(Example Pictures and Indicators)

TE: Rolando Ignacio Araoz Alborta


TSD Wireless Department
HUAWEI TECHNOLOGIES Co., Ltd.
Appearance and Connection Distribution of the
EMUA

Alarm Signal GND


Cable (RS-485)

Power Supply
Connector (PW1) 16 Available Connectors
Connected to
LOAD1 at the PDU
for 6 Different Sensors:
• Temperature EMUA Type C
• Humidity
• Smoke Model # 4832
• Liquid Level
• Gate
• Infrared
Pictures Of the
Sensors for APM-30
SMOKE SENSOR
Contents:
• Box
• Smoke Detector
Device w/protector
cover
• Chinese Printed
Manual
• 2xWall Screws
• 2xRamplug
TEMPERATURE
& HUMIDITY
SENSOR
Contents:
• Box
• Temp&Humi Device
• Chinese Printed
Manual
• 3xWall Screws
• 3xRamplug
LIQUID LEVEL
SENSOR
Contents:
• Box
• Temp&Humi Device
• Chinese Printed
Manual
• 3xWall Screws
• 3xRamplug
Types of Materials Needed for
Installing Sensors

Cross Screwdriver Small Flat Screwdriver

Color Cables Included w/Material


Contents:
Silicone Gel Cable Ties

• 1 x Green Electronic Cable x 5m

• 1 x White Electronic Cable x 5m

• 1 x Red Electronic Cable x 5m

• 1 x Black Electronic Cable x 5m


Cable Strippers Sharp Cutter
Wiring Installation Step-by-Step of the
Smoke Sensor

1 2

Need: 2 x Colored Cables (Red +, Black –) x 1m each Side A: Device, Side B (Face up): Wall Attachment Panel

3 4

Side B: Identification # 1 Negative (-) / Black Cable Side B: Identification # 3 Negative (+) / Red Cable
5 6

Strip the end of the cables about 0.5cm with the cable strippers. Connect cables according to Step 3 & 4

7 8

Side B (Face Down; Step 2): Cut the dotted red line drawn in Final Work of the other Steps
the picture
9 10

Strip the end of the cables about 0.5cm with the cable strippers. Take the Screw shown above from the Mini-Shelter

11 12

Use the screw taken in Step 10 to strap Side B to the door of Final Work of the Steps 9 to 11
the APM-30
13 14

Make sure to pass the cables thru as shown in the picture Use Cable ties; at the door and inside the APM-30

15 16

Remember to use Translucent Silicone Gel following the cyan Final Work of the Steps 13 to 15
line shown above; make it look nice and professional.
Wiring Installation Step-by-Step of the
Temperature & Humidity Sensor
1
2

Need: 2 x Cables (Black –) x 60cm each Enclosure B: Strip the tip of the cables about 0.5cm then connect
1 x Cable (White +) x 60cm the 2 x (Black –) Cables to the negative terminals (T-, H-),
1 x Cable (Green +) x 60cm connect the (White +) Cable to the T+ terminal and
connect the Cable (Green +) to the H+ terminal

3 4

This is how it should look like after Step 2 Pass the cables thru the apertures shown above with red arrows
5 6

Close enclosures A and B together and place it and fix it with Be generous with the Silicone Gel but do not exaggerate, this is
Silicone Gel in the spot shown above (red dotted lines) notice the final work of the steps 1 thru 5
that the spot is behind all cables.
Wiring Installation Step-by-Step of the
Liquid Level Sensor
1
2

The cable of the sensor device has 2.7m and 3 colored cables Pass the cable next to the Tem&Humi device and inside of the
inside Green, Red and White. aperture 1 shown above

3 4

After passing it thru the aperture we will place it under the


APM-30 attached to the supporting base
This is the final work of the Steps 1 to 3, remember to place
above 2cm of the ground and use a cable tie to secure it.
Connections Step-by-Step of the
Electronic Connection

1 2

Electronic Installation Diagrama Final Work of the Steps 1


Overview
Final Details

Make sure to use as many cable ties as needed, remember it has to look nice and professional.