METHOD STATEMENT FOR


INSTALLATION OF ELECTRICAL
DB, SMDB AND MDB
PANELBOARDS
///

 0

Method Statement For Installation of DB, SMDB and MDB.

1. INTRODUCTION AND SCOPE


This statement is written for the purpose of establishing method and procedures for the Installation of DB,
SMDB and MDB.
2. APPLICABLE PROJECTS SPECIFICATION
Section: SWITCHBOARD DISTRIBUTION PANELS AND MCCs.
Division: INSTALLATION
Sub Division: Subdivision

3. LOCATION OF ACTIVITY
Low Voltage Room and Electrical Rooms

4. HEALTH AND SAFETY HAZARDS


Specific safety measures have to follow as applicable, and all the safety measures are covered separately in
the project safety plan.
5. OPERATION
1. Materials: Materials used will be as per the material submittal approved by the engineer and will be as
per the approved drawings in coordination with other services.
2. Storage / Protection: DB, SMDB, and MDB and Accessories shall be unloaded with care to avoid any
damages. If they are shipped in packs or pallets, each pack of pallet shall be lifted individually with
suitable lifting equipment. Every precaution shall be taken to preserve their cleanliness before
installation. Store in accordance with manufacturer’s instructions, Properly protected from construction
activities and weather conditions.
3. Installation:
1. To make sure that the entire installation is in conformance and in accordance with the design
intent of the project for the Electrical and Low Voltage System in addition to the specification and
as per approved shop drawings and comply.
2. with local and International Standards.
3. All the switchboards shall be fabricated at the manufacturer’s works.
4. Before beginning installation in any area, examine all parts of the adjoining works into which
applicable work is to be placed. Should any condition be found which will prevent the proper
execution of the work, installation shall not proceed in that area until such conditions are
corrected by the contractor.
5. Fix all equipment independently of wiring system. Use cadmium of zinc electroplated bolts, nuts,
washers and screw.
6. Mount single DB at 1800mm from finish floor level to top of equipment, unless shown otherwise
on drawing / schedules.
7. Ensures that clearance in front of switchgear is not less than 1m, or as indicated.
8. Number terminals, cables and component parts to correspond with manufacturer have certified
drawings.
9. Terminate PVC, SWA PVC and MICS cables inside enclosure by securing cables to switchboards
with gland bracket; and enclosure with glanding plates or fabricated steel extension boxes.
10. For flush installation, DB’s all conductors shall terminate behind the board in an adaptable box.
For surface mounting, trunking shall be fixed between the board and ceiling or floor level, or
conduit run directly into Trunking which prevent correct installation of the Trunking lid. Adequate
earth continuity shall be made between the various components.

6. RESPONSIBILITIES

1. PROJECT MANAGER
1. To ensure that all the preparation and application works are carried out according to the Contract
Specification.
2. To ensure that the progressing of works is carried out according to the planned program and as
per the approved method statement.
3. To ensure that all equipment and material required executing the work are available according to
the planned Construction Programme.
4. To co-ordinate with the Main Contractor, MEP co-coordinator, and Safety Officer for a safe and
proper execution of the works.

2. SITE ENGINEER
1. To ensure that the works are carried out according to the Contract Specifications approved
method statement.
2. To provide all necessary information and distribute responsibilities to his construction team.
3. To monitor the progress of work in relation with the work program and to report to the Project
Manager.
4. To co-ordinate with the safety officer and to ensure that the works are carried out in safe
practicing methods.

3. FOREMAN
1. The foreman will carry out his duties by maintaining continuous coordination with the site
engineer on daily basis, and ensure proper distribution of the workforce in the required and
planned locations.
2. To ensure that his assistant foreman/ charge hand are aware of the job requirements and they
have enough information to carry out their duties properly.
3. To ensure in consultation with the site engineer that the manpower involved in the works are
moving as agreed and planned for the work.
4. To ensure that the daily work is progressing as planned and advise the Site Engineer for any
requirement of the additional resources.
5. To control disposal of waste materials to the instructions received from the site engineer.
6. To ensure full coordination with the safety officer to maintain safe working and proper house
keeping of the site, following the approved safety measures and further ensure that all his
working team are aware of the same to prevent accident and losses.
7. After completion of works, Foreman shall inform the site engineer for inspection of works.
8. Distribution and the control of materials shall be monitored by foreman and storekeeper.

4. SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in accordance with the HSE plan and
everybody aware of it for it’s proper implementation.
2. Ensure all the implemented safety measures are adequate to maintain safe working on the site.
3. Inspect all the site activities and train the person to prevent accidents and it’s proper
implementation.
4. Ensure that the site is maintained clean and tidy.

7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
DB, SMDB, MDB and accessories

9. EQUIPMENT REQUIREMENT
The equipment that will be engaged for Installation of DB, SMDB and MDB works will be as follows:

1. Wire cutters
2. Measuring tape
3. Drill machine
4. Wooden hammer
5. Flat file
6. Screw drivers
7. Open and box spanners
8. Crimping tool

10. HEALTH AND SAFETY


Strictly follow as per the manufacturer’s Health and Safety recommendations for handling and use of the
materials. Ensure all involved personal shall be aware of the same.

11. SUPPORTING DOCUMENTATION


This method Statement should be read in conjunction with the below referenced documentations.

ITP for Anti – termite Treatment


Insulation Resistance and continuity Test Report

12. DISTRIBUTION
Copy of this method statement shall be issued to the following for information/ action/ comments:

1. Project Manager
2. Site Engineer
3. Foremen

13. INSPECTION AND TEST PLAN FOR


INSTALLATION OF DB, SMDB AND MDB

ITP INSPECTION TYPE OF REFERENCE TESTING VERIFYING


CLAUSE DESCRIPTION INSPECTION DOCUMENT REQUIREMENT/ / CONTROL
NO ACCEPTANCE DATA
CRITERIA FORMS

1 Design and Review of Design All the Drawings Design


Drawings Documents Drawings drawings,
Authorities
Departments
Requirements.

2 Material Review of Approved Should be as per Submittals


Approval Documents Drawing and the approved Documents
Specification drawing and
Specification

3 Check Visual, Approved Proper location Approved


Switchgear Insulation Method installation, Drawing
installation and Resistance Statement termination etc Method
cable and Continuity Material should Statement
terminations. Test Report have minimum
status of – NO
Objection with
comments

4 Request for Visual, Approved No obstructions Approved


inspection of Insulation Drawing Level, and it is in Drawings
works Resistance proper position
and Continuity
Test report.

TAGS

METHOD STATEMENT ELECTRICAL ENGINEERING CONSTRUCTION ENGINEERING ELECTRICAL INSTALLATION

ELECTRICAL SMDB INSTALLATION WIRING METHOD


‹ Method Statement For Installation Of up Method Statement For The Installation Of
Galvanized Conduits On Exposed Surface Power and Lighting System Wiring ›

ADD NEW COMMENT 

Custom Search SEARCH

 About Lopol
 Banking System
 Construction Quality Plan for Building Projects
 Consumer Rights In India
 Electrical Engineering
- Automatic Transfer Switch (ATS) OR Automatic Mains Failure (AMF) Panel

- DC Power Supply in Medium Voltage Distribution System Construction Works

- Emergency Power Diesel Generating Set In Electrical Construction Works

- Fire Alarm System In Electrical Construction Works

- Fire Alarm System: Introduction and Importance of Fire Alarm System

- Fire Detection And Alarm System In Electrical Construction Works

- Grounding System In Electrical Construction Contract Works

- Guidelines for Installation of Emmergency Power Diesel Electrical Generating Set

- High Voltage and Low Voltage Power Cables In Electrical Construction Works

- Indoor MV Distribution Panel Boards In Electrical Construction Works

- Lighting Distribution Boards In Electrical Construction Works

- Lighting Fixtures In Building Projects

- Low Voltage Switchgears in Electrical Construction Works

- Master Antenna TV System (MATV) In Electrical Construction Works

- Medium Voltage Cables (MV Cables) In Electrical Construction Works

- Medium Voltage Distribution System In Electrical Construction

- Method Statement For Installation Of Cable Tray Or Trunking


- Method Statement For Installation Of Electric PVC Conduits And Accessories

- Method Statement For Installation Of Galvanized Conduits On Exposed Surface

- Method Statement For Installation of Electrical DB, SMDB and MDB Panelboards

- Method Statement For The Installation Of Power and Lighting System Wiring

- Public Address System In Electrical Construction Contract

- Requirements of Diesel Powered Electricity Generation Plant in Building Services

- Specification For Conduit Wiring In Electrical Construction Contract Works

- Specification For Earthing And Lightning Protection In Electrical Construction Contract Works

- Specification for General Conditions And Requirements Under Electrical Construction Contract Works

- Specification for Medium Voltage Switch Gears In MV Electrical Construction Works

- Specification for Transformers in MV Distribution System

- Structured Cabling For Communications - Wiring For Voice / Data In Building Construction Works

- Technical Submittals Required for Electrical Earthing / Grounding

- Telephone System In Electrical Construction Works

- Testing and Commissioning In Electrical Construction Works

- Vacuum Air Circuit Breakers in MV Distribution System for Electrical Construction

- Vacuum Interrupter (VI) for Vacuum Circuit Breakers (VCB)

- Wiring Materials And Installation Methods in Electrical Construction Works

 Engineering and Technology


 MEP Specifications For Building Construction
 Sample Control Guidelines of a Construction Project
 Typical Installation Details and Drawings for Construction Projects
 Useful Tips and Tricks

Username *

Password *

Create new account


Request new password
LOG IN

RELATED POSTS TO METHOD STATEMENT:

METHOD STATEMENT FOR


METHOD STATEMENT FOR
INSTALLATION OF CABLE
INSTALLATION OF
TRAY OR TRUNKING
GALVANIZED CONDUITS ON
EXPOSED SURFACE

METHOD STATEMENT FOR


METHOD STATEMENT FOR
THE INSTALLATION OF
INSTALLATION OF ELECTRIC
POWER AND LIGHTING
PVC CONDUITS AND
SYSTEM WIRING
ACCESSORIES
  ELECTRICAL ENGINEERING  METHOD STATEMENT FOR INSTALLATION OF ELECTRICAL DB, SMDB AND MDB PANELBOARDS

TRY OUT
Standard Commercial Product for Lighting Columns

Private Sector Commercial Banks in India

Types of Construction contracts: Lumpsum contract

LATEST CONTENT
Find Company Master Data Using Company CIN No. in www.mca.gov.in

State Bank Of India (SBI) Corporate Internet Banking (CINB) For Current Account Holders

Google Local Guides: 10 Levels To Reach, More Points, Rewards, and New Badges

RECENT COMMENTS

Yes you can change. Link 17

"This was a very nice and

Npci not linked


TODAY'S POPULAR

NFSA Ration Card Categories - Antyodaya (AYY), Priority (PHH), Non-Priority (NPHH), State Priority

SBI Bank Loan Scheme For Schools - School Plus

Corporate Identification Number or Company CIN No. in India

Google+ || Facebook.com

© 2018. Lopol.org. All Rights Reserved.


You might also like