PROJECT : SMK (P) BKT KUDA SURAU

MASTER WORK PROGRAMME

PHASE ACTION BY MONTH/YEAR 2017 MONTH/YEAR 2018 MONTH/YEAR 2019


MAY SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC

A) SCHEMATIC DESIGN STAGE:

1) Site Survey Land Surveyor

2) Soil Investigation

3) Conceptual proposals & approval from client Architect ( CONFIRMATION FROM CLIENT OF THE LAYOUT & CONCEPT )

4) C & S Schematic Design C&S

5) M & E Schematic Design M&E

6) Cost Estimation QS

7) Layout & Planning Submission Architect / Planner ( PLANNING SUBMISSION )

8) Approval of Planning/Layout Architect / Planner

B) DESIGN DEVELOPMENT STAGE:

1) Architectural Working Drawings Architect ( BUILDING PLAN SUBMISSION )


for Building Approval/Submission

2) Building Plan Approval Architect ( TARGETED BUILDING APPROVAL DATE )

3) Architectural Construction Drawings/Details Architect

4) C & S Working Drawings for Submission C&S

5) M & E Working Drawing for Submission M&E

C) TENDER:

1) Preparation of Tender Documentation QS

D) CONSTRUCTION STAGE:

1) Earthwork / Site Clearing ( 1 MONTH )

2) Building Works ( TARGETED COMPLETION DATE 12/19 )

31) Handing Over

32) Inspection by various Authorities


(Technical Departments)
Consultants &
33) Application of C.C.C. Contractors

34) Issuance of C.C.C.