Contractor

Mc.DERMOTT ARABIA
CO.LTD

Sub-Contractor Doc. No. MCCL-MACL


ONSHORE WORKS FOR
Job No.
ManarahAl-Jubail SAFANIYA GOSP-I & ABU-ALI-
GOSP Page No. Page 01 of 13
Const. Co. Ltd.
Rev. No. A

METHOD STATEMENT FOR


SAMPLE HYDRO TEST PACKAGE

ISSUED FOR APPROVAL


Mc.DERMOTT ARABIA CO.LTD
Approved
Approved w/ comments

ISSUE Name:
STATUS

Signature:

Date & Time:

00 19.03.2016 Issued for Approval Ravi Shankar Abdul Khader


Reviewed by
Rev. No. Date Description Prepared by MCCL
MCCL

Rejected w/comments

Name:
-----------------------------------------------------------------------------------------------------------------------------------------------
Signature:
Users are advised to ensure the current revision status of this document
Date & Time:

Method Statement For Sample Hydro Test Package Page 1


Rev. A
REVISION HISTORY

Revision No. Revision Date Page Scope of Revision


A 19.03.2016 All Issued for Approval

Method Statement For Sample Hydro Test Package Page 2


Rev. A
PACKAGENO: G97-SAF-17-0001
TYPE OF TEST: HYDRO TEST SYSTEM: WILD CRUDE
AREA: SAFANIYA SUBSYSTEM:

Table of Contents

NO Description Documents Reference

01 Flow Chart for Test Package


SAIC-A-2003
1.1 Test Package Flow Chart

1.2 Review of Test Package SAIC-A-2003


02 Pre-Test Punch List Section
2.1 Test Procedure
Piping and Instrument Diagram, Isometric Drawings
2.2
& Applicable Drawings, SIS
2.3 Pre-Test Punch List
a Pre-Test Punch List Checklist SAIC-A-2010
b Pre-Test Punch List Form SATR-A-2007

03 QA/QC Documentation for the System to beTested

3.1 Fabrication Records

a Weld Map

b Weld Summary with NDT Verification SATR-W-2008

c NDT Records Records & Assessments

3.2 Inspection of Bolted Flange Joint Assembly SAIC-L-2014

a Flange Joints Inspection Certificate SATR-L-2001

3.3 Piping/ Equipment Internal Cleaning Inspection SAIC-L-2017

Method Statement For Sample Hydro Test Package Page 3


Rev. A
PACKAGENO: G97-SAF-17-0001

Table of Contents

No Description Documents Reference

a Internal Cleaning/Flushing Report SATR-A-2008

04 Pressure Testing

4.1 Verification of Testing Media for Hydro static Testing SAIC-A-2004


4.2 Verification of Testing equipment SAIC-A-2009
4.3 Verification of Test Preparation SAIC-A-2011
4.4 Filling & Pressurization SAIC-A-2020
4.5 Visual Inspection at Test Pressure SAIC-A-2024

4.6 Pressure or Leak Test Report SATR-A-2010

4.7 Depressurization and Disposal of Hydro Test Water SAIC-A-2022

05 Calibration of Test Certificate

5.1 Calibration Test Report (Pressure Gauge) Calibration Cert & Report
5.2 Calibration Test Report (Relief Valve) Calibration Cert & Report
5.3 Pressure/ Leak Test Report (Test Manifold) Calibration Cert & Report

5.4 Water Chemistry Report (Test Medium) Calibration Cert & Report

06 Re-Instatement and/ or Final Assembly

6.1 Final Piping Punch list (Piping Re-Instatement) SAIC-A-2006


Final Inspection/ Re-Instatement Punch list (Punch
6.2 SATR-A-2011
list by the Contractor)

Method Statement For Sample Hydro Test Package Page 4


Rev. A