Document Title :

Prepared Checked Approved


Revision / Mechanical Works Quality Construction
Establishment Procedures
Omar Abdullah
No of Description : S. Phiske Abdullah Al- Ofi
Revision Pouring Concrete on Slab on Grade
QA / QC Construction Managing
Engineer Manager Director
Implementation Document No : MISCL – QMECP – 0004
Date
Contents / Reason for Revision

Jan.12, 2012
0 Establishment and Implementation
Jan.13, 2012
1. Purpose and scope

The purpose of this method statement is to explain the proper procedure on how to prepare and
cast slab on grade or any horizontal element or member including fixation of steel reinforcement,
MEP embedment’s, fixing of shutter etc. without injuries.

2. Work procedure

a. Site Planning
 Delivery – fresh concrete shall be batched from the approved supplier of concrete.
Concrete will be delivered directly to the site and to be received by MAKANA
Civil QC Engineer for checking of the required criteria of concrete. MAKANA
Civil QC Engineer will make sure the concrete delivered is as per the approved
design mix for the situated member to be casted.

 All data for testing on fresh concrete at site shall be recorded on the concrete pour
card.

b. Preparation

 After the blinding is casted and placement of waterproofing is done, the preparation
and casting for slab on grade shall be done.

 Fix the reinforcement steel as per the approved drawings, sometimes A393 BRC
mesh is indicated in the drawing and most commonly use in 250mm thick concrete
grade slab.

 Any loose binder or ties along the splices reinforcement steel shall be re-tightened.
Bend inward the free ends of the binding wire or ties.

 Use PVC spacer for vertical bars and concrete spacer for bottom as concrete covers.

 Ensure and coordinate with MEP staff for any MEP works required on the area as
per approved drawings.

 Fix the forms such; supports, sleeves etc., if any.

 Any damaged materials used for form work or shutter like plywood shall not be
used.

 All surface of forms or shutter facing concrete shall be treated with shuttering oil
and dampen with water few minutes before concrete will be poured.

 Clean the slabs on grade using air compressor for dust or any small particles or
deleterious materials that may impair the workability of concrete.
 The surveyor will then checked the level of the projected top surface of the slab and
place level strips if necessary to mark the exact level.

c. Concrete Pouring

 The concrete mixer must be stopped at the check point for the inspection of slump
test and to obtain sample cubes for test.

 One set of cubes shall be taken every 50 cubic meter concrete, each set consist of 6
cubes, 3 cubes to be tested on 7th days and 3 cubes to be tested for 28th days.

 Extra three cubes can be made for re-checking if in case circumstances may happen.

 Unload the concrete within 90 minutes from the batching plant loading time.

 Compact the concrete properly by using mechanical vibrators, extra vibrator shall
be available in case of any shortage or mechanical problems.

 Use approved hardener material after casting concrete when required. Make sure
applications shall be as per manufacturer’s recommendation.

 Use the power float for the smooth finish surface purpose. Store extra power float
near the casting area in case of any mechanical malfunctioning.

 Cure the casted area properly with covering concrete with hessian cloth and
polythene sheet on top but before placing the concrete wet the hessian with water.

 Cure the concrete by spraying water three times per day for a period of 7 days.

 The casted area or member shall be protected by placing barricade to prevent plants
and machineries damaged the concrete.

 Concrete pour card shall be filled by MAKANA Civil QC Engineer and to be


submitted to the MAKANA Project Engineer including concrete delivery notes, this
task will be done whenever required.

 Concrete cube test report shall be submitted to MAKANA Project Engineer

4. Safety

 All works shall comply with safety procedure or instruction set out in project safety
plan and municipality rules and regulations.

 Basic PPE to be worn by all staff and laborers.

 Trained operator and banksman would be engaged to control or operate heavy


equipment machine.

 Provide sufficient lighting whenever night casting.


 The concreting are as must be arranged with necessary equipment or tools for
concreting use such as vibrators, power float machine, shovel etc.

 Skilled and unskilled labor shall need to use safety requirements such as safety
helmet, safety shoes, goggles, gloves, vest etc.

 Safety devices and safety warnings shall be provided starting from the site entrance
gate till the casting area.

5. Equipment and Tools

 Concrete Pump
 Concrete Mixer
 Mini truck
 Bob cat
 Concrete vibrators
 Wheel borrow
 Slump tray
 Slump cone and other associated tools
 Rubber hammer

6. Materials and References

1. C40/20 Concrete Grade with additives


2. Deformed bars or A393 BRC mesh
3. Approved drawing