You are on page 1of 19

PROJECT NAME : CIN-17AA0321-CONCRETING OF TADAO ROAD, PASUQUIN, ILOCOS NORTE

ITEM / WORK : EXCAVATION

LEFT
STATION
HEIGHT, m BOTTOM BASE, m TOP BASE, m
7+940 2.30 2.20 2.12
7+945 2.30 2.20 2.10
7+950 2.30 2.20 2.11
7+955 2.30 2.20 2.11
7+960 2.30 2.20 2.09
7+965 2.30 2.18 2.09
7+970 2.30 2.18 2.07
7+975 2.25 2.18 2.11
7+980 2.25 2.25 2.17
7+985 2.23 2.25 2.20
7+990 2.20 2.28 2.05
7+995 2.25 2.28 2.05
8+000 2.20 2.28 2.05
8+005 1.88 2.25 2.07
8+010 1.94 2.25 2.10
8+015 1.73 2.28 2.15
8+020 1.54 2.27 2.14
8+025 1.86 2.30 2.18
8+030 1.90 2.25 2.11
8+035 2.25 2.25 2.13
8+040 2.20 2.25 2.12
8+045 2.00 2.25 2.16
8+050 2.30 2.25 2.05
8+055 2.17 2.30 2.17
8+060 1.90 2.30 2.18
8+065 1.80 2.30 2.18
8+070 1.85 2.28 2.17
8+075 1.87 2.25 2.14
8+080 1.95 2.20 2.08
8+085 1.70 2.20 2.08
8+090 1.68 2.18 2.06
8+095 1.32 2.19 2.11
8+100 1.35 2.19 2.09
PASUQUIN, ILOCOS NORTE

AREA, sq.m. VOLUME, cu.m.

4.97
4.95 24.78
4.96 24.75
4.96 24.78
4.93 24.73
4.91 24.61
4.89 24.50
4.83 24.28
4.97 24.50
4.96 24.84
4.76 24.31
4.87 24.09
4.76 24.09
4.06 22.06
4.22 20.70
3.83 20.13
3.40 18.07
4.17 18.91
4.14 20.77
4.93 22.67
4.81 24.34
4.41 23.04
4.95 23.39
4.85 24.49
4.26 22.76
4.03 20.72
4.12 20.37
4.10 20.55
4.17 20.69
3.64 19.53
3.56 18.00
2.84 16.00
2.89 14.32
total = 705.76
PROJECT NAME : CIN-17AA0321-CONCRETING OF TADAO ROAD, PASUQUIN, ILOCOS NORTE
ITEM / WORK : EXCAVATION

RIGHT
STATION
HEIGHT, m BOTTOM BASE, m TOP BASE, m
8+100 1.30 2.30 2.18
8+105 1.33 2.40 2.33
8+110 1.30 2.40 2.35
8+115 1.29 2.35 2.3
8+120 1.26 2.35 2.32
8+125 1.26 2.40 2.34
8+130 1.18 2.35 2.28
8+135 1.07 2.30 2.22
8+140 0.98 2.35 2.28

EXCAVATED VOLUME = 820.26


EXCAVATION FOR STONE MASONRY= 1789.25
TOTAL = 2609.51
PASUQUIN, ILOCOS NORTE

AREA, sq.m. VOLUME, cu.m.

2.912
3.14545 15.143625
3.0875 15.582375
2.99925 15.216875
2.9421 14.853375
2.9862 14.82075
2.7317 14.29475
2.4182 12.87475
2.2687 11.71725
total = 114.5
STATEMENT OF WORK ACCOMPLISHED
FOR THE PERIOD OF AUGUST 10 - SEPTEMBER 11, 2017
PROGRESS REPORT NO. 1

PROJECT ID NO : CIN-17AA0321
PROJECT NAME : CONCRETING OF TADAO ROAD
LOCATION : PASUQUIN, ILOCOS NORTE

Unit Physical Unit Contract


ITEM NO. DESCRIPTION of Target Cost Amount
Measurement Quantity
Provision of Field Office for the
A1.1(8) Mo. 7.00 11,224.00 78,568.00
Engineer (Rental Basis)
B.5 Project Billboard units 2.00 3,400.92 6,801.84
B7 Occupational Safety and Health Program Mo. 7.00 25,267.29 176,871.03
B9 Mobilization & Demobilization l.s. 1.00 87,593.56 87,593.56
100(2) Clearing and Grubbing l.s. 1.00 315,762.30 315,762.30
101(4)a2 Removal of Structure / Obstruction Lm 6.00 514.71 3,088.26
102(2) Roadway Excavation Cu m 3,545.00 128.28 454,752.60
104(2)d Embankment Cu m 1,619.00 489.47 792,451.93
105(1)a Sub-grade Preparation Sq m 26,203.50 18.16 475,855.56
200(1) Aggregate Sub-base Course Cu.m. 4,108.00 626.15 2,572,224.20
311(1)C1 PCC Pavement (thk=230mm, w=6100mm) Sq m 19,733.50 1,223.06 24,135,254.51
Reflective Thermoplastic Pavement
612(1) Sq m 830.43 1,247.72 1,036,144.12
Marking (white)
404(1)A Reinforcing Steel Bar kg 13,762.95 54.08 744,300.34
405(1)a2 Structural Concrete, Class A Cu m 297.28 7,273.87 2,162,376.07
500(1)b1 Pipe Culvert and Storm Drain (610 mmØ) Lm 4.00 2,212.79 8,851.16
500(1)B3 Pipe Culvert and Storm Drain (910 mmØ) Lm 2.00 3,690.96 7,381.92
506(1) Stone Masonry Cu m 880.00 3,679.84 3,238,259.20
600(3) Curb and Gutter lm 1,122.00 1,075.39 1,206,587.58
37,503,124.18

PREPARED BY: RECEIVED BY:


REMIGIO GENERAL CONSTRUCTION ENGR. INANAMA MAYBELLE DULDULAO
CONTRACTOR DPWH-INED1 PROJECT ENGINEER
ORK ACCOMPLISHED
ST 10 - SEPTEMBER 11, 2017
REPORT NO. 1

ACCOMPLISHMENT
REL. WEIGHT (%) THIS PERIOD
QTY AMOUNT %

0.21% 1.10 12,346.40 0.03%

0.02% 2.00 6,801.84 0.02%


0.47% 1.10 27,794.02 0.07%
0.23% 0.35 30,657.75 0.08%
0.84% 0.35 110,516.81 0.29%
0.01% 0.00 - 0.00%
1.21% 2,609.51 334,747.33 0.89%
2.11% 0.00 - 0.00%
1.27% 4,000.00 72,640.00 0.19%
6.86% 0.00 - 0.00%
64.36% 0.00 - 0.00%

2.76% 0.00 - 0.00%

1.98% 0.00 - 0.00%


5.77% 0.00 - 0.00%
0.02% 0.00 - 0.00%
0.02% 0.00 - 0.00%
8.63% 404.47 1,488,384.88 3.97%
3.22% 0.00 - 0.00%
100.00% 2,083,889.03 5.56%

APPROVED BY:
ENGR. EFREN J. REMIGIO
RESIDENT ENGINEER
STATEMENT OF WORK ACCOMPLISHED
FOR THE PERIOD OF AUGUST 10 - SEPTEMBER 11, 2017
PROGRESS REPORT NO. 1

PROJECT ID NO : CIN-17AA0321
PROJECT NAME : CONCRETING OF TADAO ROAD
LOCATION : PASUQUIN, ILOCOS NORTE

Unit Physical Unit Contract ACCOMPLISHMENT


ITEM NO. DESCRIPTION of Target Cost Amount REL. WEIGHT (%) THIS PERIOD
Measurement Quantity QTY AMOUNT
Provision of Field Office for the
A1.1(8) Mo. 7.00 11,224.00 78,568.00 0.21% 1.13 12,683.12
Engineer (Rental Basis)
B.5 Project Billboard units 2.00 3,400.92 6,801.84 0.02% 2.00 6,801.84
B7 Occupational Safety and Health Program Mo. 7.00 25,267.29 176,871.03 0.47% 1.13 28,552.04
B9 Mobilization & Demobilization l.s. 1.00 87,593.56 87,593.56 0.23% 0.40 35,037.42
100(2) Clearing and Grubbing l.s. 1.00 315,762.30 315,762.30 0.84% 0.40 126,304.92
101(4)a2 Removal of Structure / Obstruction Lm 6.00 514.71 3,088.26 0.01% 2.00 1,029.42
102(2) Roadway Excavation Cu m 3,545.00 128.28 454,752.60 1.21% 2,127.00 272,851.56
104(2)d Embankment Cu m 1,619.00 489.47 792,451.93 2.11% 875.00 428,286.25
105(1)a Sub-grade Preparation Sq m 26,203.50 18.16 475,855.56 1.27% 10,000.00 181,600.00
200(1) Aggregate Sub-base Course Cu.m. 4,108.00 626.15 2,572,224.20 6.86% 1850.00 1,158,377.50
311(1)C1 PCC Pavement (thk=230mm, w=6100mm) Sq m 19,733.50 1,223.06 24,135,254.51 64.36% 0.00 -
Reflective Thermoplastic Pavement
612(1) Sq m 830.43 1,247.72 1,036,144.12 2.76% 0.00 -
Marking (white)
404(1)A Reinforcing Steel Bar kg 13,762.95 54.08 744,300.34 1.98% 0.00 -
405(1)a2 Structural Concrete, Class A Cu m 297.28 7,273.87 2,162,376.07 5.77% 0.00 -
500(1)b1 Pipe Culvert and Storm Drain (610 mmØ) Lm 4.00 2,212.79 8,851.16 0.02% 0.00 -
500(1)B3 Pipe Culvert and Storm Drain (910 mmØ) Lm 2.00 3,690.96 7,381.92 0.02% 0.00 -
506(1) Stone Masonry Cu m 880.00 3,679.84 3,238,259.20 8.63% 648.89 2,387,819.36
600(3) Curb and Gutter lm 1,122.00 1,075.39 1,206,587.58 3.22% 0.00 -
37,503,124.18 100.00% 4,639,343.43
PREPARED BY: RECEIVED BY: APPROVED BY:
REMIGIO GENERAL CONSTRUCTION ENGR. INANAMA MAYBELLE DULDULAO ENGR. EFREN J. REMIGIO
CONTRACTOR DPWH-INED1 PROJECT ENGINEER RESIDENT ENGINEER
OMPLISHMENT
HIS PERIOD
%

0.03%

0.02%
0.08%
0.09%
0.34%
0.00%
0.73%
1.14%
0.48%
3.09%
0.00%

0.00%

0.00%
0.00%
0.00%
0.00%
6.37%
0.00%
12.37%
FREN J. REMIGIO
DENT ENGINEER
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ILOCOS NORTE 1st
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE-1
Cavit, Laoag City, Ilocos Norte

CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED


from November 23, 2017 to December ___,2017

Contract ID: 17AA0321


Project ID: P00147248LZ
Contract Name: Concreting of Tadao Road, Pasuquin, Ilocos Norte

Contractor: KVC CONSTRUCTION / REMIGIO GENERAL CONSTRUCTION (JV) Payment Certificate No.: 3

Original Unit Price Original Revised Unit Price Revised Total Qnty. Quantity Total Qnty. Balance Cost of Cost of Cost Balance
Item No. Description Unit Contract in Contract Quantity in Contract Approved in Approved to this of Previous This to of
Quantity Pesos Cost Pesos Amount Prev. Billing in this Billing Date Quantity Billing Billing Date Cost
Original Contract
A.1.1(8) Provision of Field Office fo the Engineer(Rental Basis) mo. 7.00 11,224.00 78,568.00 7.00 11,224.00 78,568.00 3.27 2.68 5.95 1.05 36,702.48 30,080.32 66,782.80 11,785.20
B.5 Project Billboard units 2.00 3,400.92 6,801.84 - 3,400.92 - - - - - - - - -
B7 Occupational Safety and Health Program Mo. 7.00 25,267.29 176,871.03 7.00 25,267.29 176,871.03 3.27 2.68 5.95 1.05 82,624.04 67,716.34 150,340.38 26,530.65
B9 Mobilization & Demobilization l.s. 1.00 87,593.56 87,593.56 - 87,593.56 - - - - - - - - -
100(2) Clearing and Grubbing l.s. 1.00 315,762.30 315,762.30 1.00 315,762.30 315,762.30 0.50 0.38 0.88 0.12 157,881.15 119,989.67 277,870.82 37,891.48
101(4)a2 Removal of Structure / Obstruction Lm 6.00 514.71 3,088.26 6.00 514.71 3,088.26 2.00 4.00 6.00 - 1,029.42 2,058.84 3,088.26 -
102(2) Roadway Excavation Cu m 3,545.00 128.28 454,752.60 - 128.28 - - - - - - - -
104(2)d Embankment Cu m 1,619.00 489.47 792,451.93 - 489.47 - - - - - -
105(1)a Sub-grade Preparation Sq.m. 26,203.50 18.16 475,855.56 22,602.24 18.16 410,456.68 19,701.75 50.27 19,752.02 2,850.22 357,783.78 912.90 358,696.68 51,760.00
200(1) Aggregate Sub-base Course Cu.m. 4,108.00 626.15 2,572,224.20 5,047.39 626.15 3,160,423.25 2,904.00 1,019.46 3,923.46 1,123.93 1,818,339.60 638,334.88 2,456,674.48 703,748.77
311(1)c.1 PCC Pavement (thk=230mm, w=6100mm) Sq m 19,733.50 1,223.06 24,135,254.51 16,294.93 1,223.06 19,929,677.09 9,050.00 150.00 9,200.00 7,094.93 11,068,693.00 183,459.00 11,252,152.00 8,677,525.09
404(1)a Reinforcing Steel Bar kgs. 13,762.95 54.08 744,300.34 - 54.08 - - - - - - - -
405(1)a2 Structural Concrete, Class A Cu m 297.28 7,273.87 2,162,376.07 - 7,273.87 - - - - - - - -
500(1)b1 Pipe Culvert and Storm Drain (610 mmØ) Lm 4.00 2,212.79 8,851.16 - 2,212.79 - - - - - - - -
500(1)B3 Pipe Culvert and Storm Drain (910 mmØ) Lm 2.00 3,690.96 7,381.92 - 3,690.96 - - - - - - - - -
506(1) Stone Masonry Cu m 880.00 3,679.84 3,238,259.20 2,387.00 3,679.84 8,783,778.08 2,287.00 85.00 2,372.00 15.00 8,415,794.08 312,786.40 8,728,580.48 55,197.60
600(3) Curb and Gutter lm 1,122.00 1,075.39 1,206,587.58 - 1,075.39 - - - - - - - -
612(1) Reflective Thermoplastic Pavement Markings (White) Sq.m. 830.43 1,247.72 1,036,144.12 670.36 1,247.72 836,421.58 - - 670.36 - - - 836,421.58
Revised Standardized Pay Items of Work - - - -
B.5 Project Billboard each 2.00 3400.92 6,801.84 2.00 - 2.00 - 6,801.84 - 6,801.84 -
B9 Mobilization & Demobilization l.s. 1.00 87593.56 87,593.56 0.50 0.40 0.90 0.10 43,796.78 35,037.42 78,834.20 8,759.36
102(2) Surplus Common Excavation cu.m. 6,042.00 128.28 775,067.76 3,305.00 2,012.25 5,317.25 724.75 423,965.40 258,131.43 682,096.83 92,970.93
104(2)d Embankment from Borrow cu.m. 1,566.00 489.47 766,510.02 1,309.50 40.00 1,349.50 216.50 640,960.97 19,578.80 660,539.77 105,970.26
404(1)a Reinforcing Steel kgs. 12,333.00 54.08 666,968.64 - 12,333.00 - - - 666,968.64
405(1)a.3 Structural Concrete, Class A cu.m. 179.40 7273.87 1,304,932.28 - 179.40 - - - 1,304,932.28
500(1)b.1 Pipe Culverts (D610mm) l.m. 10.00 2212.79 22,127.90 - 10.00 - - - 22,127.90
500(1)b.3 Pipe Culverts (D910mm) l.m. 9.00 3690.96 33,218.64 - 2.00 2.00 7.00 - 7,381.92 7,381.92 25,836.72
600(4) Curb and Gutter l.m. 1,130.00 1075.39 1,215,190.70 - 1,130.00 - - - 1,215,190.70
New Item of Work
101(3)b.1 Removal of Actual Structures/Obstruction sq.m. 435.00 110.93 48,254.55 - 28.30 28.30 406.70 - 3,139.32 3,139.32 45,115.23
311(1)a PCC Pavement (t=150mm, w=1550mm) sq.m. 787.00 725.13 570,677.31 - - - 787.00 - - - 570,677.31
500(1)b.2 Pipe Culvert (D760mm) l.m. 2.00 3,554.08 7,108.16 - - - 2.00 - - - 7,108.16
37,503,124.18 39,199,497.62 23,054,372.53 1,678,607.25 24,732,979.78 14,466,517.84
PROJECT: CIN-17AA0321-CONCRETING OF TADAO ROAD, PASUQUIN, ILOCOS NORTE
WORK DESCRIPTION: STONE MASONRY

STATION HEIGHT TOPPING BASE AREA VOLUME


8+220 RIGHT 1.97 0.4 1.182 1.55
8+230 RIGHT 2.5 0.4 1.5 2.37 19.6
8+240 RIGHT 2.85 0.4 1.71 3 26.85
8+250 RIGHT 3.1 0.4 1.86 3.5 32.5
8+260 RIGHT 3.4 0.4 2.04 4.14 38.2
8+270 RIGHT 3.2 0.4 1.92 3.71 39.25
8+280 RIGHT 3.1 0.4 1.86 3.5 36.05
8+290 RIGHT 2.85 0.4 1.71 3 32.5
8+300 RIGHT 2.2 0.4 1.32 1.89 24.45
total = 249.4

STATION HEIGHT TOPPING BASE AREA VOLUME


8+420 RIGHT 3.05 0.4 1.83 3.40075
8+425 RIGHT 2.98 0.4 1.788 3.26012 16.652175
8+430 RIGHT 2.48 0.4 1.488 2.34112 14.0031
8+435 RIGHT 2.08 0.4 1.248 1.71392 10.1376
8+440 RIGHT 1.4 0.4 0.84 0.868 6.4548
total = 47.247675

STATION HEIGHT TOPPING BASE AREA VOLUME


8+480 RIGHT 2.4 0.4 1.44 2.208
8+485 RIGHT 2.45 0.4 1.47 2.29075 11.246875
8+491.65 3 0.4 1.8 3.3 18.589244
8+493 TO 8+498.3 3.3 0.4 1.98 3.927 20.8131
TOTAL = 50.649219

STATION HEIGHT TOPPING BASE AREA VOLUME


10+620 LEFT 2.8 0.4 1.68 2.912
10+625 2.65 0.4 1.59 2.63675 13.871875
10+630 2.82 0.4 1.692 2.94972 13.966175
10+635 2.83 0.4 1.698 2.96867 14.795975
10+640 2.83 0.4 1.698 2.96867 14.84335
10+645 2.83 0.4 1.698 2.96867 14.84335
10+650 2.84 0.4 1.704 2.98768 14.890875
10+655 2.84 0.4 1.704 2.98768 14.9384
10+660 2.84 0.4 1.704 2.98768 14.9384
10+665 2.85 0.4 1.71 3.00675 14.986075
10+670 2.85 0.4 1.71 3.00675 15.03375
10+675 2.88 0.4 1.728 3.06432 15.177675
10+680 2.88 0.4 1.728 3.06432 15.3216
10+685 2.9 0.4 1.74 3.103 15.4183
10+690 2.9 0.4 1.74 3.103 15.515
10+695 2.95 0.4 1.77 3.20075 15.759375
10+700 2.95 0.4 1.77 3.20075 16.00375
10+705 2.88 0.4 1.728 3.06432 15.662675
10+710 2.88 0.4 1.728 3.06432 15.3216
10+715 2.86 0.4 1.716 3.02588 15.2255
10+720 2.85 0.4 1.71 3.00675 15.081575
TOTAL = 301.59528
TOTAL VOLUME = 249.4
+ 47.247675
+ 50.649219
+ 301.59528
TOTAL VOLUME = 648.89217 cu.m.
UIN, ILOCOS NORTE stationheight, footing,
m base
m at
base
top,
atmbottom,
area, m
sq.m.
volume,cu.m.
10+620 2.2 0.6 0.4 1.68 2.91
10+625 2.05 0.6 0.4 1.59 2.63 13.85
10+630 2.22 0.6 0.4 1.69 2.94 13.925
10+635 2.23 0.6 0.4 1.69 2.95 14.725
10+640 2.23 0.6 0.4 1.69 2.95 14.75
total = 57.25

STATION HEIGHT TOPPING BASE AREA


8+480 RIGHT 2.4 0.4 1.44 2.2
8+485 RIGHT 2.45 0.4 1.47 2.29
8+491.65 RIGHT 3 0.4 1.8 3.3
L = 5.30 3.3 0.4 1.98 3.92
total =
301.59528
648.89217
lume,cu.m.

VOLUME

11.22
18.58
20.77
50.57
PROJECT NAME : CIN-17AA0321-CONCRETING OF TADAO ROAD, PASUQUIN, ILOCOS NORTE
ITEM / WORK : EXCAVATION

LEFT
STATION
HEIGHT, m BOTTOM BASE, m TOP BASE, m
7+940 2.30 2.20 2.12
7+945 2.30 2.20 2.10
7+950 2.30 2.20 2.11
7+955 2.30 2.20 2.11
7+960 2.30 2.20 2.09
7+965 2.30 2.18 2.09
7+970 2.30 2.18 2.07
7+975 2.25 2.18 2.11
7+980 2.25 2.25 2.17
7+985 2.23 2.25 2.20
7+990 2.20 2.28 2.05
7+995 2.25 2.28 2.05
8+000 2.20 2.28 2.05
8+005 1.88 2.25 2.07
8+010 1.94 2.25 2.10
8+015 1.73 2.28 2.15
8+020 1.54 2.27 2.14
8+025 1.86 2.30 2.18
8+030 1.90 2.25 2.11
8+035 2.25 2.25 2.13
8+040 2.20 2.25 2.12
8+045 2.00 2.25 2.16
8+050 2.30 2.25 2.05
8+055 2.17 2.30 2.17
8+060 1.90 2.30 2.18
8+065 1.80 2.30 2.18
8+070 1.85 2.28 2.17
8+075 1.87 2.25 2.14
8+080 1.95 2.20 2.08
8+085 1.70 2.20 2.08
8+090 1.68 2.18 2.06
8+095 1.32 2.19 2.11
8+100 1.35 2.19 2.09
PASUQUIN, ILOCOS NORTE

AREA, sq.m. VOLUME, cu.m.

4.97
4.95 24.78
4.96 24.75
4.96 24.78
4.93 24.73
4.91 24.61
4.89 24.50
4.83 24.28
4.97 24.50
4.96 24.84
4.76 24.31
4.87 24.09
4.76 24.09
4.06 22.06
4.22 20.70
3.83 20.13
3.40 18.07
4.17 18.91
4.14 20.77
4.93 22.67
4.81 24.34
4.41 23.04
4.95 23.39
4.85 24.49
4.26 22.76
4.03 20.72
4.12 20.37
4.10 20.55
4.17 20.69
3.64 19.53
3.56 18.00
2.84 16.00
2.89 14.32
total = 705.76

You might also like