Professional Documents
Culture Documents
M5 1:5:10
M7.5 1:4:8
M10 1:3:6
M15 1:2:4
M20 1:1.5:3
M25 1:1:2
M30 1:0.75:1.5
M35 1:0.5:1
M40 1:0.25:0.5
https://everydaycalculation.com/concrete.php
Let’s calculate material required for M20 grade to prepare one cubic meter concrete.
Cement sand and aggregate ratio for M20 grade concrete is 1:1.5:3
Cement = 1 Part
Sand = 1.5 Part
Aggregate = 3 Part
Total Parts = 1 + 1.5 + 3 = 5.5
Total Material Required per cubic meter of concrete= 1.55
= 0.282 cu.m
= 1 x 0.282
= 0.282 cu.m
= 1.5 x 0.282
= 0.423 cu.m
= 3 x 0.282
= 0.846 cu.m
Consider for 1CUM of concrete is to be prepare ,For that M15 is a nominal mix, its
proportion is 1:2:4
for 1cum of final mix(Dence) is required, 1.50 to 1.55 Cum of loose ingredients
with the required proportion we want to add.
For Cement Qty = 1.52/7=0.217 Cum of cement required to prepare 1Cum of M15
concrete.But cement is always taken in Weight.For that the unit weight of cement
is 1440 KG/Cum
The following are the materials required to produce 1 Cum of Concrete of a given Nominal Mix
Proportion
Aggregate (in
Grade of Concrete Nominal Proportion Cement (bag)/cum Sand (in cft) cft)
Incase you want to convert the requirement of Sand and Aggregate in Cum; 1 Cum = 35.31 Cft
Volume of 01 bag (50 kg) of cement = 50 X 0.000694 = 0.035 cubic meter (cum)
Since we know the ratio of cement to sand (1:2) and cement to aggregate (1:4)
To convert Sand volume into weight we assume, we need the dry loose bulk density (DLBD). This
density for practical purposes has to be determined at site for arriving at the exact quantities. We can
also assume the following dry loose bulk densities for calculation.
DLBD of Sand = 1600 kgs/cum
So, One bag of cement (50 Kgs) has to be mixed with 115 kgs of Sand, 209 Kgs of aggregate
and 27.5 kgs of water to produce M20 grade concrete.
From the above calculation, we have already got the weights of individual ingredients in concrete.
So, the weight of concrete produced with 1 Bag of cement (50 Kgs) =50 kg + 115 kg + 209 kg + 27.5
kg = 401.5 kg ~ 400 kgs
One bag of cement and other ingredients can produce = 400/2400 = 0.167 Cum of concrete (1:2:4)
Method-2:
Although empirical method is easy to use in determining the materials requirement for Nominal
Concrete mix, it sometimes doesn’t give accurate results as it doesn’t take into factor the local
variations in the materials.
The dry volume of concrete mixture is always greater than the wet volume. The ratio of dry volume to
the wet volume of concrete is 1.54.
So 1.54 Cum of dry materials (cement, sand and aggregate) is required to produce 1 Cum of concrete
Density of Sand = 1600 Kgs/cum to 1920 Kgs/Cum (sand density varies place to place)
Volume of Cement = 0.285 cu.m Or Cement = 8.22 bag Because one bag of Cement is equal to 50 kg.
Volume of Sand = 0.471 cu.m
Volume of Crush =0.856 cu.m
we know that Concrete proportion for M20 is (1:1.5:3)
8 bag of Cement is required for 1cum of concrete work in M20.
1:1:2 (1 part of cement : 1 part Sand: 2 part of CA) is for M25 Grade.
(where 1.54 is Dry to wet volume constant, & 1440 is density of cement)
Similarly
ie, 554*1 = 554Kg/m3 (usually sand measure in Cft so 554/10.76= 15.7 Cft)
https://www.calculator.net/concrete-calculator.html
https://www.diydoctor.org.uk/projects/mixing_concrete.htm
Weight of steel bar per meter = Area of the steel x Density of steel x Bar length
Density of steel 7850Kg/M3
Weight = A x L x ρ
Where,
A = Area = πD²/4
π (pai) = 3.14
D = Diameter of steel bar in millimeter
L = Length of steel bar in meter
ρ (Rho) = Density of steel bar = 7850 kg/m³
Therefore,
6mm 0.22kg
8mm 0.39kg
10mm 0.62kg
12mm 0.88kg
16mm 1.58kg
20mm 2.47kg
For MS Flat Bar
For 1-meter length of Mild Steel bar of size 40 mm width and 20 mm breadth
Weight = A x L x ρ
= D²L/533
Where,
D = Diameter of bar in mm (1 foot = 304.80 mm)
ρ (Rho) = 7850 kg/m³ = 222 kg/ft³ (actually it is 222.287 kg/ft³)
TMT Size TMT Weight per bundle TMT Rods per bundle