Professional Documents
Culture Documents
1(2015)035
Abstract: With W anzhou Yangtze River Bridge as an engineering example, FEM is applied to simulate the whole bridge con
Downloaded from ascelibrary.org by University of California, San Diego on 02/10/16. Copyright ASCE. For personal use only; all rights reserved.
struction process to optimize the truss member assembling sequences and determine the critical member bars that should be mo
nitored. Real-time or fixed time data on stress and deflection are collected through a wireless integrated test system. Thus, the
status of stress and deflection for the cantilever structure is under good control to ensure safety and stability. Measurements and
theoretical computations of temperature effects are valuable for closure time selection and temperature deformation adjustment.
The middle span is closed under the conditions of "zero error and zero additional stress". A successful construction of this
Key words: bridge engineering; steel truss arch bridges; simulation; process optimization; construction control techniques;
temperature effects
Steel truss arch bridges have recently become popu and 12 m in internode length.
lar and important in the field of bridge constructions in A stiffening string with a leg height of 20 m is set at
China because such bridges have many advantages, such the intermediate pivot. The stiffened legs increase the
as an attractive shape, high carrying capacity, as well a height of the main girder truss at the pivot point to im
good anti-seismic and wind-resistant performance. How prove the structural stress conditions while enhancing the
ever, these bridges are complex to build because of the unity and smoothness of the bottom girder line of the rib
multiple system conversions during construction. A varie of the steel truss arch. The mid-span steel truss arch rib
ty of temporary support facilities is required during the uses the variable height N -type truss, which has an inter
construction of such bridges. These characteristics give mediate supporting point girder height of 41 m ( including
rise to many construction risks and require strict con the stiffening leg height ) . The rib girder at the mid-span
struction control accuracy. These issues have drawn con is 8 m high, the height from the vault to the bridge deck
cern from many scholars and bridge engineers in China. is 63 m, the vector height is 59 m ( the center distance of
However, people have limited experience in the con the arch rib truss ) , and the rise-span ratio of the arch is
struction of such bridges because of the small number of 1/6. 1. Different quadratic parabolas are adopted as the
similar bridges both in China and abroad. top and bottom arch axes of the arch rib truss, and a
Wanzhou Yangtze River Bridge is located at the curve smooth transition design is used to deal with the top
Tuokou bridge site of the Three Gorges reservOir area. arch axis and the top horizontal bar axis of the side span.
The main bridge is a three-span single-arch continuous A steel tie-girder is applied between the arch feet to with
steel-trussed girder structure of ( 168 + 360 + 168) m stand the great horizontal thrust that the arch rib pro
( figure 1). The steel beam is 697. 1 m in length ( inclu duces. This girder is also used as a railway traffic sys
ding the end girder ) with the two side spans of flat chord tem. The arch rib and the steel tie-girder are connected
truss girders. The mid-span is a steel truss arch bridge with booms, each with a maximum length of 55 m. As
with a rigid arch and flexible beams. The side-trussed sembled nodes are used for the connectivity of the steel
girder, and cast steel skateboard-style abutments are mid-span. Double sling towers are needed because of the
adopted as supporting points of the steel-trussed girder. large-span cantilever ( up to 180 m), whereas the side
QIN and SHA011 31 demonstrated the design of the span and mid span cables should be strengthened to im
bridge and conducted considerable research on the corre prove the stress performance of the construction progress
sponding lateral stiffness and wind-induced vibration structure. Heavy float tanks are placed at the end of the
characteristics of the boom. ZHAO[4 s] discussed the de side span girder (filled with water based on the calculat
sign of the tower and pier top arrangement method for the ing result) to balance the capsizing loads produced dur
the construction process and the closure steps of the (3) The trussed arch is closed first, the steel tie
[ ] girder is closed second, and the vertical and horizontal
large-span steel truss arch structure. PENG and LEI lo
analyzed the space static and dynamic characteristics of beams of the mid-span bridge deck system are assembled
duced stability in the construction process of the steel (4) The steel member bars are erected with the
truss arch structure. Most of the research focused on the girder erection crane, which can erect the steel truss arch
design and construction of this kind of bridge with limited both on the horizontal chord and on the 24-degree slope
attention directed toward the optimization of the erection when the arc moves.
process or field measurement of strength and stability 2. 2 Simulation model of the steel truss girder con
control. Against this background, this study probes into struction process
the issues of construction simulation, control measure Based on the original erection progress of the steel
ments, and precise computation of the erection and clo truss structure, MIDAS/Civil finite element software is
sure progress. We hope that this study will serve as a used to simulate the whole bridge construction process to
good guide for the construction of similar bridges. optimize the erection program. The full-bridge model is
member bars reach 248.4 MPa and 163.3 MPa when the
Fig.l Layout ofWanzhou Yangtze River Bridge (unit: m) reach 213.5 MPa and -210.97 MPa, respectively, be
2. 1 Overall erection scheme of the steel-trussed bars, some mid-span bridge deck systems and transverse
The steel girders are erected from the side span to closure are adjusted to be erected after the closure of the
the mid span, and closed at the mid-span point of the truss arc rib. Thus, the structure stress of each construc
main span, as shown in figure 2. tion progress meets the code requirements of stability and
(I) The side span steel truss girder ( 168. 7 m in strength. On the basis of the updated constructing
length) is erected by using the cantilever method with scheme, the member bars that should be monitored are
the aid of four temporary piers on each side. selected. The stretching forces of the temporary cables
(2) When the side span steel truss girder is com are determined according to the closure scheme of the
pletely erected, the steel girders continue to be assem steel-trussed girder and possible longitudinal and vertical
bled using t cantilever method from pier 5# and 6# to the displacement of the temporary pies. The whole bridge
Wanzhou
"""'--- �g
2
-
Low water level in three gorges reservoir: 133.46 m
�
Downloaded from ascelibrary.org by University of California, San Diego on 02/10/16. Copyright ASCE. For personal use only; all rights reserved.
1.735 56e+002 the steel truss girder and arch, provide the data for deter
9.870 80e+OOI mmmg the optimized closure techniques and tempera
2.386 02e+OOI
5.098 75e+OOI
tures.
1.258 35e+002 ( 4) The stress and deformation measurements of the
efficient=I.072 2E+OOI
key bars of the side span areas equipped with heavy float
(a)Mid-span is 120 m ing tanks appraise the effects of the tank loading.
Beam stress ( 5) A tension test is conducted on the temporary
2.134 9Ie+008
1.363 16e+008
cables to assure the safety and reliability of the tower-ca
5.914 09e+007 ble system.
0.000 OOe+OOO
( 6) The linetype and stress measurements of the
9.520 93e+007
I.723 84e+008 key bars in the completed bridge to accumulate the origi
roefficient=6.279 5E+OOO
nal data set up the bridge health records.
The section type of the monitoring bars and the cor
(b) Mid-span is 180 m
responding stress and temperature gauge layouts are illus
Fig. 4 Stress contour of two unfavorable construction
trated in figure 5. The upper and lower bars, web mem
stages of the original erection scheme
bers, tie-girder bars, and boom bar s of each tested sec
2. 3 Test scheme of the construction process control tion are emphatically tested, and each bar position can
The main span of Wanzhou Yangtze River Bridge be determined by the corresponding node numbers in fig
reaches 360 m, which exceeds the current scope of the ure 5. Gauges are laid out on each bar, as shown in fig
code for railway bridge designs. Thus, conducting the ure 6. A total of 260 strain-measuring gauges are needed
construction process control test to ensure the quality of for the whole bridge monitoring measurement.
the whole bridge is important. According to the structural A wireless integrated test system is applied to moni-
_ Wanzbou Yichang
�
[_:::_:1
Downloaded from ascelibrary.org by University of California, San Diego on 02/10/16. Copyright ASCE. For personal use only; all rights reserved.
tor the stress of bars at regular times or all day long be and conduct data analysis on time to determine the stress
cause of the large amount of gauges, high-test frequency, status of the key bars.
strict measurement and dispersed gauges layout. A total Electronic total station test system is used to meas
of 16 - 32 gauges are set to one group that accesses the ure the vertical and horizontal linetypes of the steel
collection substation placed at the node of the steel trussed structure in the main bridge. Optical pnsms are
trussed girder, whereas the main station is placed in a fixed at the bottom member bar nodes of the displacement
monitoring house 3 km away. The main monitoring sta monitoring sections to ensure the precision of the displace
tion is connected with collecting substation through a ment test. Two sets of prisms (a total of 24 prisms) are
constant wireless communication to collect the field data needed for the upstream and downstream sides of the trussed
- - - - - - - - - - - -�J
According to the construction scheme and simulation
Aj __j
construction stages and the corresponding erected truss
_______________ 1..,800 J
]� r� ] mmmmmmml[:l
A
bars are shown in table 1.
(a) Seetion type A (b) Seetion type B (c) Seetion type C Wanzhou Yangtze River Bridge
Vv'anzhou Yichang
�
14 81 __,_
13 91
�
�
I
11
'1\1
11
11\1/1' '1\1/1\111\l�l
111
""l..t / 13 14 Is 16 ,I
sl 91 " J-Y
I 2 10 1
Tab.1 Critical construction stages and erected truss bars respectively, with a difference of 0. 32 em. Meanwhile
Stage Brief description those values on Yichang side are 0. 075 rn and 0. 073 8 rn
CS01 Internodes 1# -4# steel girder erection respectively, with a difference of 0. 69 em.
4 -o-Measured elevation(upstreamJ
CS09
Internodes 28# steel girder erection (Wanzhou side); inter
.. o .. Measured elevatwn(dowJY � n)
-to.- TI1eoretical elevation /,0�
3
nodes 29# steel girder erection ( Yichang side)
-v-Pre-camber of ste" Jssed girder
CS10 Bottom bars of internodes 29# arc rib (Wanzhou side)
2 /f
h:(;
"'
CS11 Web and top bars of internodes 29# (Wanzhou side)
L
:lmag:inary line of tmssed
:#" girder's nodes
0
CS12 Tie -girder erection of internodes 29# ( Wanzhou side) -·-·-"'
-•···--···u- -·
tion of the steel-trussed girder in CS02 and CS03 have a theoretical calculating results of CS05
value is 0. 220 m, such that the difference is only -o- Measured elevation(u:pstream}
··0··· rvfeasured elevaiionldovm�tl-e'm;pJ
span on Wanzhou side are -0. 076 m and -0. 072 8 m, In CS07 , the measured deflection agrees well with
§
".;:J
"
"
6.0
CI
- -
---o-- z:
Measured elevation(upstream)
l'v[easured elevation(d wnetr )
§
"
"
"
5.1
--�--Measured elevation(upstream)
--o--Measured elevat!on(dowustre
/:
'"
" 4.5
/ <;;.:.1
--&--Theoretical elevation
�
-"'- Theoretical elevaiwn
__,,___ Pre-camber of steel
. �
" --v-- Pre-camber of steel t1 "��i
�
ed g:rder
:
0 a ·-� 3.4
L: L :
§';; 3.0 §�
·-g .g lmagimny line f trueeed
� g "!:1� ]" 1.7
1.5
/
L- �-=-��===:=-==:
" in of trucced •;J
"'" girder's node � ">
g1rder's nodes
il "...,-..1
0.0
0.0 ¢'�E=:=-----=-=X--• "
------v
" -.J)
" "
Eo E7 l'vb1 C1s Cn BJ E7 Cn Cn C26
Downloaded from ascelibrary.org by University of California, San Diego on 02/10/16. Copyright ASCE. For personal use only; all rights reserved.
M;4
Positions of deflection nodes (Wanzhou side) Positions of deflection nodes (Wanzhou side)
(a) Wanzhou (a) Wanzhou
o·- J /
-�� '
//"
9""" (
Imaginary line of trussed
Imas"inary line of trussed
"0
E; § J s
· I
J -
girder's nodes " girder's nodes
i L��
--
-----x--- -- :
=--=..:::x�--� -� ·,: _,
0.0
--
� :=��: : �;;��*
Cn
------------------ - ----,------ _____ ,_ - ---
Fig.lO Lineshape comparison between the measurements and Fig.ll Lineshape comparison between the measurements and
the theoretical results when the main span cantilever IS tive error is 3. 82%. The measured values on the Yichang
120 m, and the temporary cables are stretched. At this side are - I. 106 2 and - I. 136 0 m with an error of
stage, the measured and theoretical central deflections of 1. 99 em compared with the theoretical deflection of
the side span on the Wanzhou side are -0. 110 and - - I . 101 2 m, and the relative error is I . 8%. All theo
0. 098 m, respectively, with a difference of 1. 2 em. retical calculations agree well with the measured data be
Meanwhile, the values on the Yichang side are -0. 123 fore the closure of the steel-trussed girder, which means
and - 0. 111 m, respectively, with a difference of the accurate conditions of the main span closure may be
The measured deflections of node C26 are -0. 749 3 The measured elevation, the steel truss girder's pre
(upstream side) and - 0. 738 9 m (downstream side) camber, as well as the theoretical and measured deflec
when the main span cantilever is !56 m ( CS08). The tions of the completed bridge (CS14) are shown in figure 13.
theoretical deflection is - 0. 692 m, such that the error The data and curves show that the maximum deflection
between them is approximately 5. 21 em. The measured error between the theoretical results and the measure
values on the Yichang side are -0. 645 3 and ments is only 5. 54%. The measured lineshape of the
-0.635 I m with an error of 7. 2 mm compared with the completed bridge is smooth, and all the methods and
theoretical deflection of -0. 633 m. The deflection rela measures are suitable for the feasible closure scheme of
tive errors of node 26 are 7. 5% on the Wanzhou side the main span, which means that the lineshape of the
and 1. 13% on the Yichang side, as shown in figure 11. steel-trussed girders are under good control during all the
The measured deflections of node C26 on the Wanzhou construction stages. All the errors between the measured
side are - 0. 910 9 ( upstream side) and -0. 893 9 m values and the designed values of the trussed girder ele
(downstream side) when the cantilever of Wanzhou side vation, the vertical precamber, and the relative positions
is 168 m and the cantilever of Yichang side is 180 m. The of different nodes can meet the requirements stated in
theoretical deflection is -0. 938 3 m, such that the error Standard for Const=tional Quality Acceptance of Railway
between them is about 3. 59 em, and the deflection rela- Bridge arul Culvert EnginRering (TB10415 -2003) .
-<�- Measured elevation( upstream) 4 ..._Deviation curve of trussed girder's central line
4.8 __._Measured elevation(downstre
2
__._Theoretical elevation
--.--Pre�camber of steel I.,
0
�
;>
§ �2
Imaginary ine of trussed .,
.
girder1S n� ----v--- -4
0.0
v -�
Cl
�-g--------Q-==:::::______
·----.... -6
0 100 200 300 400 500 600 700
Eo E7 Mt4 Cts Cn C26
Downloaded from ascelibrary.org by University of California, San Diego on 02/10/16. Copyright ASCE. For personal use only; all rights reserved.
(a) Wanzhou
Fig.14 Central line deviation measuring curves of the
6.4
�- Measured elevation(upstream) steel truss girder of CS14
--<>-Measured elevation(downstream
4.8 --& -Theoretical elevation upstream member bar 33# on Yichang side). Stresses of
--v--Pre�camber of steel tru o �"
3.2 all the member bars at any construction stage are lower
Eo E1 Mt4 Cts C22 C26 upstream and downstream booms and the bridge deck
Positions of deflection nodes (Yichang side)
systems are installed after the closure of the arc rib, has
(b) Yichang
decreased the stresses of the structure to assure the struc
Fig.U Lineshape comparison between the measurements and tural safety and stability during construction.
theoretical calculating results of CS09
3. 4 Measurement and theoretical analysis of the
figure 14.
lever structure at different moments of one day before the mately 1 0 "C . The maximum theoretical longitudinal and
closure on the Yichang side are shown in figure 15. With vertical deformation values of the front end of the arch rib
the deformation of the structure at 5:00 am, which is ac are 7. 8 and -12. 3 em when the temperature rise rea
cepted as the "zero point", the maximum temperature ches 10 "C , as shown in figures 16 and 17. Moreover,
deformation of the cantilever structural end gradually in the deformation values of the end of the tie-girder are 3.
creased with the increase of temperature. The longitudi 1 and - 13. 1 em. The measurements and calculation re
nal and vertical displacements of the top bar end of the sults are consistent. On the basis of the test results of the
Downloaded from ascelibrary.org by University of California, San Diego on 02/10/16. Copyright ASCE. For personal use only; all rights reserved.
arc rib are 8. 2 and - 12. 6 em, respectively, and the temperature deformation, the truss girders are chosen to
displacements of the front end of the booms are 4. 2 and be closed at 3: 00 am. With the aid of the longitudinal
environmental temperature test results, the temperature the temperature deformation, the ideal result of "zero-er
Tab.2 Average axial stress measurements of the steel bars at some critical construction stages (unit: MPa)
3. 4. 2 Temperature stress tests and analysis of the bars former field data collected when the environmental tem
The temperature stress test results of some steel perature increases to 10 OC .
truss structure bars before closure are shown in table 3.
4 Conclusions
With the stress of the bars at 5 : 00, which are accepted
as the "zero point" the temperature stress increases grad (1) On the basis of the spatial finite element simu
ually with the ascent of the environmental temperature, lation results, the order of the bar erections are optimized
and decreases gradually with the descent of temperature for decreasing the maximum structural stress to avoid cer
Downloaded from ascelibrary.org by University of California, San Diego on 02/10/16. Copyright ASCE. For personal use only; all rights reserved.
in the afternoon. The maximum temperature stresses are tain risks in construction. The theoretical lineshape a
19. 91 (tensile stress) and -8. 92 MPa (stress). From grees well with the field data. The maximum error of the
the temperature stress contour of the bars are shown in mid-span deflection of the main span between the meas
figure 17 , in which the maximum thermal stresses are urements and the theoretical value is only 5. 54% when
19. 98 MPa and -8. 72 MPa, which are according to the the bridge is completed. The measured values of the
trussed girder elevation, the vertical pre-camber, the rel
Analysis results ative positions of different nodes, and the center line are
1.323 52e-OOI
consistent with the design values and meet the require
I 058 82e-OOI
I
7 941 14e-002 ments of the Standards for Constructional Quality Accept
I 5 294 I Oe-002
ance of Railway Bridges and Culvert Engineering
I
2 647 05e-002
l 0 000 OOe+OOO (TB10415 -2003).
C-ee IGient=l 195 2E+002
(2) The wireless integrated test system can provide
Fig. 16 Temperature deformation contour ( + 10"C) of CS09 " long-distance, real-time, and routine single gauge
1
measurements" and is a more convenient method to ana-
Axial stress lyze the stress of the bars in time and determine the sta
1.987 14e+OOI
1.467 20e+OOI tus of the structural safety and stability. During the whole
9.472 56e+OOI
construction process, the minimum stability-bearing coef
4.273 12e+OOO
0.000 OOe+OOO ficient value of the critical bar is 1. 13, and the minimum
-6.125 76e+OOO strength safety value is 1. 33. The optimized construction
zy� cient=l.l95 2E+002
scheme decreased the stress of the bars effectively to a
void the risk in construction and ensure the security and
Fig.17 Temperature axial stress contour ( + 10 "C) of bars of �
stability of the structures.
Tab. 3 Temperature axial stress measurement of the steel bars a day before closure ( unit: MPa)
YCSAIO -All 0.00 5.98 12.24 16.37 19.91 15.82 9.48 I.98
33"
YCXA10-All 0.00 5.83 11.97 15.96 19.76 16.26 10.06 2.04
( 3 ) The temperature effect tests of the cantilever Wanzhou Yangtze River Bridge [ J]. Bridge Construction, 2007
structure one day before closure prove that the maximum (S2): 14-17. (inChinese)
fectly in the sequence of the top bar, the web bar, the the Steel Truss Arch Tied Bar Beam Bridge of W anzhou
bottom bar, and the tied girder of the bridge deck sys- Yangtze River Bridge [J]. China Railway Science, 2007,
(Chinese version's doi: 10. 3969/j. issn. l002 -0268.2014.05.013, vol. 31, pp. 78 -85, 134, 2014)