system,
blinders was 0.08 s (or 4.8 cycles). If the time delay on the several coordination issues must be faced. The instantaneous
relay was set at less than 0.08 s, the relay should trip for overcurrent relay must be eliminated or set above the maximum
this swing. current that could be expected at the generator due to any
swing that may occur. The undervoltage relay must be delayed
beyond the time the voltage is expected to be depressed by
V. R ELAY C ORDINATION
the slowest swing, either stable or unstable, that could happen
Fig. 15 is a simplified relaying single-line diagram for the on the system. The voltage restrained overcurrent relay must
system described. have settings that will prevent it from tripping for the depressed
Typical settings for the relays in Fig. 15 are given in Table II. voltage and elevated current conditions expected during both
For each of the faults examined here, the first relay to pick up stable and unstable swings.
a trip signal would be the generator instantaneous overcurrent As an alternative, the out-of-step element could be used to
(50) relay. This relay had a setting of 1000 A primary and, as block other relay elements from tripping until the generator
1512 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 41, NO. 6, NOVEMBER/DECEMBER 2005
TABLE II
TYPICAL RELAY SETTINGS FOR FIG. 15
actually went out of synchronism with the system. When it neutral voltage of the system. The circuit breaker may not be
sensed that the generator was out of step, it could initiate capable of interrupting the current available at these elevated
tripping or allow one of the other relays to trip. If this alternative voltage levels.
was chosen, other relay settings would have to be examined The out-of-step relay has the advantage that the blinders
to ensure that all other relays that could trip faster than the can be set to ensure that the trip is not initiated until the
out-of-step swing occurred were blocked. The time this block- swing angle has proceeded beyond a certain point. An angle
ing action would be required would be difficult to determine of 120◦ is often used for this setting. Some manufacturers
without the results of a transient stability study to determine voluntarily test their breakers under this condition and label
the slowest swing that might be expected on each individual their breakers as being capable of interrupting 25% of their
system. Consideration should also be given to the damage that interrupting rating under this condition. A breaker that meets
might result to the generator during this delayed period of time. the IEEE Std. C37.013-1997, Standard for AC High-Voltage
Any condition that would result in damage to the generator Generator Circuit Breakers Rated on a Symmetrical Current
must be removed as quickly as possible. Basis, and that has an out-of-phase current switching rating
must be capable of interrupting 50% of its maximum inter-
rupting rating during an out-of-step condition where the voltage
VI. C IRCUIT B REAKER C ONSIDERATIONS
angle difference is 90◦ at its rated voltage. If the breaker
If the overcurrent or undervoltage relays are allowed to open is expected to interrupt under out-of-synchronism conditions,
the breaker at the time when the generator is out of step with the breaker manufacturer should be consulted to determine
the system, the circuit breaker will be subjected to severe the capability of the breaker under these conditions.
conditions. If the interruption occurs when the generator is The protective relaying must trip the generators before a true
exactly 180◦ out of phase with the system, the breaker contacts out-of-synchronism condition occurs to prevent overstressing
may have a voltage across them equal to twice the peak line-to- the interrupting device. Alternatively, the out-of-step relay may
MALMEDAL et al.: OUT-OF-STEP RELAYING FOR SMALL GENERATORS IN DISTRIBUTED GENERATION 1513
be used to block tripping of the breaker until the swing has An in-depth transient stability study can be an expensive
progressed to a point where the breaker is not required to undertaking on a large system. In a small generation project
interrupt under elevated voltage conditions. The 78 relay may sufficient information and funds are often not available to
be employed to block the tripping of other relay elements perform a meaningful study. If a transient stability study is
instead of being used to trip. not undertaken, then the 78 relay should not be used in the
If a generator is connected to an existing distribution sys- system since it cannot be predicted what, if any, effect it will
tem, there may be fuses present on the system. If generator have. This is also consistent with the IEEE Std. 242 recom-
protection is blocked or delayed, these fuses may interrupt mendations. Other types of relaying are capable of sensing
before the generator relaying operates under conditions when and disconnecting the generator from the system during an
the generator is out of step. This will place high voltages across out-of-step condition if the breakers are capable of withstanding
the fuses as they try to interrupt. It is possible that the fuse the stress of an out-of-step interruption.
is unable to interrupt and completely extinguish the arc under If other types of relaying are depended upon to interrupt for
these conditions, resulting in further damage until other types an out-of-step condition, it should operate as fast as possible
of relaying on the circuit operate. Coordination is necessary to allow circuit breakers to clear before a true out-of-step
to determine which fuses on the system may interrupt under condition occurs, which would increase the voltage stress on
these conditions and whether they are capable of interruption the interrupting device.
during an out-of-step condition. If fuses are present, delaying One disadvantage in depending upon other types of relays
or blocking generator protection may not be an option. is that they cannot discriminate between a stable and an un-
stable swing, and will cause a trip for both conditions. For
a small distributed generator, tripping for any swing, stable
VII. C ONCLUSION
or unstable, may be satisfactory. On a small- or medium-
This paper has only examined a few of the myriad of sized generator installation, the following conclusions may be
possible faults that might occur on a distribution system to reached.
which a generator is to be connected. If an out-of-step relay
1) An ANSI no. 78 device should not be set unless sufficient
is used, an in-depth transient stability study is required. This
information is available and an in-depth transient stability
study will require detailed information about the distribution
study is performed.
system including an accurate system model and settings and
2) Relay manufacturer’s preliminary setting methods for
types of relays and fuses used throughout the system. Only by
out-of-step relays are a starting point only, and are not
examining the various system conditions that may cause an out-
sufficient to properly set this relay without the informa-
of-synchronism swing can the optimum settings for the 78 relay
tion provided by a transient stability study.
be calculated.
3) Other relays will likely disconnect the generator for
Relay manufacturers usually suggest a method for mak-
an out-of-step condition due to the high currents and
ing preliminary settings. These preliminary settings cannot be
depressed voltages inherent in such an event. The follow-
relied upon without checking them using the results of the
ing may be used:
stability study [1]. Only in this way can it be determined if these
a) An instantaneous phase over current relay (Device 50)
settings need to be modified to achieve the results necessary
may be set.
for a particular system or if the out-of-step settings and the
b) A voltage restrained phase over current relay (Device
settings of other relays are properly coordinated. It is quite
51V) may be set with the smallest possible time dial,
possible, as shown in the example considered in this paper,
which will still coordinate with other types of relaying
that the other types of relaying in the system would render the
on the system.
78 relay irrelevant to system protection.
c) A voltage-controlled phase over current relay (Device
In generator connections such as the one in Fig. 15, where
51V) may be set. The control voltage may be set at
the 78 relay is applied at the interconnection point instead
50% of the nominal voltage, and the current pickup
of at the generator, false tripping has been witnessed due to
should be set at or slightly above the generator full
inrush currents when the facility loads are energized without
load current and an extremely fast time dial, or a
the generation being on-line. It may be necessary to alter the
short definite time setting (less than five cycles) should
preliminary settings so this relay does not overtrip. The size
be used. This should rapidly disconnect the gener-
of the mho circle and the settings of the blinders should be
ator from the system for a developing out-of-step
adjusted to be as small as possible while still allowing the
condition.
relay to trip for all out-of-step events. Sometimes, a delay is
d) An undervoltage relay (Device 27) may be set at
introduced to try to eliminate the possibility of false tripping.
approximately 50% of the nominal voltage with a
If this is done, the information from the stability study is
short time delay (five cycles).
essential in determining how long a swing can be expected
to keep the impedance between the two blinders so the delay Any of the above devices may be used to disconnect
is not set too long to prevent a trip from occurring for an the generator for an out-of-step condition when insufficient
out-of-step swing. Arbitrarily adding a time delay without information is available to set a Device 78. However, these
understanding its result may totally defeat the ability of the other relays will not discriminate between a stable and an
relay to respond to an out-of-step condition. unstable generator swing. If the out-of-step relay is set to block
1514 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 41, NO. 6, NOVEMBER/DECEMBER 2005
other types of relaying, a transient stability study as well as an Pankaj K. (PK) Sen (S’71–M’74–SM’90) received
understanding of the effect this will have on the generator and the B.S.E.E. degree (with honors) from Jadavpur
University, Calcutta, India, and the M.Eng. and Ph.D.
other protective devices in the system is essential. degrees in electrical engineering from the Technical
University of Nova Scotia (Dalhousie University),
Halifax, NS, Canada.
R EFERENCES He is currently a Professor of Engineering and
[1] J. Berdy, Out-of-Step Protection for Generators, GE Publication No. Director of the Power Systems Engineering Research
GER-3179. Center at the Colorado School of Mines in Golden,
[2] W. D. Stevenson, Jr., Elements of Power Systems Analysis, 4th ed. New CO. His research interests include application prob-
York: McGraw-Hill, 1982. lems in electric machines, power systems, and power
[3] R. D. Evans et al., “Electrical transmission and distribution reference engineering education. He has published more than 70 articles in various
book,” in Power-System Stability Basic Elements of Theory and Appli- archival journals and conference proceedings.
cation, 5th ed. Raleigh, NC: ABB Power T&D Company Inc., 1997, Dr. Sen is a Registered Professional Engineer in the State of Colorado.
ch. 13.
[4] J. L. Blackburn, Symmetrical Components for Power Systems Engi-
neering. New York: Marcel Dekker, 1993.
[5] C. R. Mason, The Art and Science of Protective Relaying. New York:
John P. Nelson (S’73–M’76–SM’82–F’97) received
Wiley, 1954.
the B.S.E.E. degree from the University of Illinois,
[6] E. Clarke, “Impedances seen by relays during power swings with and
Urbana, in 1970, and the M.S.E.E. degree from the
without faults,” AIEE Trans., vol. 64, pp. 372–384, 1945.
University of Colorado, Boulder, in 1975.
[7] IEEE Guide for AC Generator Protection, 1987, New York. C37-102-
He is President and Principal Engineer at NEI
1987.
Electric Power Engineering, Inc., Arvada, CO. He
[8] J. A. Imhof et al., “Out-of-step relaying for generators working group
has authored or coauthored numerous papers, typi-
report,” IEEE Trans. Power App. Syst., vol. PAS-96, no. 5, pp. 1556–1564,
cally involving electric power systems in the petro-
Sep./Oct. 1977.
chemical industry.
[9] P. L. Blackburn, Protective Relaying Principles and Applications. New
Mr. Nelson is a Registered Professional Engi-
York: Marcel Dekker, 1987.
neer in the States of Colorado, Arizona, California,
[10] Recommended Practice for Protection and Coordination of Industrial
Louisiana, New Mexico, Utah, Wisconsin, and Wyoming. He has been active
and Commercial Power Systems, New York: IEEE. (Buff Book), IEEE
with the Petroleum and Chemical Industry Committee of the IEEE Industry
Std. 242-1986.
Applications Society for more the 20 years.
[11] T. F. Bogart, Jr., Electric Circuits. New York: Macmillan, 1988.
[12] IEEE Standard for Interconnecting Distributed Resources With Electric
Power Systems, New York: IEEE, IEEE Std. 1547-2003.
[13] Standard for AC High-Voltage Generator Circuit Breakers Rated on
a Symmetrical Current Basis, New York: IEEE, IEEE Std. C37-013-
1997.