NOTES

10mm thick
ROOF: CONCRETE ROOF TILES ON TRUSSES
220mm thick
CONCRETE ROOF TRUSSES internal plaster brick wall
ROOF NOTES DAMP PROOF MEMBRAINE
ROOF NOTES - TILES ON 38x38mm BATTENS AT 320mm CENTRES MAX
CONCRETE ROOF TILES TO MANUFACTURE'S SPECIFICATIONS
FLOOR FINISH AS ON FLOOR PLAN 10mm thick
38x38mm S.A PINE BATTERNS AT 345 C/C MAXIMUM 5610 AT 345 C/C MAXIMUM WITH '410 SISALATION' TO MANURACTURE'S skirting to match external plaster
ON 114x38mm S.A PINE RAFTERS AT 760mm C/C MAX ON 114x38mm S.A PINE RAFTERS
AT 760mm C/C MAX WITH 152x38mm S.A PINE TIE BEAM
114x38mm ROOF TRUSSES floor finish EMBEDDED AT LEAST 300mm INTO BRICKWORK WITH CONNECTING DEVICES ACCORDING TO
WITH 152x38mm S.A PINE TIE BEAM AT AT 760mm C/C MAX WITH 114x38mm S.A PINE WALL PLATE 30mm SAND CEMENT SCREED D.P.C
ALL WEB MEMBERS TO BE 114x38mm S.A PINE GRADE SIX
85mm SURFACE BED TABLE L2, SCHEDULE 1, OF SABS 0400
760mm C/C MAX WITH 114x38mm S.A PINE WALL PLATE CONCRETE ROOF TILES
ALL WEB MEMBERS TO BE 114x38mm 50 'ISOTHERM' MINERAL WOOL INSULATION 25mm SAND BLINDING -ALL WEB MEMBERS TO BE MINIMUM 38x114mm GRADE 4 WITH EQUAL BAYS SMALLER
S.A PINE TO BE GRADE SIX 38x38mm PINE BATTERNS THAN 1500mm. APPROVED BRACING MUST PREVENT BUCKLING AND KEEP TRUSSES UPRIGHT
trusses by specialist 150mm WELL COMPACTED
AT 345 C/C MAXIMUM
HARDCORE -VALLEY AND HIP RAFTERS TO BE GRADE 6 50x228 SA PINE
6.4mm gypsum ceiling board -LAMINATED TIMBER TO COMPLY WITH SABS 876
152x32mm TIE BEAM -50mm GLASS FIBRE INSULATION TO BE INSTALLED ON CEILING
plaster & paint NATURAL GROUND
(CEILING JOIST)
plaster & paint 50x38mmTILTING BATTERN CONCRETE ROOF
plaster & paint
38x38mm S.A BRANDERINGS STORM WATER MUST FLOW WHERE THE 600x230mm CONCRETE STRIP -CONCRETE ROOF TO ENGINEER'S DETAIL WITH MINIMUM 50mm THICKNESS
& PAINTED INTERIOR & EXTERIOR plaster & paint plaster & paint FOUNDATION FOOTING
DIRECTION OF THE SLOPE FLOWS -VERMICULITE SCREED GRADED TO 1:50 FALL TO 100m DIAMETER BILD IN DOWNPIPES
30mm THICK SCREED LAYED ON
85mm THICK CONC SURFACE BED dpc FFL FFL dpc
BRICK CORBELLING 6.4mm THICK BY 900MM WIDE -WATERPROOFING BY SPECIALIST WITH A TEN YEAR GUARANTEE AS PER SPECIFICATION
150mm WELL COMPACTED HARDCORE CORNICE TO CLIENT CHOICE
GYPSUM CEILING BOARD FIXED
*SMALL DSTV DISH WILL BE USED & POSITION APPROVED
UNDERNEATH THE SURFACE BED
600x230mm 600x230mm
/ EQUALLY APPROAVED
ON 38x38mm BRANDERING BY RESIDENTIAL MANAGER. FLOORS AND WATERPROOFING
concrete footing concrete footing SPACED AT 450x900mm c/c FIXED *SOLAR HEATING PANELS & AIR CONDITIONING UNITS -GROUND FLOOR SLAB=85mm THICK 20mpa CONCRETE PERFECTLY LEVEL AND AT
ON 52x152mm CEILING JOIST \ POSITION TO BE APPROVED BY RESIDENTIAL MANAGER MINIMUM 150mm ABOVE GROUND LEVEL ON PROPERLY COMPACTED HARDCORE FILL
TIE BEAM
INTO BRICKWORK -25mm THICK SCREED AND FINISHES AS INDICATED

10mm THICK EXTERNAL


-SUSPENDED CONCRETE FLOOR SLABS TO ENGINEER'S DETAIL AND SPECIFICATIONS
10mm THICK INTERNAL WASHING LINES /GAS INSTALLATIONS/
PLASTER PLASTER 110mm INTERNAL BRICK WALL PLASTERED -DPC UNDER ALL WALLS (EXCEPT FREE STANDING), FLOORS AND WINDOW SILLS
5610 CHIMNEY/COWL -1000mm 5610 REFUSE AREAS TO BE SCREENED OFF NOT
& PAINTED TO CLIENT'S COLOUR CHOICE AND TO ALL VERTICAL CHANGES IN FLOOR LEVELS
ABOVE HIGHEST PITCH TO BE VISIBLE FROM STREET/ PUBLIC AREAS
TO COMPLY WITH NBR PART V V1-4 10mm thick -FLUSHINGS TO ALL PARAPETS AND CHANGES IN ROOF LEVELS

natural
stone
CONCRETE ROOF TILES internal plaster
GEYSER INSTALLATION TO COMPLY WITH FROM CATCHPIT FITTED WITH GRATING AND SILT TRAP
SABS 0252 GLAZING TO COMPLY WITH skirting to match
-PLANTERS TO BE WATERPROOFED AND DRAINAGE INSTALLED
floor finish
SABS 0137 AND SABS 0400 PART "N"
FOUNDATIONS, BRICKWORK & PARTITIONS
plaster & paint ALL WORK TO COMPLY WITH SABS 0400 BOUNDARY WALLS TO MATCH HOUSE & TO BE -ALL FOUNDATIONS TO BE 25mpa CONCRETE , AT LEAST 200x700mm. MINIMUM
AND NATIONAL BUILDING REGULATIONS MAINTANANCE FREE ON NEIGHBOURS SIDE 200mm UNDER GROUND TO ENGINEER'S DETAILS AND SPECIFICATIONS
-BOUNDARY WALLS' FOUNDATION MUST NOT ENCROACH ON BOUNDARY AND WALLS
plaster & paint plaster & paint
ARE TO BE PLASTERED AND PAINTED ON THEW INNER WALL
ALL WINDOW & DOOR FRAMES TO BE GARDEN DOORS/ GATES SHOULD -PARAPET WALLS TO BE ATLEAST 300mmHIGH AND MAXIMUM 500mm WITH BRICKFORCE
ALUMINIUM HAVE SELF CLOSING ARM IN EVERY COURSE
R.E
R.E
I.E
-ALL SCREEN WALLS TO BE AT LEAST 1800mm HIGH ABOVE GROUND LEVEL
min 1:40 fall connecting to septic tank/future municipal sewer I.E 5610 CHIMNEY/COWL -1000mm 5610 -LINTOLS TO BE SUPPORTED MINIMUM 150mm FOR OPENINGS UPTO 4800mm.BRICKFORCE
I.E ABOVE HIGHEST PITCH
GLAZED EARTHENWARE
DISHED GULLEY CAST
TO COMPLY WITH NBR PART V V1-4 IN CONCRETE ngl CLEANING EYE ngl TO BE BUILT IN EVERY COURSE BELOW FLOOR LEVEL AND ABOVE WINDOW LEVEL, EVERY
CONCRETE ROOF TILES THIRD COURSE BETWEEN BETWEEN IN CONTINOUS BANDS

350 min
-NO TEETHING OR BLOCK BONDING WILL BE ALLOWED UNDER ANY CIRCUMSTANCES
-ANY PARTITION TO BE RODENT PROOF
5610 CHIMNEY/COWL -1000mm 5610 pipe laid
ABOVE HIGHEST PITCH to min 1:
40 fall STAIRS AND BALUSTRADES
TO COMPLY WITH NBR PART V V1-4
natural
stone

CONCRETE ROOF TILES


-STAIRS TO BE 750mm MIN WIDTH, TREADS 300mm , RISERS 170mm WITH 6mm MAX DEVIATION
INVERT LEVEL=+450 mm.
-1000mm HIGH BALUSTRADES TO ALL STAIRS AND BALCONIES
IF LESS ENCASE IN CONC
-MAX 3000mm VERTICAL RISE PER FLIGHT , WINDERS WHERE SHOWN ,TO BE AT LEAST 250mm
plaster & paint plaster & paint plaster & paint WIDE, 450mm FROM THE NARROW END AND ANGLE BETWEEN THE RISERS TO BE CONSTANT
whb
WC WC -MINIMUM HEADROOM TO BE 2100mm MEASURED FROM PICHLINE
B B
plaster & paint plaster & paint -GLASS BALUSTRADES (IF SHOWN ) TO BE SAFETY GLASS
R.E gulley R.E
I.E I.E
I.E
BUILDING MUST BE CONSTRUCTED GLAZING
ACCORDING TO ALL DETAILS AND SPECIFICATIONS
min 1:40 fall connecting to I.E
septic tank/future municipa
l sewer
CONTAINED IN THESE DRAWINGS AS PER SANS 1400.
ANY CHANGES TO DETAILS OR SPECIFICATIONS
MUST BE APPROVED BY ARCHITECT.
ENERGY EFFICIENCY SPECIFICATIONS MUST BE
APPLIED TO, ACCORDING TO -BATHROOM WINDOWS TO BE FROSTED GLASS
5610 CHIMNEY/COWL -1000mm 5610 SANS 10400-XA SHEET ATTACHED HEREWITH.
ABOVE HIGHEST PITCH -ALL GLAZING ON DOORS TO BE SATETY GLASS
TO COMPLY WITH NBR PART V V1-4

natural
stone
-ALL GLAZED AREA LESS THAN 300MM ABOVE FFL TO BE COVERED WITH SATETY GLASS
CONCRETE ROOF TILES
ELECTRICAL KEY
AREA SCHEDULE
LIGHT SWITCH
GROUND FLOOR AREA

plaster & paint SITE PLAN AREA =

SITE COVERAGE = %
plaster & paint
S

pipe & vent


R.E DOORS & WINDOWS SCHEDULE
min 1:40 fall connecting to septic tank/future municipal sewer SEE SCHEDULE DRAWINGS OF DOORS AND WINDOWS

DO NOT SCALE THE DRAWINGS

SANS 10400-T-2011. Edition 3


fire wall

4.9.2
R.E
I.E min 1:40 fall connecting to septic tank/future municipal sewer I.E b) ANY DOOR BETWEEN SUCH GARAGE & ANY
SUCH ROOM SHALL HAVE A FIRE RESISTANCE
fire wall fire wall
OF NOT LESS THAN 30minutes & SUCH
DOORWAY SHALL REQUIRE A THRESHOLD

fire wall
OF NOT LESS THAN 10mm &
R.E I.E c)NO COMBUSTIBLE ROOF COMPONENTS
concrete columns

SHALL PENETRATE THE SEPARATING ELEMENT


DIVIDING THE SPACE BETWEEN THE GARAGE
& THE HABITABLE ROOM

I.E
INVERT LEVE L=+450 mm.
IF LESS ENCASE IN CONC

I.E

I.E
R.E

CHIMNEY/COWL -1000mm
ABOVE HIGHEST PITCH concrete columns
TO COMPLY WITH NBR PART V V1-4

concrete columns