PEMBAIKAN CERUN-CERUN DI JALAN KOTA KINABALU-SANDAKAN (LALUAN PERSEKUTUAN 22) PAKEJ 2 DI KM83.90 DAN KM96.

70, SABAH
VALUATION NO. 12 (30th NOVEMBER 2018)
SLOPE AT KM83.90
Bill No. 2.10 - GUNITING
(All Quantities are provisional Quantities)
Work Done
CODE RATE AMOUNT
ITEM DESCRIPTION UNIT QTY Previous Current Accumulated
NO
(RM) (RM) Qty. Amount (RM) Qty. Amount (RM) Qty. Amount (RM)

F100 EXCAVATION

Cut and Dispose, Excavation between Boredpiles Vertical face

Excavation in cut shall be deemed to include trimming and preparation of


excavated surface and transportation from source to place of fill or disposal.

G400 SURFACE PROTECTION


2.10.1 G410.1 (100mm) thick (G25) guniting to cut slope. Rate shall be deemed to include m2 120 - - 0 -
steel fabric mesh, PVC drain pipe, dowel bar, and filter material as shown in
Drawing No. (SARG/JKR/SLP/R83.9/05).

I500 REINFORCEMENT
Rate for reinforcement shall be deemed to include labour for cutting, bending,
and placing.

High Tensile Bars

2.10.2 I524 Nominal diameter: 16mm t 25 - - 0 -

Total Carried to Grand Summary : - - - -

Prepared by : ………………………………….. Verified by : …………………………………….


Name : WILLY CHIN Name : DENIS BIN CHRISTIANUS
Designation : PROJECT MANAGER Designation : RESIDENT ENGINEER

(2.10) 1 of 1