ID Task Task Name Duration Start Finish PreResource Names

Mode
Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19
12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14
1 1 MEKA INC PROJECT MANAGEMENT PLAN  123 days? Wed  Fri 15/02/19
29/08/18

2 1.1 Signing of Sales Contract 1 day Wed  Wed 29/08/18 Client Client


29/08/18

3 1.2 Project Start 0 days Wed  Wed 29/08/18 29/08


29/08/18

4 1.3 PHASE 1 ‐ Design Conceptualization 30 days Thu  Wed 10/10/18 2


30/08/18

5 1.3.1 Preparation of Design Brief 0.5 days Thu  Thu 30/08/18 2 Project Manager Project Manager


30/08/18

6 1.3.2 Site Specific Zoning By‐Laws Documentation 0.5 days Thu  Thu 30/08/18 5 Architect Architect


30/08/18

7 1.3.3 Initial Design Meeting with Client 1 day Fri 31/08/18 Fri 31/08/18 6 Manager Manager

8 1.3.4 Preparation of Concept Design Drawings 23 days Mon  Wed 03/10/18 7 Architect Architect


03/09/18

9 1.3.5 Client Review  5 days Thu 04/10/18Wed 10/10/18 8 Client Client

10 1.4 PHASE 2 ‐ Design Development 17 days Thu  Fri 02/11/18 9


11/10/18

11 1.4.1 Drawing Development   5 days Thu  Wed 17/10/18 9 Architect Architect


11/10/18

12 1.4.2 Meeting with Client 1 day Thu 18/10/18Thu 18/10/18 11Manager Manager

13 1.4.3 Drawing Development Revisions, Coordination 5 days Fri 19/10/18 Thu 25/10/18 12Architect Architect

14 1.4.4 Meeting with Client 1 day Fri 26/10/18 Fri 26/10/18 13Manager Manager

15 1.4.5 Review, Approval of Specifications 5 days Mon 29/10/1 Fri 02/11/18 14


16 1.5 PHASE 3 ‐ Costing 13 days Mon 29/10/1Wed 14/11/18
17 1.5.1 Submission of Plans and Specifications for costing 1 day Mon  Mon 29/10/18 14Project Manager Project Manager
29/10/18

18 1.5.2 Coordination, Inquiries from GC 7 days Tue 30/10/18Wed 07/11/18 17Manager,Project M Manager,Project Manager

19 1.5.3 Review of Bid/Costing 2 days Thu 08/11/18Fri 09/11/18 18Project Manager Project Manager

20 1.5.4 Submission of Final Costing 3 days Mon 12/11/1 Wed 14/11/18 19GC GC

21 1.6 PHASE 4 ‐ Permits 81 days Fri 26/10/18 Fri 15/02/19


22 1.6.1 Submission to Client of Permit Related Documents 1 day Fri 26/10/18 Fri 26/10/18 13Client Client

23 1.6.2 Application, Review and Approval 80 days Mon 29/10/1 Fri 15/02/19 22Building Official Building Official

24 1.7 PHASE 5 ‐ Assembly and Construction Documentation 20 days? Thu  Wed 12/12/18 20


15/11/18

25 1.7.1 Assembly/ Construction Drawings ‐ Architectural 10 days Thu 15/11/18Wed 28/11/18 20Architect Architect

26 1.7.2 Fabrication Drawings 10 days Thu 29/11/18Wed 12/12/18 25


27 1 day? Thu 15/11/18Thu 15/11/18

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: PM Plan
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 29/08/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress