PROJECT: Proposed Two Storey Residential Building SUBJECT: CONSTRUCTION SCHEDULE

LOCATION: De Joya Bayview Vill, Batangas City DATE: March 29, 2017
OWNER: Ms. Josephine Villanueva DURATION: 6 Months (24 Weeks)

Month # Month Section General Activity Week # Major Activity Manpower Minor Activity Manpower
Week 1 Site Layout & Excavation 6-8 Labor for Footing Excavation Steel works for Foundation 2 Skilled (Steelman) + 1 Helper
Foundation & Substructure works Week 2 Foundation & Tie Beam Concrete Pouring 6-8 Labor for Footing Excavation Steel works for Beams 2 Skilled (Steelman) + 1 Helper
Month 1 APR
Week 3 Substructure works, Slab-on-grade Construction Ground Floor Plumbing works 1 Skilled (Plumber) + 1 Helper
Week 4 CHB Wall to Header
Week 5 Header Construction
Month 2 MAY Week 6 CHB Wall to Beam
Week 7 Slab & Beam Construction 6-8 Skilled (Steelman/Mason), 6-8 Helper Electrical works 1 Skilled (Electrician)
Structural Week 8 CHB Wall to Header Second Floor Plumbing works 1 Skilled (Plumber) + 1 Helper
Building Massing Week 9 Header Construction
Month 3 JUN Week 10 CHB Wall to Beam Electrical works 1 Skilled (Electrician)
Week 11 Beam Construction Truss works
Week 12 Second Floor Interior Wall Plastering Subcontractor
Week 13 Ground Floor Interior Wall Plastering Roofing works
Month 4 JUL Week 14 Second Floor Exterior Wall Plastering
Week 15 Ground Floor Exterior Wall Plastering 6-8 Skilled (Mason), 6-8 Labor
Tileworks on Second Floor
2 Skilled (Tile Setter) + 1 Helper
Week 16 Second Floor Interior Wall Skim Coat Tile works on Ground Floor
Week 17 Ground Floor Interior Wall Skim Coat Installation of Doors 4 Skilled (Carpernter)
Month 5 AUG Week 18 Second Floor Exterior Wall Skim Coat Construction of Fence 2 Skilled (Mason/Steelman/Carpenter) + 4 Helper
Architectural Painting works, Tileworks, Doors & Windows Week 19 Ground Floor Exterior Wall Skim Coat Painting works on Fence 2 Painter
Week 20 Second Floor Interior Painting Works
Landscaping 2 Labor
Week 21 6-8 Painter
Month 6 SEPT Week 22 Ground Floor Interior Painting Works
Electrical works 1 Skilled (Electrician)
Week 23 Installation of Windows, Installation of Cabinets Subcontractor
Week 24 Project (Site & Bldg) Cleaning & Demobilization 10 Labor Punchlisting Architect

TOTAL 6 Months ( 24 Weeks)


8-12 Skilled (Mason/Steelman/Carpenter)
8-10 Painter
8-12 Labor