PROJECT PLAN

PO NO : 89000573&89000595 PWO NO : BSE-PWO-000037&38


CLIENT : EXTERRRAN ENERGY FZE DELIVERY : 6-8 WEEKS
PROJECT: SUPPLY OF MANUAL VALVES REF DOC NO: BSE-PRP-000037&38 REV NO : 00 SCHEDULE
PO DESCRIPTION: SUPPLY OF MANUAL VALVES DATE : 02-08-2018
PO ITEM QTY : 161&67 NOS SCHEDULE:
S.NO ACTIVITY RESPONSIBLE START END STATUS 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK
1 ENGINEERING DESIGN PROJECT & DESIGN 1 WEEK 1 WEEK
PROCUREMENT OF TRIM
2 PROCUREMENT TEAM 1 WEEK 3 WEEK
PARTS
PROCUREMENT OF
3 PROCUREMENT TEAM 2 WEEK 5 WEEK
CASTINGS
PROJECT &
4 MACHINING/FABRICATION 3 WEEK 7 WEEK
PRODUCTION
5 ASSEMBLY & TESTING QC & PRODUCTION 5 WEEK 8 WEEK
6 PAINTING PRODUCTION 6-8 WEEK
7 PACKING & DISPATCH STORES & DISPATCH 6-8 WEEK

REMARKS:
PREPARED BY: VV REVIEWED BY : PSK APPROVED BY : PJ