Professional Documents
Culture Documents
Purpose
This procedure and practice is provided as a guide to
Contractor, its subcontractors their staff, and
specifically the rigging staff and rigging coordinators
to execute all crane lifts safely. This procedure shall be
implemented by Contractor and enforced by Owner
on the Project.
2
SCOPE
This procedure provides the following:
Establishes the requirement for organizing a Contractor Crane and
Rigging Group, lists personnel and defines their role in the successful
execution of this practice, identifies the responsibilities of key
personnel for this practice.
Identifies the requirements for design and review of lifting lugs.
Categorizes rigging lifts for and establishes responsibility for the
design, engineering and approval of the transportation and rigging of
all equipment and modules. This practice covers all crawler cranes,
truck cranes, carry deck cranes, monorails, boom trucks, etc.
Establishes guidelines that must be adhered to when requiring a
variance from this procedure.
3
Crane Operator
A qualified person who is licensed, trained, certified
and experienced in the use, the capabilities, and all of
the functions of a specific machine, mechanical system,
or tool. All Crane Operators must meet the following
requirements:
An up-to-date shall be on file with Contractor, detailing
specific experience in crane operation.
4
Signalman
A designated person who is trained and experience in hand signals
used and understood by crane operators.
Under certain conditions, such as multiple crane lifts, or lifting "in the
blind", it may be deemed necessary for additional signalmen to
participate in a lift or Heavy Rigging Activity. One signalman will be
designated as the “Lead Signalman”.
5
Responsibilities
Responsible Personnel - The crane operator, and the
qualified field rigger, are jointly responsible for
determination of the load weight and placement of the
crane so that it is set up within the operating radius
selected. The rigging supervisor has final
responsibility for all operations.
6
Contents
Partial extension
OUTRIGGER
SPAN 1
ALL MAXIMUM
SPAN
OUTRIGGER
SPAN 2
ALL PARTIAL
SPAN
INCORRECT
OUTRIGGER SPAN 1
PARTIAL
SPAN
X FULL
SPAN
INCORRECT
OUTRIGGER SPAN 2
PARTIAL FULL
SPAN SPAN
X
SPAN OPERATION
THE BEAMS TRANSFER LOAD TO THE CARRIER AT THE CORRECT
POSITIONS WHEN CARRIER WHEELS CLEAR THE GROUND.
INCORRECT SPAN -
OPERATOR ERROR
THIS BEAM TRANSFERS LOAD TO THE CARRIER AT AN
INCORRECT POSITION WHEN CARRIER RAISES.
X
THIS AREA IS
NOT STRONG
This accident is due to an
OPERATOR ERROR
Operator Error.
He used an Incorrect
Outrigger Span……..!
No extension
beams used
OUTRIGGER SECURITY
X
FOR ROAD
TRAVEL, THESE
LOCKING
DEVICES MUST
BE USED
TIPPING AXIS
EXPLANATION 1
‘outriggers
nearest to
the load’
TO RIGHT SIDE
TIPPING AXIS
EXPLANATION 2
CRANE WEIGHT
‘outriggers
nearest to
the load’
LOAD WEIGHT
Y X
TIPPING AXIS
OPERATOR ERROR
Crane was on
tires only.
No outriggers
in use
Lift
Operating Code Lift Configuration
Configuration Outrig
gers
Parts-of-Line Counterweight
OPERATOR ERROR
INCORRECT CONFIGURATION
CRANE INSPECTION
I must ensure If it is to Even for a
this machine be used run-up,
is safe to use If it is to be for craning an inspection
used for is needed
traveling
Operation Responsibility
• Crane, Crane Operator, Rigger Certificate.
• Maintain daily checklist
• An approved lift plan provided.
• Heavy lifts must be noted on the Work Permit.
• If load critical or man basket required operation foreman should
issue the work permit.
• Crane location and positioning.
• Critical Wind Speed.
• Stop the work
Maint. / Construction Responsibility
Poor flat
support
X
X
Load is
too
Telescoping out close
and increasing from the
Too much load
The load radius crane
RESULT
Stability Tripping Strength
failure structure
failure
Incidents
Crane Incident
Stabilizers are
retracted
10.5t
Counterweights
Crane Incident
Note the
trench here
Owner shall review and approve locations for storage of all fuels, lubricants, starting fluids
prior to use by Contractor for storage.
Contractor shall equip all vehicles and fuel driven construction equipment with a fire
extinguisher, red triangles, flashlight and a first aid kit.
Safety Devices
Contractor shall equip all vehicles and fuel driven construction equipment with a fire
extinguisher, red triangles, flashlight and a first aid kit.
All rubber tired, self propelled scrapers, rubber tired, front-end loaders, rubber tired dozers,
wheel type agricultural and industrial tractors, crawler tractors, crawler type loaders and
motor graders shall be equipped with rollover protective structures and seat belts.
Inspection of these devices will be included as part of the operators' daily pre-operational
inspection, as well in the formal monthly inspection.
All multiple crane lifts (exclusive of a tailing crane) in which the load could be
transferred from one crane to another during the lift.
All lifts over eighty (80) percent of the capacity chart of the crane for the boom
length and operating radius being used, or over ninety (90) percent if the crane
has an operational load indication device with an overload cut-off.