You are on page 1of 30

Presented by:

Dr. Ahmad Tarmizi Bin


Haron
(ahmadtarmizi@ump.edu.my)
019-9000880
FKASA, UMP

Founder of UMP MyBIM


Satellite Center East Coast

Member of Initiative
Working Group 11
Building Information
Modelling
Construction Industry
Transformation
Programme MALAYSIA
2

 PhD in Construction & Property Management specialising in BIM (The University of Salford,
U.K)
 The founder of UMP MyBIM Satellite Center – East Coast Malaysia
 Head of Consultant & Strategist at UMP Holdings Sdn Bhd
 Member of Initiative Working Group 11: BIM: CITP: Ministry of Work Malaysia
 Vast experience in training & education, project implementation and
organisational & industrial transformation of BIM.
About UMP MyBIM Satellite Center East Coast
-Area of specialisation

1. BIM TECHNICAL AND MANAGEMENT TRAINING


a) Satellite Center for CIDB MyBIM Satellite Center (East Coast
Region)
b) CIDB BIM Module (Management and Technical)
c) Customised BIM training for project & organisation
d) Industrial and academic Talk
2. ORGANISATIONAL TRANSFORMATION STRATEGY
a) BIM strategy for organisation
b) BIM coaching and on the job
assistance
3. PROJECT & CONSULTANCY
a) Modelling services
b) 4D Simulation
c) BIM model audit and checking
d) BIM management & execution
e) Object library & content creation
THE CONCEPT OF BUILDING INFORMATION
MODELLING (BIM)
Dr. AHMAD TARMIZI HARON
(ahmadtarmizi@ump.edu.my)
UNIVERSITI MALAYSIA PAHANG (UMP)
FACULTY OF CIVIL ENGINEERING AND EARTH RESOURCES
INTRODUCTION
6

 INFORMATION?

 COMMUNICATION?
Traditional Design & Construction
The Client

DRAWING AS THE MAIN MEDIUM OF COMMUNICATION


DESIGN TEAM CONSTRUCTION TEAM POST CONSTRUCTION

Architect Main Contractor Facilities


Management
Civil & Structural SubCon Supplier
Engineer Occupant/User
Mechanical & Electrical
Engineers
8

 Traditional ‘Over the Wall’ workflow

Image courtesy of Dave Willard, HNTB


CHALLENGES IN CONSTRUCTION INDUSTRY
 In many studies, fragmentation was identified as one of the critical problem and many
believe by resolving the fragmentation issue, the industry could improve significantly.
 Some of the problems, caused by the fragmentation are:
 Information with data generated at one stage could
not automatically available for re-use downstream
 Difficulties in changing and adapting design, planning and
cost estimate.
 Failure to link impacts of design to construction decision The need for
 Poor coordination information
 Difficulties in promoting a collaborative environment integration
 Ineffective communication
 Would allow for information wastage and a lot of
repetition.
 Redundant and replicated work at different interfaces
between department
What is BIM?

PhD Viva/Maxwell 921 7/24/2018


MISCONCEPTION ABOUT BIM
11

 BIM is just 3D Modelling


 Revit is BIM
 BIM takes more time to improve productivity
 BIM is just for big companies and projects
 BIM is solving clash detection
 BIM is difficult or maybe too easy.
 A magic pill to solve entire problems in construction
12
DEFINITION OF BIM
13

BUILDING INFORMATION MODELLING is modeling


TECHNOLOGY and associated set of PROCESS to produce,
communicate, analyze and use DIGITAL INFORMATION
MODELS for construction project life-cycle:
Working definition as endorsed by Malaysia BIM Steering
Committee,2013
WHAT IS BIM?
14

PEOPLE PROCESS
• BIM Manager • Model oriented process flow
• BIM Coordinator • 3D parametric model as


BIM Modeller
Discipline based professional
BIM the main deliverables with
associated data for drawings,
• Leadership specifications, BQ and etc.
• Collaboration • Design intent validation
• Stakeholders engagement • Data & Information driven
decision making
TECHNOLOGY
• Parametric technology software tools
• Hardware
• Facilities
• Interoperability
WHAT IS BIM?
15
16
BUILD IT DIGITALLY

BEFORE……

BUILDING IT PHYSICALLY
WHAT IS BIM (THE PROCESS)
17
WHAT IS BIM (THE PROCESS)
18
19
WHAT IS BIM (THE PEOPLE)
20
WHAT IS BIM (THE TECHNOLOGY)
21

 The concept of parametric objects is central to understanding BIM and its differentiation from traditional 3D
objects. It serves as the main technology in BIM. Parametric BIM consists of the following characteristic
 Consist of geometric defi nitions and associated data and rules.
 Geometry is integrated nonredundantly, and allows for no inconsistencies. When an object is shown
in 3D, the shape cannot be represented internally redundantly, for example, as multiple 2D views. A
plan and elevation of a given object must always be consistent. Dimensions cannot be “fudged.”
 Parametric rules for objects automatically modify associated geometries when inserted into a
building model or when changes are made to associated objects. For example, a door will fi t
automatically into a wall, a light switch will automatically locate next to the proper side of the door, a
wall will automatically resize itself to butt to a ceiling or roof, and so forth.
 Objects can be defi ned at different levels of aggregation, so we can define a wall as well as its
related components. Objects can be defi ned and managed at any number of hierarchy levels. For
example, if the weight of a wall subcomponent changes, the weight of the wall should also change.
 Objects’ rules can identify when a particular change violates object feasibility regarding size,
manufacturability, and so forth.
 Objects have the ability to link to or receive, broadcast, or export sets of attributes, for example,
structural materials, acoustic data, energy data, and the like, to other applications and models.
WHAT IS BIM (THE TECHNOLOGY)
22
23

SOME BASIC APPLICATION


VISUALISATION
24
INTEGRATED DRAWINGS & DESIGN CHANGE IN BIM
25
CLASH DETECTION
26
CENTRALISED DATABASE
27

3D models as main
deliverables

Image courtesy of Dave Willard, HNTB


CONSTRUCTION SEQUENCING (4D BIM)
28
AUTOMATED MTO (5D BIM)
29
THE BENEFITS OF BIM
30

 Lots of benefits gain through BIM, but the implementation still low
 The Nature of 3D Parametric
 Design Visualization
Visualize building early in the process to support and accelerate the
decision making process.
 Schedule Visualization
Visualize construction process to review and optimize the construction
sequence and the schedule.
 Design Validation
Integrate 3D models of all trades to identify interferences and
constructability issues before they materialize in the field.
 Estimating
Tie scope of project to a price;
Manage scope changes more efficiently

Image courtesy of Dave Willard, HNTB


31

The Conclusion is…..?

You might also like