You are on page 1of 95

ZXMW NR8950

Digital Microwave Transmission System


Hardware Installation Guide

Version: V2.04.02

ZTE CORPORATION
No. 55, Hi-tech Road South, ShenZhen, P.R.China
Postcode: 518057
Tel: +86-755-26771900
Fax: +86-755-26770801
URL: http://support.zte.com.cn
E-mail: 800@zte.com.cn
LEGAL INFORMATION
Copyright © 2016 ZTE CORPORATION.
The contents of this document are protected by copyright laws and international treaties. Any reproduction or
distribution of this document or any portion of this document, in any form by any means, without the prior written
consent of ZTE CORPORATION is prohibited. Additionally, the contents of this document are protected by
contractual confidentiality obligations.
All company, brand and product names are trade or service marks, or registered trade or service marks, of ZTE
CORPORATION or of their respective owners.
This document is provided “as is”, and all express, implied, or statutory warranties, representations or conditions
are disclaimed, including without limitation any implied warranty of merchantability, fitness for a particular purpose,
title or non-infringement. ZTE CORPORATION and its licensors shall not be liable for damages resulting from the
use of or reliance on the information contained herein.
ZTE CORPORATION or its licensors may have current or pending intellectual property rights or applications
covering the subject matter of this document. Except as expressly provided in any written license between ZTE
CORPORATION and its licensee, the user of this document shall not acquire any license to the subject matter
herein.
ZTE CORPORATION reserves the right to upgrade or make technical change to this product without further notice.
Users may visit the ZTE technical support website http://support.zte.com.cn to inquire for related information.
The ultimate right to interpret this product resides in ZTE CORPORATION.

Revision History

Revision No. Revision Date Revision Reason

R1.1 2016-01-27 l Added the installation of the 2+0 XPIC configuration in “3.2.3
2+0 Buckle Installation”.
l Added the Installation of antenna in “Appendix B Installing
Antenna”.
l Added the installation and cable connection of the PIMDC in
“Appendix D, Installing the PIMDC”.
l Added the Installation of PSE in “Appendix E Installing PSE”.
l Added the completed installation in the power cable scenario,
PoE scenario, and AC power supply scenario in “Section 1.1
Completed Installation”.
l Added the steps of making the power cable plug in “Section
3.3 Installing the Power Cable”.
l Added the wire sequence description of the 568B standard
straight network cable in “Section 3.4.1 Installing the Ethernet
Cable”.
l Added the cross-connection description of the 2+2 XPIC
HSB protection configuration and the 2+2 XPIC SD
protection configuration in “Section 3.6 Installing the XPIC
Cross-Connection Cables (Optional)”.

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Revision No. Revision Date Revision Reason

l Added steps to adjust the XPD value in “2.1.3 2+0 Buckle


Installation”.

R1.0 2015-11-25 First Edition

Serial Number: SJ-20151105160201-004

Publishing Date: 2016-01-27 (R1.1)


Contents
About This Manual ......................................................................................... I
Chapter 1 Overview .................................................................................... 1-1
1.1 Completed Installation ........................................................................................ 1-1
1.2 Installation Flow ................................................................................................. 1-4
1.3 Installation Precautions....................................................................................... 1-5
1.4 Preparation for Tools and Instruments.................................................................. 1-6

Chapter 2 ZXMW NR8950 Installation....................................................... 2-1


2.1 Buckle Installation .............................................................................................. 2-3
2.1.1 1+0 Buckle Installation.............................................................................. 2-3
2.1.2 1+1 Buckle Installation.............................................................................. 2-8
2.1.3 2+0 Buckle Installation............................................................................ 2-14
2.2 Separate Installation......................................................................................... 2-21
2.2.1 1+0 Separate Installation (Single-Polarization) ......................................... 2-21
2.2.2 1+1 Separate Installation (Single-Polarization) ......................................... 2-26
2.2.3 2+0 Separate Installation (Dual-Polarization)............................................ 2-29
2.2.4 2+2 Separate Installation (Dual-Polarization)............................................ 2-33

Chapter 3 Cable Installation ...................................................................... 3-1


3.1 Cable Installation Requirements .......................................................................... 3-1
3.2 Installing the Protective Grounding Cable............................................................. 3-2
3.3 Installing the Power Cable .................................................................................. 3-3
3.4 Installing the Ethernet Cable ............................................................................... 3-5
3.5 Installing the Optical Fiber................................................................................... 3-7
3.6 Installing the XPIC Cross-Connect Cables (Optional)............................................ 3-8

Chapter 4 Installation Check ..................................................................... 4-1


4.1 Installation Check for the ZXMW NR8950 ............................................................ 4-1
4.2 Cable Installation Check ..................................................................................... 4-2

Chapter 5 Power On and Power Off.......................................................... 5-1


5.1 Power on ........................................................................................................... 5-1
5.2 Power off ........................................................................................................... 5-3

Appendix A Antenna Pole Installation (Optional)................................... A-1


A.1 Installing the Pole on the Roof of a Building ......................................................... A-1
A.2 Installing the Pole on an Angle Steel Tower ......................................................... A-3

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix B Installing Antenna ................................................................ B-1
Appendix C Antenna Adjustment (Optional) .......................................... C-1
C.1 Adjusting the Polarization Mode of an Antenna ....................................................C-1
C.2 Adjusting the Antenna Azimuth ...........................................................................C-4
C.3 Adjusting the Antenna Pitch Angle ......................................................................C-5

Appendix D Installing the PIMDC............................................................. D-1


Appendix E Installing the PSE ..................................................................E-1
Glossary .......................................................................................................... I

II

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


About This Manual
Purpose
This manual describes the hardware installation procedure of the ZXMW NR8950 digital
microwave system, to guide installation engineers to install the ZXMW NR8950 correctly,
safely and in compliance with specifications.

Intended Audience
This manual is intended for:

l Equipment installation engineers


l Installation supervision engineers
l Maintenance engineers

What Is in This Manual


This manual contains the following chapters and appendix.

Chapter 1, Overview Describes the ZXMW NR8950 hardware


installation flow, precautions, and preparation for
tools and instruments.

Chapter 2, ZXMW NR8950 Installation Describes how to install the ZXMW NR8950.

Chapter 3, Cable Installation Describes how to install the cables of the ZXMW
NR8950.

Chapter 4, Installation Check Describes the checking process after the ZXMW
NR8950 installation is completed.

Chapter 5, Power On and Power Off Describes how to power on and power off the
ZXMW NR8950.

Appendix A, Antenna Pole Installation (Optional) Describes antenna pole installation.

Appendix B, Installing Antenna Describes antenna installation.

Appendix C, Antenna Adjustment (Optional) Describes antenna azimuth adjustment.

Appendix D, Installing the PIMDC Describes how to install the PIMDC and its
cables.

Appendix E, Installing the PSE Describes how to install the PSE.

Conventions
This manual uses the following conventions.

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Danger: indicates an imminently hazardous situation. Failure to comply can result in
death or serious injury, equipment damage, or site breakdown.

Warning: indicates a potentially hazardous situation. Failure to comply can result in


serious injury, equipment damage, or interruption of major services.

Caution: indicates a potentially hazardous situation. Failure to comply can result in


moderate injury, equipment damage, or interruption of minor services.

Note: provides additional information about a topic.

II

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 1
Overview
Table of Contents
Completed Installation ................................................................................................1-1
Installation Flow .........................................................................................................1-4
Installation Precautions ..............................................................................................1-5
Preparation for Tools and Instruments ........................................................................1-6

1.1 Completed Installation


Powered Through a Power Cable
If the ZXMW NR8950 is powered through a power cable, it is directly connected to the DC
power supply equipment through the DC lightning protection module (PIMDC), see Figure
1-1.

1-1

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 1-1 Completed Installation (Powered Through a Power Cable)

1. Antenna 3. DC lightning protection 4. Operating terminal


2. NR8950 module 5. DC power supply

Powered Through PoE


In a PoE power supply scenario, the ZXMW NR8950 is connected to the PSE module by
an Ethernet cable connected to the Ethernet electrical interface (GbE1&PoE), see Figure
1-2.

1-2

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 1 Overview

Figure 1-2 Completed Installation (PoE)

1. NR8950 3. PES module 5. Operating terminal


2. Antenna 4. DC power supply

Powered by an AC Power Supply


In an AC power supply scenario, the AC-DC power supply equipment is used to convert
the AC voltage (90 V AC–290 V AC) to the DC voltage (–54 V DC), see Figure 1-3.

1-3

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 1-3 Completed Installation (AC Power Supply)

1. Antenna 4. AC-DC power supply 6. Photoelectric converter


2. NR8950 equipment (used for commissioning)
3. DC lightning protection 5. Operating terminal
module

1.2 Installation Flow


For the ZXMW NR8950 installation flow, see Figure 1-4.

1-4

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 1 Overview

Figure 1-4 Installation Flow

1.3 Installation Precautions


The following precautions must be noted for hardware installation:

l Non-professionals should not install or debug the system unless they are instructed
by professionals on the site.
l Installation personnel must be very careful of personal safety, and avoid accidents
such as electric shocks or personal injury due to falling objects.
l To avoid eye injury caused by laser beams, installation personnel must not directly
look at the cross-section of any optical fiber or the socket of an optical terminal during
the installation of optical fibers.
l Replacing any part or a device might result in unexpected dangers. Therefore,
replacement of any part or a device can be implemented only after authorization is
acquired.
l To ensure your safety, contact ZTE Corporation if you have any question.

1-5

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

1.4 Preparation for Tools and Instruments


Prepare tools and instruments listed in Table 1-1, and use them in accordance with the
actual requirements.

Table 1-1 Tools and Instruments

Name Example Name Example

Antistatic wrist Spanner


glove

Wire stripper Crimper

Crystal Wire
connector punchdown
crimper tool

Hex wrench Screwdriver

Plier Paper knife

Crowbar Telescope

1-6

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 1 Overview

Name Example Name Example

Pulley PVC insulating


tape

Hand file Marking pen

Waterproof Hoisting cable


cement

Tape Sleeve

Multimeter Grounding
resistance
tester

Compass GPS

1-7

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

This page intentionally left blank.

1-8

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2
ZXMW NR8950 Installation
Installation Modes
l In accordance with installation types, the ZXMW NR8950 installation falls into two
types: buckle installation and split installation.
l In accordance with the configured amount of the ZXMW NR8950 and antenna, the
ZXMW NR8950 installation falls into two types: installation with a combiner and
installation without any combiner.
For ZXMW NR8950 installation modes, refer to Table 2-1.

Table 2-1 ZXMW NR8950 Installation Modes

Installation Mode Single-Polarized Antenna Dual-Polarized Antenna

Buckle Without For detailed information of the -


installa- combiner installation process, refer to “2.1.1
tion 1+0 Buckle Installation”.

With combiner l For detailed information of the -


installation process, refer to
“2.1.2 1+1 Buckle Installation”.
l For detailed information of
the installation process, refer
to“2.1.3 2+0 Buckle Installation”

Split in- Without For detailed information of the For detailed information of the
stalla- combiner installation process, refer to installation process, refer to
tion “2.2.1 1+0 Separate Installation “2.2.3 2+0 Separate Installation
(Single-Polarization)”. (Dual-Polarization)”.

With combiner For detailed information of the For detailed information of the
installation process, refer to installation process, refer to
“2.2.2 1+1 Separate Installation “2.2.4 2+2 Separate Installation
(Single-Polarization)”. (Dual-Polarization)”.

Adjusting Polarization Mode


This procedure describes how to adjust the ZXMW NR8950 polarization mode during the
installation process. Here, the vertical polarization adjustment is used as an example.
1. Loose the guide screws anticlockwise, and remove the guide pin from the guide hole,
see Figure 2-1.

2-1

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 2-1 Removing the Guide Pin

2. Rotate the guide pin 90° clockwise (from “V” to “H”), and place the guide pin marked
with “H” upwards, see Figure 2-2.

Figure 2-2 Adjusting the Guide Pin Direction

Note:
During the guide pin adjustment, please strictly perform the related operations in
compliance with the directions mentioned in Figure 2-2.

3. Place the guide pin on the guide hole, and tighten the guide screws clockwise, see
Figure 2-3.

2-2

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-3 Installing the Guide Pin

Table of Contents
Buckle Installation ......................................................................................................2-3
Separate Installation.................................................................................................2-21

2.1 Buckle Installation


2.1.1 1+0 Buckle Installation
For the installation components and tools used in 1+0 buckle installation, refer to Table
2-2.

2-3

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Table 2-2 Installation Components and Tools Used in 1+0 Buckle Installation

Compo- Qua- Graph


nent / Tool ntity

Antenna One

ZXMW One
NR8950

Hex One
wrench set

Lubricant One -

Prerequisite
The ZXMW NR8950 polarization mode is the same as that of the antenna.

Steps
1. Remove the waveguide diaphragm from the ZXMW NR8950's antenna interface, see
Figure 2-4.

2-4

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-4 Removing the Waveguide Diaphragm

2. Put lubricant on the antenna interface of the ZXMW NR8950 and the waveguide
interface of the antenna, see Figure 2-5.

Figure 2-5 Putting Lubricant

1. ZXMW NR8950 3. Antenna waveguide


antenna interface interface
2. Lubricant 4. Waterproof rubber ring

Caution!

The waterproof rubber ring must be in good condition.

2-5

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

3. Align the antenna interface of the ZXMW NR8950 with the feeder source, slowly insert
it into the waveguide interface of the antenna, and verify that the screw hole on the
ZXMW NR8950 is aligned with the corresponding screw hole on the antenna, see
Figure 2-6.

Figure 2-6 Installing the ZXMW NR8950

4. Fasten four M6 captive screws about 70% of the screw depth into the screw holes,
and secure the screws one by one in diagonal sequence, see Figure 2-7.

2-6

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-7 Securing Screws

– End of Steps –

Result
The ZXMW NR8950 is installed completely in 1+0 buckle installation, see Figure 2-8.

2-7

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 2-8 ZXMW NR8950 1+0 Buckle Installation Completed

2.1.2 1+1 Buckle Installation


For installation components and tools used in 1+1 buckle installation, refer to Table 2-3.

Table 2-3 Installation Components and Tools Used in 1+1 Buckle Installation

Compo- Qua- Graph


nent / Tool ntity

Antenna One -

2-8

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Compo- Qua- Graph


nent / Tool ntity

Combiner One

ZXMW Two -
NR8950

Hex wrench One -


set

Lubricant One -

Before installing the ZXMW NR8950, installation personnel must verify that the polarization
mode of the combiner is the same as that of the antenna. For the combiner polarization
mode adjustment), see Figure 2-9. Here, the adjustment from horizontal polarization to
vertical polarization is used as an example.

Figure 2-9 Adjusting the Polarization Mode of a Combiner

1. Remove the screws from 3. Install the screws on the


the polarization plate polarization plate.
2. Rotate the polarization 4. The vertical polarization
plate 45° clockwise. adjustment is completed.

Steps
1. Remove the waveguide diaphragm from the ZXMW NR8950 antenna interface, refer
to “step 1” in “2.1.1 1+0 Buckle Installation”.

2-9

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

2. Put lubricant on the antenna interface of the ZXMW NR8950, the waveguide interface
of the antenna, and the combiner interfaces, see Figure 2-10.

Figure 2-10 Putting Lubricant

1. ZXMW NR8950 3. Antenna waveguide 5. Combiner interfaces


antenna interface interface
2. Lubricant 4. Waterproof rubber ring

Caution!

The waterproof rubber ring must in good condition.

3. Install the combiner on the feeder source of the antenna, see Figure 2-11.

2-10

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-11 Installing the Combiner

Caution!
Fasten the four captive screws of the combiner about 70% of the screw depth into the
screw holes, and secure the screws one by one in diagonal sequence.

4. Install two ZXMW NR8950s on the two sides of the combiner, see Figure 2-12.

2-11

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 2-12 Installing the ZXMW NR8950

Caution!
Fasten the four captive screws of each ZXMW NR8950 about 70% of the screw depth
into the screw holes, and secure the screws one by one in diagonal sequence, see
Figure 2-13.

2-12

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-13 Fastening screws

– End of Steps –

Result
The ZXMW NR8950 is installed completely in 1+1 buckle installation, see Figure 2-14.

2-13

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 2-14 ZXMW NR8950 1+1 Buckle Installation Completed

2.1.3 2+0 Buckle Installation


For installation components and tools used in 2+0 buckle installation, refer to Table 2-4.

Table 2-4 Installation Components and Tools Used in 2+0 Buckle Installation

Component/ Qua- Graph


Tool ntity

Antenna one -

2-14

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Component/ Qua- Graph


Tool ntity

OMT one

ZXMW NR8950 two -

Hex wrench one -


set

Lubricant one -

Prerequisite
The OMT polarization modes are the same as that of the ZXMW NR8950.

Steps
1. Remove the waveguide diaphragm from the ZXMW NR8950 antenna interface, refer
to “step 1.” in “2.1.1 1+0 Buckle Installation”.
2. Apply a lubricant on the antenna interface of the ZXMW NR8950, the waveguide
interface of the antenna, and the OMT interfaces, see Figure 2-15.

2-15

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 2-15 Applying a Lubricant

1. ZXMW NR8950 3. Antenna waveguide 5. OMT interfaces


antenna interface interface
2. Lubricant 4. Waterproof rubber ring

Caution!

The waterproof rubber ring must in good condition.

3. Install the OMT on the feeder source of the antenna, see Figure 2-16.

2-16

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-16 Installing the OMT

Caution!
Screw six M6 captive screws of OMT in about 70% of the depth and tighten screws in
diagonal sequence.

4. Install two ZXMW NR8950 on the two sides of the OMT, see Figure 2-17.

2-17

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 2-17 Installing ZXMW NR8950

5. Screw four M6 captive screws of each ZXMW NR8950 in about 70% of the depth and
tighten screws in diagonal sequence, seeFigure 2-18.

2-18

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-18 Securing Screws

6. Perform the following steps to adjust the cross-polarization discrimination (XPD) value:
a. Stop the horizonatally-polarized transmit signals of the opposite end.
b. Use the multimeter to measure the vertically-polarized singals of the local end, and
adjust the XPD bolt to minimize the XPD value.
c. Stop the vertically-polarized transmit signals of the opposite end.

d. Use the multimeter to measure the horizonatally-polarized singals of the local end,
and adjust the XPD bolt to minimize the XPD value.
e. Repeat steps a-d to optimize the XPD value.

– End of Steps –

Result
The ZXMW NR8950 is installed completely in 2+0 buckle installation mode, see Figure
2-19.

2-19

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 2-19 2+0 Buckle Installation Completed

Related Tasks
After the ZXMW NR8950 is installed, in the antenna adjusting process, the vertical or
horizontal azimuth can be adjusted within the range of ± 5 ° through polarization fine
adjusting unit, see Figure 2-20.

2-20

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-20 Adjusting the azimuth of OMT

2.2 Separate Installation


2.2.1 1+0 Separate Installation (Single-Polarization)
This procedure uses the single-polarized antenna manufactured by SHENGLU
Corporation as an example to describe how to install a ZXMW NR8950 in 1+0 separate
installation mode.
For installation components and tools used in 1+0 separate installation, refer to Table 2-5.

2-21

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Table 2-5 Installation Components and Tools Used in 1+0 Separate Installation

Compo- Qua- Graph


nent / Tool ntity

Single- One
polarized
antenna

ZXMW One -
NR8950

Installation One
bracket

Flexible One
waveguide

Hex wrench One -


set

Adjustable One -
wrench

2-22

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Compo- Qua- Graph


nent / Tool ntity

Screw- One -
driver set

Lubricant One -

Flexible - -
waveguide
clamp (for
flexible
waveguide
over 0.6 m)

Steps
1. Install the separate installation bracket on the pole, see Figure 2-21.

Figure 2-21 Installing the Installation Bracket

1. Nut 3. Flat washer 5. Bolt


2. Spring washer 4. Installation bracket

2. Remove the waveguide diaphragm from the ZXMW NR8950's antenna interface, refer
to “step 1” in “2.1.1 1+0 Buckle Installation”.

3. Install the ZXMW NR8950 on the installation bracket, see Figure 2-22.

2-23

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 2-22 Installing the ZXMW NR8950

Caution!

Fasten the four captive screws of the ZXMW NR8950 about 70% of the screw depth
into the screw holes, and secure the screws one by one in diagonal sequence.

4. Install the UDR end of the flexible waveguide on the single-polarized antenna, and
install the PDR end of it on the installation bracket, see Figure 2-23.

2-24

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-23 Installing the Flexible Waveguide

5. Use flexible waveguide clamps to fix the flexible waveguide, put lubricant on the flexible
waveguide surface, and paste labels on the two ends of the flexible waveguide.

Note:
Flexible waveguides shorter than 0.6 m need not be fixed. Flexible waveguides longer
than 0.6 m should be fixed by flexible waveguide clamps.

– End of Steps –

Result
The ZXMW NR8950 is installed completely in 1+0 separate installation mode (here, the
antenna is single-polarized), see Figure 2-24.

2-25

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 2-24 ZXMW NR8950 1+0 Separate Installation Completed (Single-Polarized


Antenna)

2.2.2 1+1 Separate Installation (Single-Polarization)


This procedure uses the single-polarized antenna manufactured by SHENGLU
Corporation as an example to describe how to install ZXMW NR8950s in 1+1 separate
installation mode.
For installation components and tools used in 1+1 separate installation, refer to Table 2-6.
Table 2-6 Installation Components and Tools Used in 1+1 Separate Installation

Component/Tool Quantity

Single-polarized antenna One

Combiner One

ZXMW NR8950 Two

Installation bracket One

Flexible waveguide One

Hex wrench One set

Adjustable wrench One

Screwdriver One set

Lubricant One

Flexible waveguide clamp (for -


flexible waveguide over 0.6 m)

2-26

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Steps
1. Install the installation bracket on the pole, refer to “step 1” in “2.2.1 1+0 Separate
Installation (Single-Polarization)”.

2. Install the combiner on the installation bracket, see Figure 2-25.

Figure 2-25 Installing the ZXMW NR8950 Combiner

Caution!
Fasten the four captive screws of the combiner about 70% of the screw depth into the
screw holes, and secure the screws one by one in diagonal sequence.

3. Remove the waveguide diaphragm from the ZXMW NR8950's antenna interface, refer
to “step 1” in “2.1.1 1+0 Buckle Installation”.

4. Install the two ZXMW NR8950s on the combiner, see Figure 2-26.

2-27

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 2-26 Installing the ZXMW NR8950

Caution!
Fasten the four captive screws of the ZXMW NR8950 about 70% of the screw depth
into the screw holes, and secure the screws one by one in diagonal sequence.

5. Install the UDR end of the flexible waveguide on the single-polarized antenna, and
install the PDR end of it on the installation bracket.
6. Use flexible waveguide clamps to fix the flexible waveguide, put lubricant on the flexible
waveguide surface, and paste labels on the two ends of the flexible waveguide.

Note:
Flexible waveguides shorter than 0.6 m need not be fixed. Flexible waveguides longer
than 0.6 m should be fixed by flexible waveguide clamps.

– End of Steps –

Result
The ZXMW NR8950 is installed completely in 2+0 separate installation mode (here, the
antenna is dual-polarized), see Figure 2-27.

2-28

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-27 ZXMW NR8950 1+1 Separate Installation Completed (Single-Polarized


Antenna)

2.2.3 2+0 Separate Installation (Dual-Polarization)


This procedure uses the dual-polarized antenna manufactured by SHENGLU Corporation
as an example to describe how to install ODUs in 2+0 separate installation mode.
For installation components and tools used in 2+0 separate installation, refer to Table 2-7.

Table 2-7 Installation Components and Tools Used in 2+0 Separate Installation

Compo- Qua- Graph


nent/Tool ntity

Dual-polarized One
antenna

ZXMW NR8950 Two -

Installation Two -
bracket

Flexible Two -
waveguide

2-29

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Compo- Qua- Graph


nent/Tool ntity

Hex wrench One -


set

Adjustable One -
wrench

Screwdriver One -
set

Lubricant One -

Flexible - -
waveguide
clamp (for
flexible
waveguide over
0.6 m)

Steps
1. Install two installation brackets on the pole.
2. Remove the waveguide diaphragm from the ZXMW NR8950's antenna interface, refer
to “step 1” in “2.1.1 1+0 Buckle Installation”.
3. Install two ZXMW NR8950s on the two installation brackets respectively, see Figure
2-28.

2-30

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-28 Installing the ZXMW NR8950

Caution!
Fasten the four captive screws of the ZXMW NR8950 about 70% of the screw depth
into the screw holes, and secure the screws one by one in diagonal sequence.

4. Install the UDR ends of the two flexible waveguides on the dual-polarized antenna,
and install the PDR ends of the two flexible waveguides on the two installation brackets
respectively, see Figure 2-29.

2-31

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 2-29 Installing the Flexible Waveguide

5. Use the flexible waveguide clamp to fix the flexible waveguide, put lubricant on the
flexible waveguide surface, and paste labels on the two ends of the flexible waveguide.

Note:

Flexible waveguides shorter than 0.6 m need not be fixed. Flexible waveguides longer
than 0.6 m should be fixed by flexible waveguide clamps.

– End of Steps –

Result
The ZXMW NR8950 is installed completely in 2+0 separate installation mode (here, the
antenna is single-polarized), see Figure 2-30.

2-32

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-30 ZXMW NR8950 2+0 Separate Installation Completed (Dual-Polarized


Antenna)

2.2.4 2+2 Separate Installation (Dual-Polarization)


This procedure uses the dual-polarized antenna manufactured by SHENGLU Corporation
as an example to describe how to install ZXMW NR8950s in 2+2 separate installation
mode.
For installation components and tools used in 2+2 separate installation, refer to Table 2-8.

Table 2-8 Installation Components and Tools Used in 2+2 Separate Installation

Component/Tool Quantity

Dual-polarized antenna One

ZXMW NR8950 Four

Installation bracket Two

Combiner Two

Flexible waveguide Two

Hex wrench One set

Adjustable wrench One

Screwdriver One set

Lubricant One

2-33

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Component/Tool Quantity

Flexible waveguide clamp (for flexible -


waveguide over 0.6 m)

Steps
1. Install the two installation brackets on the pole, refer to “step 1” in “2.2.3 2+0 Separate
Installation (Dual-Polarization)”.
2. Install the two combiners on the two installation brackets respectively, refer to “step 2”
in “2.2.2 1+1 Separate Installation (Single-Polarization)”.
3. Remove the waveguide diaphragm from the ZXMW NR8950's antenna interface, refer
to “step 1” in “2.1.1 1+0 Buckle Installation”.
4. Install the four ZXMW NR8950s on the two combiners respectively, refer to “step 4” in
“2.2.2 1+1 Separate Installation (Single-Polarization)”.
5. Install the UDR ends of the two flexible waveguides on the dual-polarized antenna,
and install the PDR ends of the two flexible waveguides on the two installation brackets
respectively, refer to “step 4” in “2.2.3 2+0 Separate Installation (Dual-Polarization)”.
6. Use the flexible waveguide clamp to fix the flexible waveguide, put lubricant on the
flexible waveguide surface, and paste labels on the two ends of the flexible waveguide.

Note:
There is no need to fix the 0.6 m flexible waveguide. For flexible waveguides longer
than 0.6 m, installation personnel should use the flexible waveguide clamp to fix them.

– End of Steps –

Result
The ZXMW NR8950s are installed completely in 2+2 separate installation mode (here, the
antenna is dual-polarized), see Figure 2-31.

2-34

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 2 ZXMW NR8950 Installation

Figure 2-31 ZXMW NR8950 2+2 Separate Installation Completed (Dual-Polarized


Antenna)

2-35

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

This page intentionally left blank.

2-36

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 3
Cable Installation
Table of Contents
Cable Installation Requirements .................................................................................3-1
Installing the Protective Grounding Cable ...................................................................3-2
Installing the Power Cable..........................................................................................3-3
Installing the Ethernet Cable.......................................................................................3-5
Installing the Optical Fiber ..........................................................................................3-7
Installing the XPIC Cross-Connect Cables (Optional) .................................................3-8

3.1 Cable Installation Requirements


The following lists the cable installation requirements:
l In the equipment room where support and static floor are installed, all cables can be
routed in downward cabling mode, that is, cables are routed from the in-between floor
or a cable trough. If cables are routed in upward cabling mode, a cable rack must be
paved above the cabinet, and cables are routed through the cable rack.
l Before leading the outdoor cable into the equipment room, a waterproof bend must
be made.
l The cable layout position must be designed in advance, and all cables must be in
good condition and routed in order.
l External cables include the power cable, tail fiber, trunk cable, and other signal cables.
Cables in the cable rack must be bundled by category, and cannot be crossed. The
cables must be fixed by cable ties, with a spacing of 1 m – 1.5 m between each other.
l All cables must not be spiral.
l Cable bendings must be smooth and round, and the minimum bending radius is not
less than 60 mm.
l Cables must be bundled tidily and straightly, with appropriate tension and even
spacing between cable ties. The surplus cable part must be cut off, leaving no sharp
edge.
l Cables routed in a cable trough can be loose, but must be straight and not crossed,
and the cables cannot go beyond the cable trough. Cables must be bundled at the
cable trough's entry/exit and where cables are bent.
l The trunk cables that are routed from the cabinet to the relay rack cannot be pulled
tightly, and the extra cables should not be cut off. Cables routed in a cable trough or
on the raised floor must be bundled separately, and must be straight and not crossed.
After being routed, the cables must be tidy and in good condition, and sufficient margin
should be reserved as required.

3-1

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

l Cables must be pasted with labels, including project user cable label, IF cable label,
fiber cable label, and power cable label. A label is pasted 2 cm from the cable end. It
specifies the direction of the two ends of the cable: cabinet No. + board No. + socket
No.
l The cable routing must facilitate maintenance and future expansion.

3.2 Installing the Protective Grounding Cable


This procedure describes how to install the protective grounding cable.
The cross-sectional area of the protective grounding cable is 16 mm2.

The length of the protective grounding cable is not fixed upon delivery. Installation
personnel should make the terminals at the two ends in accordance with the actual
condition.

Steps
1. In accordance with the distance to the grounding point, cut the protective grounding
cable and crimp the terminals.
2. Fix one terminal of the grounding cable on the grounding screw of the ZXMW NR8950,
see Figure 3-1.

Figure 3-1 Connecting the Protective Grounding Cable

3. Connect the other end of the protective grounding cable to the grounding busbar of
the metal tower, and crimp the terminals in accordance with the grounding busbar
structure and size.

3-2

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 3 Cable Installation

Before connecting the grounding busbar, remove the antirust paint and the oxidization
layer from the grounding point.
After the connection is completed, perform antirust handling for the grounding point.
– End of Steps –

3.3 Installing the Power Cable


This procedure describes how to install the power cable.

Prerequisite
l The protective grounding cable is installed.
l The power switch on the power box that connects the power supply of the ZXMW
NR8950 is turned off.

Steps
1. Cut a bared power cable of a certain length as planned.
2. Install the round power cable plug to the bared power cable, see Figure 3-2.

Figure 3-2 Installing the Power Cable Plug

3. Insert the cable into the terminal hole and fix the cable with screws, see Figure 3-3.

3-3

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 3-3 Fixing the Power Cable Plug

Note:
The terminals must be connected to the correct connectors with the corresponding silk
screen marks.
l “-” to the –48 V connector (blue wire)
l “+” to the –48 V RTN connector (black wire)
After all screws are tightened, make sure that the power cable is not loose when you
pull it with a force of 2 kg.

4. Tighten the seal assembly clockwise to fix it to the plug and tighten the tail nut to fix
the cable, see Figure 3-4.

Figure 3-4 Completed Installation

5. Connect one end of the power cable with appropriate length to the power interfaces of
the ZXMW NR8950, see Figure 3-5.

3-4

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 3 Cable Installation

Figure 3-5 Installing the Power Cable

6. Connect the other end of the power cable to the office power supply.
– End of Steps –

3.4 Installing the Ethernet Cable


This procedure describes how to install the Ethernet cable.
Use the outdoor category 5e shielded cable with 8P8C straight cable crimped shielded
terminals as the Ethernet cable.

Steps
1. Select an Ethernet cable of a proper length in accordance with the actual requirements.

2. Paste labels at the two ends of the Ethernet cable.


3. Put the waterproof sleeve on the Ethernet cable.

4. Crimp the Ethernet cable with the shielded connector.


The 568B standard straight network cable is recommended. The wire sequences at
both ends must be the same, see Figure 3-6.

3-5

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 3-6 Wire Sequence of the Straight Network Cable (568B Standard Cable)

1. White, orange 4. Blue 7. White, brown


2. Orange 5. White, blue 8. Brown
3. White, green 6. Green

5. Connect the Ethernet cable to the Ethernet port of the ZXMW NR8950 see Figure 3-7.

Figure 3-7 Installing the Ethernet Cable

6. Fasten the waterproof sleeve until it reaches the flange, and tighten the locknut of the
waterproof sleeve.

– End of Steps –

3-6

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 3 Cable Installation

3.5 Installing the Optical Fiber


This procedure describe how to install the optical fiber.

Steps
1. Check whether the ZXMW NR8950 GbE2 interface contains an optical module, and
perform the corresponding operations as follows.

If... Then...

The GbE2 interface contains an Perform step 2.


optical module

The GbE2 interface does not Insert an optical module into the ZXMW NR8950 GbE2 interface
contain any optical module

2. Select an optical fiber of a proper length and paste labels at the two ends of it.
3. Connect one end of the fiber to the ZXMW NR8950 GbE2 interface, see Figure 3-8.

Figure 3-8 Installing the Optical Fiber

4. Connect the other end of the fiber in accordance with the actual requirements.

– End of Steps –

3-7

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

3.6 Installing the XPIC Cross-Connect Cables


(Optional)
The Cross Polarization Interference Canceller (XPIC) technology helps to reduce the
interference among dual-polarization signals and enhances the system immunity.
The XPIC cross-connect cable connects the XPIC IF interfaces of two ZXMW NR8950s,
transmitting the interference cancelling IF signal between two ZXMW NR8950s.

Prerequisite
The IDU protective grounding cable is installed.

Context
l For the 2+0 XPIC cross connect, see Figure 3-9.

Figure 3-9 2+0 XPIC Cross Connect (Bottom View)

l For the 2+2 XPIC cross connect, see Figure 3-10.

3-8

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 3 Cable Installation

Figure 3-10 2+2 XPIC Cross Connect

Figure 3-11 shows the difference between the 2+2 XPIC HSB protection configuration
and the 2+2 XPIC SD protection configuration.

Figure 3-11 2+2 XPIC HSB and 2+2 XPIC SD Cross Connection

Steps
1. Paste labels at the two ends of the XPIC cross-connect cable.
2. Use a torque spanner with SMA connector to fasten the two ends of the four XPIC
cross-connect cables on the X_IN interface and the X_OUT interface on the four
ZXMW NR8950s respectively.

3. Tighten the QMA corrugated tubes at the corresponding point of the shell, see Figure
3-12.

3-9

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 3-12 Installing the XPIC Cross-Connect Cables

– End of Steps –

3-10

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 4
Installation Check
Table of Contents
Installation Check for the ZXMW NR8950...................................................................4-1
Cable Installation Check.............................................................................................4-2

4.1 Installation Check for the ZXMW NR8950


This check involves the installation of the ZXMW NR8950, antenna, combiner, and the
components for separate-installation.

Table 4-1 Check Items for the Installation of the Antenna, Combiner, and ZXMW NR8950

Item Requirement

1 The installation position and direction of the antenna meet the engineering design
requirements.

2 The antenna is installed with a correct orientation; that is, the side with a larger area faces
upwards while the side with a smaller area faces downwards.

3 The support of the antenna is firmly fixed to the pole, meeting the wind resistance
requirements.

4 The four screws of the ZXMW NR8950 are fastened tightly.

5 The four screws of the combiner are fastened tightly.

6 The antenna, combiner, and ZXMW NR8950 are in the coverage of the lightning rod. The
protection angle of the antenna's lightning rod should be less than 45° in general, and less
than 30° in the areas with high mountains or frequent thunderstorms.

Table 4-2 Installation Check Items for Separate-Installation Components

Item Requirement

1 The installation position and direction of the ZXMW NR8950's adapter meet the engineering
design requirements.

2 The adapter of the ZXMW NR8950 is firmly fixed to the pole, meeting the wind resistance
requirements.

3 The four screws of the antenna adapter are fastened on the antenna tightly.

4 The flange interfaces of the flexible waveguide are connected to the ZXMW NR8950's
adapter and antenna adapter (or the antenna) firmly and reliably.

4-1

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Item Requirement

5 The bending radius of the flexible waveguide does not exceed the allowable value, with a
torsional angle not more than 90°.

6 The components for separate-installation are in the coverage of the lightning rod. The
protection angle of the antenna's lightning rod should be less than 45° in general, and less
than 30° in the areas with high mountains or frequent thunderstorms.

4.2 Cable Installation Check


This check involves the installation of the cables of the ZXMW NR8950, the power cable
and grounding cable of the cabinet.

Table 4-3 Check Items for Cable Installation of the ZXMW NR8950

Item Requirement

1 The cable layout meets the engineering design requirements for easy maintenance and
capacity expansion.

2 The cables are in good condition without any damage, breakage, or in-between joint.

3 The cables are laid in order and bundled with a proper force, with even spacing between
cable ties. The unwanted part of the ties are cut after bundling, leaving no sharp edges.

4 The fiber pigtail is protected with a protection tube or trough.

5 The protection tube of the fiber pigtail is bundled and fixed inside the cabinet.

6 The protection tube of the fiber pigtail is cut smoothly and, if necessary, wrapped with
insulating tapes at the cut to protect against injuries.

7 The fiber pigtail is not bundled too tightly. It is desirable for the fiber pigtail to be drawn
out of the cable ties easily.

8 The fiber pigtail is laid without other cables or objects placed on it.

9 The joint of the fiber pigtail is clean and dust-free. Unused fiber connectors and optical
interfaces on a board are covered with protection caps or plugs.

10 The cable bends are smooth and round, with a bending radius as large as possible.

11 The signal cables are labelled properly with all labels in good order and in the same
direction. They are recommended to be labelled 2 cm from the plug. Labels can be made at
the request of customers.

12 Unused cable connectors are covered with, for example, protection caps.

4-2

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 4 Installation Check

Table 4-4 Check Items for Installation of the Cabinet's Power Cable and Grounding
Cable

Item Requirement

1 Layout of the power cable and grounding cable meet the engineering design requirements
for easy maintenance and capacity expansion.

2 The power cable or grounding cable of the cabinet is connected properly.

3 The cross-sectional area of the power cable and grounding cable satisfies the power supply
requirements of the equipment.

4 The core of the power cable and grounding cable is made of an integrated copper wire
without any joint.

5 When the power cable or grounding cable is connected to the primary power supply, copper
grounding bar, or first cabinet of each row, cut the unwanted part of the cable.

6 Outside the cabinet, the power cable, grounding cable, and the signal cables are routed
separately, with a distance of 3 cm between each other.

7 The power cable or grounding cable is routed and bundled straightly and in good order.

8 The bends of the power cable and grounding cable are smooth and round.

9 The power cable or grounding cable is welded or crimped to the cable lug securely.

10 The cable lug's handle and the bare part of the power cable or grounding cable are wrapped
by tube or insulating tape. There is no bare copper wire at the cable lugs and terminals, and
the flat washer and spring washer are installed correctly.

11 Inside the cabinet, all the devices with metal casings are grounded correctly and connected
reliably.

12 The power cable and grounding cable are labelled properly with all labels in good order
and in the same direction. They are recommended to be labelled 2 cm from the plug.
Labels can be made at the request of customers. The power distribution switch of the
first cabinet of each row is labelled clearly.

4-3

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

This page intentionally left blank.

4-4

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 5
Power On and Power Off
Table of Contents
Power on....................................................................................................................5-1
Power off....................................................................................................................5-3

5.1 Power on
The AOU can be supplied power through the direct, NR8250 and PSE box power-on
procedures.

Prerequisite
l The power cable and grounding cable of the AOU are connected correctly.
l The power supply of the AOU is turned off.

Power-on Procedures

Figure 5-1 Direct Power-on Procedure

5-1

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure 5-2 NR8250 Power-on Procedure

5-2

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Chapter 5 Power On and Power Off

Figure 5-3 PSE Box Power-on Procedure

5.2 Power off


For the AOU power-off procedure, see Figure 5-4.

Figure 5-4 Power-off Procedure

5-3

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

This page intentionally left blank.

5-4

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix A
Antenna Pole Installation
(Optional)
Poles are used to fix antennas. Before installing an antenna on a pole, installation
personnel must connect the pole to or fixed the pole on an object with certain strength,
such as a metal tower or cement wall. This procedure describes how to install the pole on
the roof of a building and on an angle steel tower.

Caution!
This equipment should be installed and operated with minimum distance 16m between the
radiator & your body.

Table of Contents
Ÿ Installing the Pole on the Roof of a Building ............................................................ A-1
Ÿ Installing the Pole on an Angle Steel Tower ............................................................ A-3

A.1 Installing the Pole on the Roof of a Building


This procedure describes how to install the antenna pole on the roof of a building.

Steps
1. Assemble the components for pole installation, see Figure A-1.

A-1

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure A-1 Assembling the Pole Installation Components

2. Fix the main body of the pole to the roof with expansion bolts, and install the three feet
of the pole on the roof.

Note:
The installation process described above is only for reference because the installation
varies from one site to another.

Figure A-2 shows the installed pole.

A-2

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix A Antenna Pole Installation (Optional)

Figure A-2 Installed Pole

– End of Steps –

A.2 Installing the Pole on an Angle Steel Tower


This procedure describes how to install the antenna pole on an angle steel tower.

Steps
1. Install a flat washer, spring washer, and nut on one end of a straight bolt, see Figure
A-3.

A-3

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure A-3 Assembling a Straight Bolt

2. Hoist the pole assembly to the height and position specified in the design drawing.
3. Install the pole assembly on the angle steel tower, see Figure A-4.

A-4

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix A Antenna Pole Installation (Optional)

Figure A-4 Installing the Pole on the Angle Steel Tower

1. Assembled straight 3. Angle steel on the 6. Nut


bolt angle steel tower
2. Pole installation 4. Flat washer
component 5. Spring washer

Figure A-5 shows the installed pole.

A-5

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure A-5 Installed Pole

– End of Steps –

A-6

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix B
Installing Antenna
This installation of antenna has two manners: left installation and right installation, see
Figure B-1.
User can choose one manner based on the installation site and circuit design. Only
antenna right installation is introduced herein. The left installation is similar to the right
installation.

Figure B-1 Manners of Antenna Installation

Steps
1. (Optional) Install the anti-fall clamp to the pole.

Note:

If there is no anti-fall clamp, go to Step 2.

2. Install the hanging bracket to the pole, see Figure B-2.

B-1

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure B-2 Installing Hanging Bracket

3. Install the elevation angle preset to antenna, see Figure B-3.

B-2

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix B Installing Antenna

Figure B-3 Installing the Elevation Angle Preset

4. Install one of the two bolts M10×40 to the antenna, keeping the distance of 20 mm,
and another one on standby, see Figure B-4.

B-3

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure B-4 Installing the Bolts

Four screw holes (No.1, 2, 3 and 4) are available in elevation angle preset.

Screw Hole Elevation Angle Range of Antenna


Adjustment

No.1 and 3 0° ±15°

No.1 and 4 10° up -5° to +25°

No.1 and 2 10° down -25° to +5°

5. Hoist the antenna, and the bolt in antenna will move down into the groove of elevation
adjuster. Tighten two bolts after the preset angle is confirmed, see Figure B-5.

B-4

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix B Installing Antenna

Figure B-5 Antenna Hoisting

– End of Steps –

B-5

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

This page intentionally left blank.

B-6

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix C
Antenna Adjustment
(Optional)
Table of Contents
Ÿ Adjusting the Polarization Mode of an Antenna....................................................... C-1
Ÿ Adjusting the Antenna Azimuth ............................................................................... C-4
Ÿ Adjusting the Antenna Pitch Angle .......................................................................... C-5

C.1 Adjusting the Polarization Mode of an Antenna


This procedure describes how to adjust the polarization mode of an antenna.

Context
A feeder provides two polarization modes:
l Vertical polarization (see Figure C-1)

The polarization arrow on the feeder is aligned with the mark "V" on the antenna.

C-1

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure C-1 Vertical Polarization

1. Feeder fastener 3. Screw


2. Polarization arrow 4. Feeder

l Horizontal polarization (see Figure C-2)

The polarization arrow on the feeder is aligned with the mark "H" on the antenna.

C-2

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix C Antenna Adjustment (Optional)

Figure C-2 Horizontal Polarization

Steps
1. Loosen the four screws on the feeder.

2. Rotate the feeder by 90° clockwise, see Figure C-3.

Figure C-3 Adjusting From Vertical Polarization to Horizontal Polarization

3. Fasten the four screws on the feeder.

C-3

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Note:
Adjustment from horizontal polarization to vertical polarization is made in the same
way. The adjustment requirements depend on the actual circuit on site.

– End of Steps –

C.2 Adjusting the Antenna Azimuth


This procedure describes how to adjust the antenna azimuth.

Context
l The antenna azimuth can be finely adjusted in a range of ±15°.
l If this range is not big enough for actual applications, users can change the position
of the anti-falling angle steel before adjusting the azimuth. In that case, a U-clamp
must be used to fix the bracket.
l Figure C-4 and Figure C-5 show the installation components used for azimuth
adjustment of an antenna.

Figure C-4 Installation Components for Antenna Azimuth Adjustment

1. Azimuth fine-adjustm 2. Fine-adjustment nut 4. Nut of the U-clamp


ent screw 3. Bracket fastening bolt 5. U-clamp

C-4

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix C Antenna Adjustment (Optional)

Figure C-5 Reinforcing Rod

1. Setting screw 2. Reinforcing rod

Steps
1. Make a coarse adjustment of the antenna azimuth.
a. Remove the azimuth fine-adjustment screw and the bracket fastening bolt.
b. Loosen the nut on the U-clamp and the setting screw on the reinforcing rod slightly.
c. Push the antenna or reinforcing rod gently, and adjust the antenna azimuth around
the pole.

Warning!
During the adjustment, make sure that the bracket does not fall from the anti-falling
angle steel to avoid any accident.

2. Roughly determine the antenna azimuth visually or with a compass according to the
circuit design.
3. Fasten all the components that were loosened during the adjustment.
4. Install and fasten the azimuth fine-adjustment screw and the bracket fastening bolt.
– End of Steps –

C.3 Adjusting the Antenna Pitch Angle


By adjusting the pitch angle of an antenna, the AOU receiving level can be adjusted.

For the relationship between the AOU receiving level and the measuring voltage level, see
Figure C-6.

C-5

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure C-6 Relationship Curve of the AOU Receiving Level and the Measuring Volatge

• X-axis: receiving level • Y-axis: Measuring voltage


(dBm) (V)

Context
l The pitch angle of an antenna can be finely adjusted in a range of ±10°.
l For the installation components used for pitch angle adjustment of an antenna, see
Figure C-7,.

Figure C-7 Installation Components for Antenna Pitch Angle Adjustment

1. Pitch angle 2. Pitch angle 3. Setting bolt


fine-adjustment screw fine-adjustment nut

C-6

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix C Antenna Adjustment (Optional)

Steps
1. Loosen the setting bolt slightly.
2. Rotate the pitch angle fine-adjustment nut with a proper tool.
3. Make a fine adjustment of the pitch angle.
4. Fasten the pitch angle fine-adjustment nut.
– End of Steps –

C-7

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

This page intentionally left blank.

C-8

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix D
Installing the PIMDC
The DC lightning protection module PIMDC should be equipped if the ZXMW NR8950 is
powered by an external DC power supply and needs to be protected from lightning.

Steps
1. Pass two hoop irons through the mounting bracket and fix the bracket to the pole, see
Figure D-1.

Figure D-1 Fixing the Mounting Bracket to the Pole

1. Hoop iron 2. Mounting bracket

2. Place the PIMDC on the mounting bracket and tighten the upper and the lower screws,
see Figure D-2.

Figure D-2 Fixing the PIMDC to the Mounting Bracket

3. Install cables for the PIMDC, see Figure D-3.

D-1

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure D-3 Cable Connection

– End of Steps –

D-2

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Appendix E
Installing the PSE
The PSE can be installed with the AC-DC power supply equipment and ODCPD1.

Pole-Mounted Installation
For the installation steps, seeFigure E-1.

Figure E-1 Pole-Mounted Installation

A. Power supply module


B. Fixed feame
C. APSU
D. Fixed feame
E. ODCPD1

Wall-Mounted Installation
For the installation steps, seeFigure E-2.

E-1

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


ZXMW NR8950 Hardware Installation Guide

Figure E-2 Pole-Mounted Installation

E-2

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential


Glossary
AC
- Alternating Current
AOU
- All Outdoor Unit
DC
- Direct Current
GPS
- Global Positioning System
PSE
- Power Sourcing Equipment
PoE
- Power over Ethernet
XPD
- Cross Polarization Discrimination
XPIC
- Cross Polarization Interference Canceller

SJ-20151105160201-004|2016-01-27 (R1.1) ZTE Proprietary and Confidential