Professional Documents
Culture Documents
A CASE STUDY
A
DISSERTATION
Submitted in partial fulfillment of the requirements
for the award of the degree
of
Master of Technology
In
Electrical Engineering
(Control Systems Specialisation)
of
Kwiksbetra University,
Knrakshetra
Submitted
by
ASHOK KUMAR MAHESHWARI
Certified that the dissertation entitiled “Automation of Steam Turbine (EAST)-A Case
Study” which is being submitted by Mr. Ashok Kumar Maheshwari, Roll No. 295731, in
his own work carried out by him under our supervision and guidance. This matter
embodied in this report has not been submitted to any other University or Institution for
Lecturer Professor
D ept of Electrical Engg. Dept, of Electrical Engg.
REC Kurukshetra REC Kurukshetra
ACKNOWLEDGEMENT
Dr. Krishna Gopal, Professor, Electrical Engg. Dept, and Sh. J. S. Lather, lecturer,
guidance and consistent help given at every stage of this dissertation work. I am
extremely grateful to Er. Amod Jindal and Er. P.N. Tripathi, AEE, Panipat Thermal
Power Station, who provided me with really rich and nourishing food for thought on the
showered at me. Their faith in my capacity to achieve things has always stood me in
good stead.
CONTENTS
CHAPTER-1. INTRODUCTION
2.1 Introduction
2.2Turbine Stress Evaluator (TSE)
2.3Electro-Hydraulic Controller(EHC)
2.4Automatic Turbine run-up Systems(ATRS)
2.5LP Bypass and Gland Seal Steam Control
2.6Automatic Turbine Tester (ATT)
2.7Turbine Protection
2.8 Vibration & Expansion Measurement
2.9 Load shedding Relay
CHAPTER-3. Discussions and Suggestions
References
CHAPTER-I
INTRODUCTION
Panipat Thermal Power Station (PTPS) is located 10 km away from
Panipat on Panipat-Jind Road. First unit of PTPS was commissioned in 1979, now it
has five generating units with total generation capacity of 650 MW (Four units of 110
MW each and one unit of 210 MW), one more unit of 210 MW capacity is under
construction which is likely to start generating in June 2001. The area occupied by
the power station is about 744 acres in addition to 640 acres for ash disposal. The
Sewah ( near Panipat) from where it is fed to the transmission network of Haryana.
The raw water supply for various plant usages and condenser cooling (circulating
water) is obtained from Western Yamuna Canal. Five operating units are divided into
Stage-I includes Unit-I and Unit-2 with capacity 2X110=220 MW. Unit I and
respectively.
Stage-m includes Unit-5 with generating capacity of 210 MW. This unit was
commissioned in 1990.
exciter and other auxiliaries on unit basis. The steam generators are of direct fired,
reheat type designed for pulverized fuel (coal) with provision of HSD/HFO/LSHS
firing at startup and low load conditions. Steps have been taken to minimize the
91.5m, 120m, 180m height serve the boilers of stage-1, stage-11 and stage-in
The classical static excitation system with AVR has been employed in Unit-I
and Unit-11 while U nit-in, Unit-IV &Unit-V have been provided with complete solid
Unit-I - Unit-4 are each of 110MW and have almost identical constructional
Each unit can generate upto maximum 26.4 lakh units o f electricity per day (if the
plant load factor is 100%). At average 1800MT o f coal and 350MT o f DM water
Main Boiler: Boiler supplied by BHEL , Tiruchirapalli, TN has the capacity of 375
t/hr with max design pressure of 158.2 kg/cm2 and temperature 540°C.
Coal Mills: Each unit has five coal mills, four remain in service (for full load) and
one stand by. Each coal mill has Raw Coal feeder (RC feeder) with 20t/hr capacity
and Coal pulverizer with 16.5 t/hr capacity. As a change of design Stage-II (i.e. Unit
Ill & Unit-IV) has been provided with six coal mills out of which five remain in
service.
Induced Draft Fans (ID Fans): Unit has three ID fans, two remain in service and
one stand by. Each has the capacity of 132 m3/sec. Fan motor is of 600 kW, 6.6 kV
rating.
Forced Draft Fans (FD Fans): Unit has two FD fans. Each with capacity 58m3/sec.
Primary Air Fans (PA Fans): Unit has two PA fans. Each with capacity 40m /sec.
Dust Collecting System: Each Unit has a Electrostatic Precipitator (ESP) for
collecting dust from the emission. Each ESP has a capacity of Gas flow 200 m3/sec
and two parallel gas path. Efficiency 99.52% and treatment time 24.68 sec.
Main Turbine:
At 110 MW- steam flow at inlet is 364.5 t/hr (pressure -130 atm., Temp. 535°C R/H
Head 23 mmWC
Number 7
Head 50 atm.
Condensate Pumps
Generator
Output 110 MW
Rated Frequency 50
1995-96 54 56 58 46
1996-97 67 84 85 42
1997-98 58 102 80 76
1999-2000 101 - 70 94
Unit-5 can generate 50.4 Lac unit every day (corresponding to 100% PLF).
unit overview of Unit-5 is shown in fig. 1.1 . Brief Technical specifications of this
Main Boiler: Boiler is Natural Circulation, Wet bottom, Tangential fired, balanced
draft, Radiant Re-heat type with direct fired pulverized coal system. Boiler is
equipped with superheater, Economizer and air heaters to improve its efficiency.
Coal Mills: Unit has 6 coal mills (A, B, C, D, E, and F). As per design 4 should
remain in service one standby and one for maintenance but practically 5 coal mills
remain in service. Every coal mill has a Raw Coal feeder of 37.5 t/hr capacity.
ID Fans
FD Fans
Number 2
Dust Collecting System: Electrostatic Precipitator (ESP) has been used to collect
the dust from the emission before it reaches the stack. The rating of the ESP
Temperature 140 C
Boiler is equipped with 12 number of Heavy Oil guns to support the coal mills
. These HFO guns are tilting, tangential, Steam atomized, air cooled type. 12 Guns
are located in Four Corners of three elevations (Elevation AB, CD & EF). Oil firing
rate is 750 to 1000 kg/hr/gun and the pressure is 4.5 to 6.0 kg/cm2.
Turbines and Auxiliaries:
for HP, IP and LP Turbine. The HP turbine is single flow type whereas the IP & LP
are of double flow type. It is basically engineered on reaction principle with throttle
governing.
Servo prime 46 oil is used for Governing and lubrication system where as
Servo Vonvel 46 for HP bypass system. Specific gravity for this oil at 50 C should
0.852.
No. of AOP 2
No. of EOP 1
No. of MOP 1
Condensate System
Condenser
cooler, Three LP heaters, Two HP heaters, one Gland steam condenser, one Dearator
used as a part of close condensate cycle. Their purpose is to increase the temperature
of the water, which is taken from the hot well and fed back to the boiler drum.
ELECTRICAL SYSTEM
Generator:
Generator Transformer
Make BHEL
Connection symbol Y -n d l
Station Transformer
Make BHEL
Rating 40 MVA ^
Number 2
Make BHEL
TaWe 1.5
From the statistics of last five years (Table 1.1-1.5) it is very much clear that the
performance of 210 MW Unit is much better as compared to 110 MW units (i.e. unit
1-4). For example yearly PLF of 110 MW units is around 35% whereas that of 210
MW is more than 80%, specific oil consumption for 110 MW unit is around 30
KL/MU where as that of 210 MW is 3-4 kl./MW, No. of Tripping for a 110 MW unit
is around 100 per year and that of 210 MW unit is 40 per year. Auxiliary
factor may also be playing its part in the performance of old 110 MW units.
One main area of the technological advancement is in the field of Control and
EAST package.
This work is carried out to study the various aspects of EAST package such as
Chapter 2 is devoted to study the EAST package starting with the Introduction
of this Package. Chapter deals with all the important features of this package such as
Turbine Run-up System (ATRS), Automatic Turbine Tester (ATT), LP bypass and
gland steam controller, Turbine protection, Turbo Supervisory system and load
shedding relay.
discussed. Suggestions for the solution of these problems and results there of are also
briefly discussed.
DIAGRAM NUMBER * 2000 VERSION
CHAPTER-2
EAST Package
2.1 INTRODUCTION: The ever increasing size of Thermal Units, plant complexity
and operation at higher optimal steam pressure and temperature demand considerable
increase in the role of control and instrumentation. The C&I system being provided
along-with steam turbine to KWU design has been developed to meet such demands.
The system was earlier called ATRS (Automatic Turbine Run-up System). It
includes only binary control like alarms, protection, interlock and above all automatic
run up system for barring gear, vacuum pulling and Turbine rolling. All these
6. Turbine Protection
full load keeping the stresses on the turbine components within permissible limits is
of prime importance. TSE is specifically designed for achieving the above objectives.
During changes in operation of the turbine, the internals of the turbine are subjected
stress is proportional to the difference in the temperature at the surface on the steam
side and the mid wall temperature. This difference is compared with the permissible
turbine, thermal fatigue, strength of material, and the geometry of the components.
The difference between permissible temperature difference and the actual temperature
an analogue computing circuit and displayed on the instrument as upper and lower
temperature margins upto the stage of synchronization, and as load margins during
subsequent loading. The display also indicates the component, which is critical at
TSE system consists of following five computing channels
Channels 1 & 5 are from the steam admission area and channels 2,3 &4 are
NiCr-Ni thermocouples are used for measuring the surface temperature near
steam 0; and mean temperature (midwall temperature) 0m for the above five channels
mentioned. But for the channels 2 & 4 the mean shaft temperature 0m is derived by
computation from 0*. The output of thermocouple is fed for analog signal
conditioning. Where it is converted into 4-20 mA signal and fed to TSE. The actual
load of the turbine generator set Pad is measured separately and a current signal of 4
20 mA is available for load indication and computation of load margin . The speed is
also measured separately and 4-20 mA signal is available for display in the TSE
indicator.
computing the mean shaft temperatures. The steam temperature representing the
surface temperature of the shafts are measured at suitable locations and they are
in fig 2.1.
The temperature margin for turbine shaft is computed from the difference in
shaft surface temperature and simulated mean shaft temperature. Turbine stress
evaluator predetermines the constraints only from thermal stress consideration. Other
vital turbine parameters like differential expansion axial shift etc. are to be considered
margins with the help of mechanical stress calculations for on load operation of the
TG set. The available temperature margins are converted into corresponding load
margins by TSE circuitry with the help of mathematical algorithms. These load
margins are the guiding factors to further load or unload the TG set on both manual
Principal of Operation:
temp.at 50% depth and 0i is actual temp, at 100% depth) is calculated as D0 and this
is compared with the permissible upper and lower temperature difference D0uper and
D0i per which are dependent on the midwall temperature and are derived from the
function generators. The difference of D0uper or D0iper and D0 are the available
temperature margin D0u and D0j. The lowest of the respective upper and lower
temperature margins of admission area and turbine areas are selected for display and
for further processing. Fig above gives the maximum permissible temperature
difference allowed versus Bm- These curves depend upon the thickness of the material
at the point where we are calculating margins and as well as on material composition.
Hence all the five channels of the TSE have different curves. The basic philosophy
for computing the margins remains the same. For example refer figure above
so e=(e,-em)=280- 250=30°C
9imaX-280+30=310°C
©**,=280-110=170°C
It means that 0j can be increased by 30°C safely. This is known as upper margin.
Similarly 0; can be decreased by 110°C safely and this is known as lower margin.
Temperature margin for all the five channels are calculated in the similar way and the
minimum upper margin and minimum lower margin of all the five channels is
selected separately and fed to EHC for controlling the rate of rise of speed and rate of
rise/fall of load (rate of fell of speed can not be controlled as it will come down on its
Influence of Margin during Load: During loaded condition the rate of rise of load
depends upon upper margin and rate of decrease of load depends upon lower margin
0 to 30°C = 0 to 25 MW/min
If margin is more than 30°C load will increase / decrease at a constant rate of
proportional to margin.
The TSE indicator has two separate sections one for starting upto
synchronization stage and other for on load conditions (Fig.2.2 ). The sections are
illuminated according to the operating mode. The sector shaped aperture formed by
two semi circular disc displays margins. The top rectangles get illuminated and
indicate the component, which is the cause for imposing the minimum margin. The
upper boundary of the transparent sector indicates the upper margin for startup /
increasing load and the lower boundary indicates lower margin for decreasing load /
lowering of speed.
During speeding up and upto synchronization, the marking on the white scale
indicate the actual speed of the set. The aperture formed by the red disc indicate the
safe temperature margins (in Kelvin) in which components remain stressed within the
permissible level only. These indicated margins along with the actual metal
rolling correcting action has to be taken when the margin narrows down or becomes
zero.
During on load operation the display indicates the load range in which the
output can be altered without any restriction on the rate of load change.
KWU design steam turbines are provided with hydraulic as well as Electro
hydraulic governing systems. The addition of EHC enables the operation of the turbo
set in interconnected grid system, with precise maintenance of rated frequency of the
grid by means of exact frequency load characteristics with good response, reliable
operation of isolated power grid, reliable control during load rejection, low speed
deviation under all operation conditions, safe operation in conjunction with Turbine
Stress Evaluator etc. Normally EHC will be in action while hydraulic controller
S The electrical control system incorporating the power supply, sub controller for
Principle of Operation: The functioning of the speed control are, start up and shut
shedding, limitation of turbine speed before reaching the overspeed protection limit
and for load control when necessary. The speed controller essentially compares the
speed reference generated by the speed reference limiter circuit, and the actual speed
The EHC governing system essentially consists of following three control loops
These control loops essentially influence the steam control valves actuated by
Electro-hydraulic converter and valve lift controller. Fig.2.3 Shows the schematic
Speed Controller:
The speed controller compares the speed reference generated by the speed
reference limiter circuit and the actual speed of the turbine and accordingly provides
system based on the hall probe principle. The output of each pick up is processed in
three different channels. The output from only one channel is used. In the event of
failure of this channel, the system is automatically switched on to the other channel.
The speed reference is generated by the speed reference limiter control loop. The
desired reference speed is set with the help of a potentiometer remotely from control
desk or manually from the panel. In the speed reference limiter the reference speed
signal is juxtaposed with the output from the turbine stress evaluator at every instant
highest permissible rate of speed increase which is consistent with the safe separation
of the turbine. After attaining the target reference speed the output of the speed
reference limiter is held constant. The output of the speed reference limiter is
automatically blocked in the event of a fault in the turbine stress evaluator and the
speed of the set cannot be changed until and unless TSE is suitably disconnected.
The speed controller exhibits a steady state proportional control to form the necessary
Load Control:
The load control loop consists of load reference setter, frequency load droops and
load controller. The load controller is designed for two modes of operation
The output of the power controller acts along with other controllers in a selection
mode on the Electro hydraulic converter and thus acts on the turbine control valves.
Measurement of Load:
to load controller via a selection circuit. The system is connected to PT’s and CT’s of
the generator. Solid state multiplicator based upon Hall effect are used for
speed control. The load reference limiter generates the time dependent load reference
signal PRiim, which is fed to the load controller. The signal rises (during building up
of load) at a rate MW/min selected through load gradient setter until PR is reached.
enables the response of the controller to be proportional for small changes of load
reference signal and PI for large changes. TSE limiting is effective irrespective of the
type of control action. To limit the total power delivered by the turbine the system is
equipped with maximum load reference limit Pmax which has priority over all other
influences acting directly or indirectly on the valve lift controller. To enable smooth
transition from speed controller (during start up) to load controller (after
synchronization) matching of the integrator output signal with actual power output is
Frequency Influence:
unit. The droop characteristic of the frequency controller can be varied from 2.5 to
At P.T.P.S Unit-V automatic turbine run-up system (ATRS) consist of three subgroup
3. Turbine system
system accomplishes its task which comprises of keeping at least one of the two
condensate pumps in operation, evacuation of non condensible gases from the system,
maintaining the desired level of condenser pressure when the turbine is in operation
and breaking the vacuum as and when required by the mechanical process through
SLC Drains
The logics of sub groups control for oil supply system perform its task
comprising starting relevant oil pumps ensuring turning of the Turbine as and when
The logics of subgroup control for turbine during start up execute the task
subsequent block loading through a number of sequential steps and sub loop controls
(SLC) namely
SLC fo r Drains
This subgroup control also shutdown the turbine, which comprises unloading, closure
of steam supply to turbine, isolation from grid and bringing the turbine drains to the
desired position.
Permissive
STEP-15
The program will return back to Step-12 if condenser vacuum > 0.88 kg/cm
Permissives:
MOT level or OK
STEP-1
STEP-2
Or
STEP-3
H2 Purity >97%
STEP-4
STEP-5
SLC AOP-I ON
SLC AOP-II ON
SLC EOP ON
SLC JOP-I ON
SLC JOP-II ON
STEP-6
STEP-7
JOP-I OFF
JOP-H OFF
STEP-9
STEP-10
AOP-I OFF
AOP-II OFF
EOP OFF
COMPLETE
The SGC program will revert back to step no. —1 if the turbine speed
510 rpm at step no. 8 or the speed is less than 2800 rpm at step no. 11.
Permissives:
Starting Device 0%
Load Controller ON
Synchronizer OFF
STEP-1
SLC Drains ON
HPCV-1 Close
HPCV-2 Close
IPCV-1 Close
IPCV-2 Close
STEP-2
-do- >-40K
-do- >-40K
STEP-3
STEP-4
STEP-5
STEP-6
HPESV-1 Open
HPESV-2 Open
STEP-7
Fire ON
STEP-8
STEP-9
Tracking Device ON
IPESV-1 Open
IP ESV-2 Open
Step-10
H2 purity >97%
STEP-11
STEP-12
STEP-13
STEP-14
STEP-15
STEP-16
STEP-17
STEP-18
STEP-20
STEP-21
Generator Breaker ON
COMPLETE
STEP-51
SLC Drain ON
STEP-52
Speed Controller ON
STEP-53
STEP-54
Synchronizer OFF
STEP-55
Starting Device 0%
STEP-56
COMPLETE
dumping the steam from reheater outlet directly into condenser at suitable steam
reheat circuit due to its large time constant during transient non steady state. LP
bypass valves get opened and dump steam to condenser to such an extent as to
maintain the reheater pressure at a value derived form the criteria representing the HP
turbine flow conditions at any given instant during load changes. This control
criterion ensures that only the requisite flow is maintained through the IP and LP
turbines. The control of LP bypass system is hooked up by same control oil /fluid
LP bypass control system is to regulate the pressure in the reheat system under
Since the reheat pressure is a function of steam flow, tie referdnce varkable fop the
Dwring st'rtup ang shut dlwn a fixed set point is employed instead of variable set
point. If the reheat pressure exceeds the set#value the electsonic coltroller#actuatep
Prespure traosducers are useg for acruisitioo of rehdat pressure (actual valve) and mf
pqessure wransducdr generctes a ctrrent skgnal 4-00 mA proportion' 1to the pressure.
The set point values ( a fixed set point and a sliding set point) which are selected
depending on the operating condktions, 're utilkzed whepeby the higher of the two
values acts on the controller. The fixed set point can be adjusted from the control
room between zero and 20% of the maximum reheat pressure/ The sliding set point is
deriwed from the pressure bedore the#HP drump blading by meals of mawching
alplifier#and a ftnction generatop. A vasiable upper pressure lilit for vhe set point
is#also prlvided b{ the me ns of wkich the set poiot is lilited a walue below the
To protect whe conddnser agcinst exaessive steam innet tempgrature tnder bysass
condition, whe bypaps values are cllsed wheo the sev permissible telperature is
valve in the signal fluid line of the LP bypass is moved to reset position, as a result of
protection devices, causing the closure of! bypass ptation kn case If following
eveltualitifs
• Contpol faulw
This pystem eosures the sealiog of gl'nds in KP, IP aid LP tusbines ulder
through steam supply valve (MAW-10) is taken to seal the HP, IP and LP glands.
During this period the valve (MAW-50) connecting this header to condenser is kept
closed. After 40% load, valve (MAW-50) open and MAW-10 closed. System is so
designed that leak off steam from front and rear end of HP turbine goes to the
condenser through valve MAW-50 while steam from the two IP glands is utilized for
Fig 2.8 Shows the schematic diagram of Gland Seal Steam Control system. This seal
steam header pressure is sensed by the pressure transmitter and converted into 4-20
mA (-10 to +30m bar). The reference value for steam pressure can be set by means of
potentiometer on the controller (0-20mbar). This is compared with the actual value.
The deviation is fed to the PI controller via progressive static characteristics (not
shown). This enables fast action in the event of large disturbance e.g. a load throw
off. For small deviation upto lmbar, the characteristic is chosen to ensure stable
control under all operating conditions. Remote control manual operation of the valve
is possible when the controller is switched off. Bumpless transfer from auto to
The output of the controller is used for deriving valve position reference through a
valve position reference module. When the controller is off the output signal of the
For a positive input voltage, the module gives out the position reference value for the
steam supply valve (MAW-10). For a negative input voltage the modules gives the
position reference value for leak steam valve. An overlap is given for stable
The output of the pressure controller is applied through valve position reference
module. Each valve has a PDD position controller in its loop. The difference between
valve position reference valve and the value of the actual valve position is the control
deviation for one position controller. The actual valve position is measured by a
Hall-Effect potentiometer located at the control valve. The output of the position
controller (0-4.8V) is applied to the EHC after power amplification which determines
Functional groups have been developed for testing at regular intervals the
functioning of stop valves, control valves and protection devices while the turbo set is
in operation. This facility increases the reliability at the same time without
interrupting operation of the Turboset. The ATT has been divided into two subgroups
Only one subgroup can be selected at a time. The test programme will be
An alternative trip oil circuit is established for the duration of testing of the
safety devices in order to ensure tripping of the turbine if called for during testing.
The successful completing of the tests are concluded from the check back signals of
oil pressure and other conditions. Associate annunciation are also activated enabling
Subgroup Stop and Control Valves: HP/IP stop and control valves are the final
control elements of the safety devices and hence their serviceability is important as
One of the major test requirements is that the output of the Turboset must be
less than maximum load as it calls for closing of one valve at a time.
emergency stop and control valves as soon as any condition occurs which causes
danger to the turbine. The command from the protection system goes to the trip
solenoids, which reduces the trip oil pressure to zero. Reduction in trip oil pressure
closes the stop and control valves. The pressure of the trip oil can also be reduced
system has two independent channels, which gives command to two independent
solenoids. The response of one of the solenoid valves is sufficient to trip the turbine
1. Hydraulic/Mechanical Trip
2. Electrical Tnp
the Auxiliary trip oil pressure which in turn reduces the trip oil thus closing stop and
control valves.
over speed. The turbine trip is initiated when an admissible speed limit (approx.
111%) is exceeded. Trip initiation takes places with the assistance of mechanical
overspeed governors.
Low-Vacuum Trip: In the event of deteriorating vacuum, the turbine trip is initiated
to protect the condenser from over pressure. In this way the steam supply through the
turbine to the condenser is interrupted. Trip initiation occurs when the admissible
Axial-Shift Displacement high: When axial shift displacement of the rotor is too
great, which can occur as a result of unacceptable wear of the axial bearing pads, the
turbine is put out of operation in order to avoid damage. Turbine trip is initiated by
Electrical Trips: As mentioned earlier electrical trip system has two independent
channels, which operates two independent solenoid valves. Both the channels are
Lubricating Oil pressure low: The supply of the oil to the bearing in endangered
whenever the lubricating oil pressure drop. Hence to prevent damage to bearings
Low Vacuum Trip: As explained in Hydraulic vacuum falls below admissible value
Fire Protection: Turbine trip is initiated with in the framework of the fire protection
measures to stop delivery of oil from the main oil pump (turbine driven) as quickly as
possible.
Fire Off: When “Boiler Fire off“ signal appears, turbine trip is initiated to protect the
Electrical Generator Protection: Turbine trip is initiated together with the response
Manual Trip: This initiation device enables the operating personnel both during
operational shut down or in the event of detection of failure to trip the stop and
stores steam. If drum level will become Very High then there may be chances of
intermixing of water into steam which may result into wet steam entry in the turbine
In the operation of large steam turbines certain vital parameters are required to
the operational conditions of the turbine during various stages of operation like start
Measurement system for this includes all necessary sensors mounted on the
turbine with flexible leads for connection to junction boxes, circuits for processing
the sensor signal alongwith power supply monitoring , signal level monitors, test
• Relative Expansion
• Absolute Expansion
• Valve position
Absolute Bearing Vibrations Measurement
The seismic mass type pickup is mounted on the bearing pedestal. The
airgap in resilient way by a spring. The magnetic flux in the airgap remains constant.
The permanent magnet if firmly connected to the housing and to the magnetic return
path. Above the natural frequency, the plunger coil is steady in space due to its mass
- inertia. Thus a fixed point in space is created and vibrations can be referred to this
point. The relative motion between the coil and magnet generates a voltage, which is
range of 16Hz to 200 Hz and measures the amplitude of the vibrational displacement.
suppresses any interference voltage picked up by the cable. Then the signal is
shaft vibration with respect to the bearing pedestal and adding the absolute bearing
manner according to the Eddy Current method. The measuring range is 0-400
This measurement yields information on the position of the shaft in the thrust
position of the shaft as axial shift beyond permissible limit would lead to mechanical
The measuring principle is based on the fact that the impedence of a coil with
iron core depends upto the sized of the air gaps in the magnetic circuit. There are two
such coils mounted on the either side of the measuring disc, and connected to form a
bridge, the output of which changes proportionally to the change in air gap, the bridge
casings and rotors of the turbine due to their different thermal inertia. This is the case
particularly during start up and in case of major load changes. These expansions are
Relative expansions of HP, IP and LP turbines are monitored in the same way
as described earlier for axial shaft position measurement. The difference lies in the
size of the measuring discs and the sensor arrangements. For the large range of
relative expansion in LP turbine, the measuring disc is in the form of double cone to
produce less change in air gap due to large change in expansion. As the bridge output
for a large air gap change becomes nonlinear a linearizing network is also used in the
sudden load throw off. Whenever a large load throw off takes place the turbine speed
increases. To prevent the turbine from reaching overspeed trip value the Emergency
Stop valves are closed for a short time by load shedding relay. Three conditions have
If any of the above condition is not fulfilled load shedding relay will not
operate as governing itself is sufficient to take care of small disturbances. If all the
three conditions are satisfied in that case load-shedding relay operates for short time
and closes the control valves for the same time. The time for which load shedding
relay operates depends upon the amount of the load thrown off. Maximum time of
60
THfX*>06*>nei A TyP/CAL C oM#JT/M6> C H M N E l
0
*
o
*
a
k
0
<v> \
V ^
LU
« > i/i
3 $
3! vo
c\ ui K
fc> v>
H t /
fc i £
C^f
O <v
K i
< V3T
O U-
a
* I
u) h
K <
<U
h u)
<
X
< £
-J O
a. ~4
<^e> Z
o
i
H
|ELEcT8.oHyI>**ul- lc
C o N T « .o L l - e / i ( S t > c \
Unit
control
Group control
(when,how m a n y , w h i c h 17) \
/
\
\
Control interface
N10.017U
f 'r ~
OPERATOR
0Subgroup
0 No01 Checkback Signal
'SUBGROUP IN
OPERATION 1
SHUT DOWN SI OR Start
SEQUENCE Release
— T7—
o ff ! cn & AND
SI OR
Checkback
Criteri a
3J
Step ,
Indication
KWU
Subgroup Control Structure
Q V 792
F it, : - 2 . S ’
Step
C D C D m C D C D Indication
16 | | 7 I C D C D H
Q D QD P D Q D
Criteria
1* 1 I * 1 13 | U1 D?J Indication
LD 11 1 Ll J CD QD
LuJ LhJ I 13! QD
OFF Fault ON
Shutdown Start up
program in - - programm in
operation
--P1 ^ LJ 1_ih' operation .
( Flicker light)
Sh u t d o wn ""
JO 9
3 Gk
(Flicker light)
•Start up
. , _ k
•Label
Subgroup
ON / OFF
m
o
<
'71
— J!
LU ■ i
3 ' :
> . i
v p w;; j
.>»• SS/ ;.c- •:;<*&rJ
Chapter-3
DISCUSSIONS AND SUGGESTIONS
clear from the performance abstract of this unit (Table 1.5). However, a few
problems/ Deficiencies/ Deviations from design were observed by the author while
In this chapter some such problems are discussed. Suggestions for the
solution of these problems are also presented after consulting the maintenance
As we studied (refer Article #2.3) that while raising the speed of the turbine
and till house loading is achieved system remains in speed control mode. After house
loading is achieved load control mode comes into picture and frequency influence
remains ON. But practically ‘Frequency Influence’ remains OFF during normal
running of the unit and system remains in pressure control mode only.
The grid conditions are highly fluctuating. There are very rapid and heavy
fluctuations in the system frequency and in case the load is allowed to change with
particularly because the control of fuel and air to the boiler is not in the automatic
control mode- even when on the auto-mode, there is inbuilt process delays in
regulation of coal flow, its burning and the resultant system pressure.
exercise for Frequency Control. The Coordinated Master Control (CMC) is not
functional in this unit. The effect of frequency Influence was set in such a way that
Even with the limited variation of load (upto 10MW) due to frequency
the range of 49.67 to 50.33 Hz. or beyond there is a sudden fluctuation of 20MW in
load that causes appreciable variation in the steam parameters even if the action for
p - f ( p - 3-%
PROBLEM #3: Stoppage of Barring Gears:
It has been observed many times that machine coast down to rest position
during the hot shut down period.
Reason: It has been well noticed that the speed of the turbine on barring gear, comes
down slowly whenever there is a wet steam entry into the turbine glands instead of
the usual superheated gland sealing steam supply through auxiliary PRDS.
Suggestion/Action Taken: To prevent entry of water into the turbine following steps
were taken.
1 For gland sealing steam valve (MAW-10) a protection (close) provided if
temperature before the valve is <195°C. This protection was provided through
ATRS
2 Auxiliary PRDS temperature which was maintained at 200°C now it kept >210°C
ensuring 15 to 20°C superheat (minimum)
3 The motorized drain valve for MAW-10, calibration for auto open temperature
<195°C and closes for temperature >200°C, has been rechecked and set right.
After these adjustments the problem has been more or less eliminated.
Further there are few suggestions for retaking the machine on barring gear if coasted
down to rest in hot condition.
1 Cut-off gland sealing steam supply and kill the system vacuum
2Reduce the turbine lubricating oil temperature to 40°C
3 With one AOP, JOP and gate valve gearing valve in open position, try for hand
barring.
4 If hand barring is not possible, on no account must force be used for shaft
rotation.
5 Readjust the jacking oil header pressure > 120 kg/cm2 using the pressure
regulating valve or take second JOP if required.
6 Reduce the jacking oil pressure for the individual bearing
66
REFERENCES
1 Operation and Maintenance (O&M) Manual - Vol. 1 & Vol. 2 For 210 MW,
Unit-V, by Design India Limited.
2 Instruction Manual for 210 MW plant by BHEL.
3 Power Plant Operation Manual by National Power Training Institute.
4 Control and Instrumentation Vol. I, II & HI by National Power Training
Institute.
5 Thermal power Plant Familisation Vol. H & HI by national Power Training
Institute.
6 J. Arogyaswamy, “ Power Station Practice”, 1985, IBH Publication.
7 E.B. Jones, “ Instrument Technology” 1985 New-Butterworth Publication.
8 Charles H. Becker, “ Plant Manager”, Hand Book, 1981, Prentice hall
Publication.
68
REFERENCES
1 Operation and Maintenance (O&M) Manual - Vol. 1 & Vol. 2 For 210 MW,
Unit-V, by Design India Limited.
2 Instruction Manual for 210 MW plant by BHEL.
3 Power Plant Operation Manual by National Power Training Institute.
4 Control and Instrumentation Vol. I, II & HI by National Power Training
Institute.
5 Thermal power Plant Familisation Vol. II & HI by national Power Training
Institute.
6 J. Arogyaswamy, “ Power Station Practice”, 1985, IBH Publication.
7 E.B. Jones,MInstrument Technology” 1985 New-Butterworth Publication.
8 Charles H. Becker, “ Plant Manager”, Hand Book, 1981, Prentice hall
Publication.
68