PILINGS
(Deep footings)
Piles
Cerucuk
Required when
strong soil is located > 3m under ground
deep excavation is difficult
weak soil
high water level
footings are not economical
Types of Piles
Driven
Pre-cast
1
Dr Shaiful Amri Mansur
FKA UTM Skudai
Types of Piles
Bored
Drilled Hammered
Water jet
Concrete
Load Transfer
End
Friction Bearing
Pile Pile
Soft
clay or
Hard Weak
clay sand
Stronger
soil or
rock
10
Driven Piles
11
2
Dr Shaiful Amri Mansur
FKA UTM Skudai
Cast in-situ
Quick and versatile
for most ground conditions
Normally pre-stressed
Use tube & shoe.
Drive tube to the required depth.
Place reinforcement.
Fill with high slump concrete.
Withdraw tube.
12
13
3
Dr Shaiful Amri Mansur
FKA UTM Skudai
Pre-cast Piles
Concrete (square, hexagon or round)
Solid& hollow (example: 230x230mm and
270x270mm square sections.)
20m long each (no limitation on total depth)
Steel protection at both top and bottom
ends
A bitumastic slip coating can be applied to
reduce skin friction.
15
Types of Hammer
Drop hammers
Cable, pulley, frame and driver
Diesel or electrical
Gravity (1000 to 5000 lb)
Slow (4 to 8 strokes/min)
16
17
4
Dr Shaiful Amri Mansur
FKA UTM Skudai
18
20
Precast Piles
5
Dr Shaiful Amri Mansur
FKA UTM Skudai
Sheet piles
24
6
Dr Shaiful Amri Mansur
FKA UTM Skudai
Enclosing/Surrounding Technique
25
26
27
7
Dr Shaiful Amri Mansur
FKA UTM Skudai
38
41
8
Dr Shaiful Amri Mansur
FKA UTM Skudai
Bored Piles
42
Check boring
Install Casing
Bore in Soil
Fill in concrete
Integrity testing
43
Check boring
To determine the casing length for the pile
To avoid wall from collapse
i.e. 4 checks boring per piers, more for larger
piers
Equipments
Drilling machine
Water pump
Working platform (4m x 4m)
44
9
Dr Shaiful Amri Mansur
FKA UTM Skudai
45
46
Install Casing
Drive casing until
50cm above limestone
Sit on the limestone
Into the limestone
Sit on hard strata
Use water jet (100-150 bar) & vibro
hammer
47
10
Dr Shaiful Amri Mansur
FKA UTM Skudai
48
Pilot Hole
Do soil boring first
Must not overlap with the result from
check boring
To determine the actual soil strata below
the check boring
One core per pile
49
50
11
Dr Shaiful Amri Mansur
FKA UTM Skudai
Cavity
For empty cavity use cement grout grade
30 mix and the pilot hole casing to fill in
grout
If filled with clay, use jet grouting to push
out the clay
54
55
Tests
Inclination, integrity and load tests
Inclination is done prior to reinforcement
Install
inclinometer casing into the pile casing
Lower sensor down to the toe
Read during upward movement (done twice)
Integrity
uses sonic transmitter to test
homogeneousity of concrete
56
12
Dr Shaiful Amri Mansur
FKA UTM Skudai
61
65
13