Unless decided otherwise at the time of the incident, the CMT will operate initially
from an Emergency Control Centre (ECC). If [xxxx] is available following the
incident, recovery will take place at this site. Otherwise, recovery will take place at
an alternative site, as decided by the CMT at the time of the incident. A permanent
site will be sought concurrently with any recovery effort.
By 4 Hours
1. Hold the initial CMT meeting.
2. Liase with Primary Site Team to:
• Inform insurers.
• Devise and release a detailed statement for internal and trusted third
party use.
• Devise a holding press statement for external release.
3. Brief the CMT Secretary and telephone operators on PR, call filtering and
establish routing to other staff.
4. Complete an interim impact assessment. Consider:
• Loss of fileservers.
• Loss of applications.
• Loss of communication links.
• Loss of data.
• Fileserver recovery priority.
• Loss of assets.
• Which operations will be effected if the Plan is not invoked.
5. Decide whether to continue Plan invocation.
6. If the Plan is NOT to be invoked then resolve any problems and
implement the stand-down procedure [section 2.3.3]. Otherwise,
continue with the planned response.
7. Refine the Recovery Strategy according to the situation. Decide which teams
must become active and by when.
8. Establish the minimum facilities and equipment that will be required by each
recovery team to achieve its minimum acceptable level of operations.
9. Establish what facilities and equipment are available at each alternate venue
and by when, including any accessible workspace and facilities still available at
the primary site.
10. Contact Alternate Site Team Leader to:
• Invoke the alternate site(s).
• Verify the level of resources and materials required.
• Plan occupation by Recovery Teams.
By Day 1
1. Contact and inform other third party contacts [Appendix B].
2. Use approved statements to respond to incoming calls.
3. Authorise recovery agreements with third party service providers.
4. Arrange a meeting with landlord to establish insurance and reconstruction
responsibilities.
5. Ensure:
• That all Health and Safety regulations are satisfied at the alternate site.
• That Fire Officers and First Aiders have been assigned and briefed.
6. Keep detailed PR response updated as per continuing situation. Determine if
assistance from third parties is required. Decide whether to hold a press
conference.
7. Confirm with the Alternate Site Team:
• Redirection of lines and recovery status for the PABX.
• The recovery status of the following day one critical applications:
• To be specified,
• Others
• Which day's backups where used to restore the computer systems
i.e. extent of information loss.
• Obtain status of the following:
• Disaster recovery agreements.
• Redirection of voice and data communications.
• Retrieval of back-up media.
By Week 1
1. Work with Oversight Board to:
• (Finance Director – [Mr xxxx]) Agree purchasing and budgetary limits
with insurers. Authorise placement of orders / invocation of
emergency procurement agreements for equipment.
• (Company’s BCP Manager – [Mr xxx]) Confirm that IT & business
operations at the alternate site are stabilised.
2. Contact the Alternate Site Team Leader and verify recovery status of
computer systems:
• Determine the extent of backlogs and their impact on recovery
timeframes.
3. Continue contact with the Primary Site Team to review status of damage at
[xxx].
4. Continue to assess staff reaction to the disaster and address any HR issues
with the Personnel department.
5. Ensure that management remains visible and accessible.
6. Review the status and effect of any PR activity.
7. Consider issuing further PR update to inform interested parties that
outsourcing has recovered to acceptable operating levels.
8. If [xxx] will not become habitable within one month, meet with Property
services to plan longer term recovery options. Otherwise, authorise
reconstruction and refit of [xxxx]. Also investigate the availability of local
office space for short-term rental.
9. Liase with the Recovery Team Leaders to begin to develop a long term
By 6 weeks
1. Begin to develop a long term recovery plan. Convene an CMT meeting to
confirm and communicate recovery objectives and strategies.
2. Decide if refit of [xxxx] is viable. If necessary, search for local office space for
short-term rental.
3. Consolidate the detailed damage assessment and salvage report from the
Primary Site Team.
4. Meet with the loss adjuster and the insurance company representative to
establish the basis for submitting insurance claims.
1. Contact Alternate Site Team Leader to confirm progress on the permanent
site, in particular:
• Construction/refurbishment.
• Floor layout design.
• Plans for phased occupancy of the site.
• Procedures for security, cleaning, post and other services.
• Procurement, installation, commissioning and testing of replacement
fileservers.
• Procurement, installation, commissioning and testing of replacement
PABX.
• Status of voice and data communication links.
• Cutover date and time.
• Emergency procedures.
• Health and Safety regulations satisfied.
6. Control all expenditure decisions and maintain regular contact with the
Finance department.
7. Work with the Primary Site and Alternate Site Teams to ensure the
prompt submission of any insurance claims.
8. Use the Alternate Site Team Help Desk:
• Inform it of any problems at the alternate site.
• Inform it of any systems-related problems.
• Check extent of data loss following restoration of backups.
• Check availability of individual servers and other systems.
• Check salvage status - availability of paper-based records and
extent of information lost.
• Request updates on casualties / staff well being.
• Request staff counselling or other assistance, if required.
• Request support for recruitment, if necessary.
9. Conduct regular CMT briefings on progress and strategy.
• Provide the minimum data to initiate the response and explain the current
situation.
• Verify the Team’s specific Emergency Response tasks.
• Identify any business-critical activities which should receive priority.
• Confirm CMT and Team Leader’s immediate contact details.
• Give notice of the CMT and Team Leaders’ briefing time and place.
• Clearly state the need for secrecy pending a formal press release.
• Instruct Team Leaders to prepare Initial Assessment Forms.
• [xxxx] has an account with [TAXI companies], which should be used where public
transport is unsuitable or unavailable [section B.3.4].
• Reimbursement of minor travel expenses must be obtained through a regular
expense claim.
• Reimbursement of major travel expenses such as airline tickets, must be
sanctioned and obtained through the CMT via the Recovery Team Leader.