Vendor : Base technologies Ltd.

Address : Hosna Center(5th Floor)106,Gulshan Avenue Dhaka


Contact : +8801818226187 ,mehedi.hasan@base-technologies.net

Attention to: HF Power Limited (A sister Concern of Hosaf Group)


High Tower, 9 ,Mohakhali,Dhaka-1212

SCHEDULE OF PILE WORKS:


SL
DESCRIPTION OF ITEMS UNIT QUANTITY UNIT PRICE GRAND TOTAL
No.
Mobilization and demobilization for contractor site office and store
1 sft 10,000.00 4.5 45,000.00
after completion of the works under contract accepted by Engineer.
Layout & pile marking for earth work in excavation in foundation
2 accepted by the Engineer. (Plinth area of the structure shall be sft 30,000.00 2.5 75,000.00
considered for measurmennt)
Boring/drilling and casting of 500 mm dia cast in situ pile up to the
required depth with 5 mm thick steel temporary casing, true to vertical,
providing bentonite slurry and maintaining water level in the hole,
washing the hole for at least 30 minutes, placing steel cage and
concreting including hire charge of rig set with winch machine, tripod
stand, trimie pipe, cost of fuel, lubricant, mobilization, demobilization,
maintenance, spares, stand-byes, insurance coverage, water, electricity
& other charges all compete as per design and direction of engineer-in-
charge. The in situ Concrete will be reinforced cement concrete
3 works(1:1.5:3) (with admixtures) of specified compressive strength, f'c RFT 32,300.00 2,214.65 71,533,195.00
24.14 Mpa at 28 days on standard cylinder with cement (Lafarge/Scan)
conforming to BDS 232 & ASTM standards,CEM 1 best quality sand
[Sylhet coarse sand of equivalent F.M. 2.2] and 20 mm down well
graded stone chips etc. all complete as per specification and direction of
the engineer-in-charge. (Rate is including the cost of reinforcement)

Boring/drilling and casting of 600 mm dia cast in situ pile up to the


required depth with 5 mm thick steel temporary casing, true to vertical,
providing bentonite slurry and maintaining water level in the hole,
washing the hole for at least 30 minutes, placing steel cage and
concreting including hire charge of rig set with winch machine, tripod
stand, trimie pipe, cost of fuel, lubricant, mobilization, demobilization,
maintenance, spares, stand-byes, insurance coverage, water, electricity
& other charges all compete as per design and direction of engineer-in-
charge. The in situ Concrete will be reinforced cement concrete
4 works(1:1.5:3) (with admixtures) of specified compressive strength, f'c RFT 43,000.00 2,988.88 128,521,805.60
24.14 Mpa at 28 days on standard cylinder with cement (Lafarge/Scan)
conforming to BDS 232 & ASTM standards,CEM 1 best quality sand
[Sylhet coarse sand of equivalent F.M. 2.2] and 20 mm down well
graded stone chips etc. all complete as per specification and direction of
the engineer-in-charge. (Rate is including the cost of reinforcement)

Page 1 of 2
SL
DESCRIPTION OF ITEMS UNIT QUANTITY UNIT PRICE GRAND TOTAL
No.
Conducting static load test as per ASTM D1143 or equivalent standard
for the cast-in-situ/pre-cast pile providing required scaffolding, bracing,
jacks, pressure test gauge, loading unloading, Kentledge and other
plants and equipment including staging, mobilization, demobilization,
hire charge, gunny bags, sand and filling sacs/gunny bags for loading,
record readings and preparation of results in standard forms and other
incidental charges per standard practice and procedures including
6 submission of load test report, furnishing all graph and chart etc. Nos 1.00 200,000.00 200,000.00
complete in all respects approved and accepted by the Engineer
(Minimum two cyclic loading-one at service load).
Before commencing load test, Contractor shall submit method statement
for conducting load test to the Engineer for approval. However,
Engineer’s approval shall not relieve the Contractor of his
responsibilities and obligations under Contract

Total Cost 200,375,000.60

Mode of Payment
1. VAT & TAX are included as per Govt. rule
2. Running bill will be submitted after every 7 days of work
3. Bill has to be cleared within 7 days of submission
4. 20 % Mobilization advance to be paid against BG

Page 2 of 2