Daily Report of Mobis Quality Center Project

■ Report By Hankuk Construction & Trading Pvt. Ltd.


Date 15-Dec-14 Day
Number of Employees & Workers
Annual Manpower Daily Manpower
Up to Yesterday Up to today Skilled Unskilled
0 21 9 12

Part Weekly Plan Progress


ARCHITECTURE VIP toilet Brick work & Plaster
Old Toilet Renovation work
Near Dinning washbasin work
Demolition of old floor
ELECTRICAL Emergency light Conduit work
Workstation raceway work
Cable try & LT Panel
Earthling work
MECHANICAL

Part Today Work Description Progress


ARCHITECTURE VIP toilet Brick work layout & Tile cutting
Old Toilet Renovation work
Near Dinning washbasin brick work
Demolition of old floor

ELECTRICAL Emergency light Conduiting layout


Workstation raceway layout
LT Panel fabrication
Earthling layout

Part Tomorrow Work Plan Progress


ARCHITECTURE VIP toilet Brick work
Old Toilet Renovation work
Near Dinning washbasin brick work
Demolition of old floor

M/S Hankuk Construction Trading Pvt, Ltd.


ELECTRICAL Emergency light Conduiting layout & Laying
Workstation raceway layout & Laying
LT Panel fabrication
Earthling layout & Laying

Feed back

Prepared by: Mr. Manish Sharma Checked by:

M/S Hankuk Construction Trading Pvt, Ltd.


ter Project
Monday

Daily Manpower
Today total
21

Remark

Remark

Remark

M/S Hankuk Construction Trading Pvt, Ltd.


y:

M/S Hankuk Construction Trading Pvt, Ltd.


Working Photo attach photo
Project : Mobis Quality Center Project
15 12 14

Area Mobis Date 15 12 14 Area Mobis Date 15 12 14

Desc Near Dinning washbasin brick work Desc Near Dinning washbasin brick work

Area Mobis Date 15 12 14 Area Mobis Date 15 12 14

Desc Electrical Material for cunduiting Desc Emergency light Conduiting layout

Area Mobis Date 15 12 14 ### Area Mobis Date 15 12 14

Desc Emergency light Conduiting layout Desc VIP toilet Brickwork layout & Tile cutting
Project :
Area Mobis Date 15 12 14 Area Mobis Date 15 12 14

Desc Old floor Demolition Desc Material for Brick work