BSCPL Infrastructure Limited

Name of Work: Resurfacing of Runway and Aircraft Operating Areas at AF Station Chandigarh
Material Details of Overall Project (Tentative)

Executed Stock Available


Total Quantity Balance Quantity
S.no Description of Material Unit Required As per BOQ Sep-18 (RAR-27) at Site
Quantity Up to Up to Remarks
Required
Sep

1 6 mm MT 35636 21587 165 13884


2 10 mm MT 256480 127337 23774 105369
3 20 mm MT 186837 99425 40302 47109
4 26.5 mm MT 25411 13997 4463 6952
5 31.5 mm MT 95289 23043 32690 39557
6 40 mm MT 41466 30431 3934 7101
7 Stone Dust MT 160441 126564 5449 28429
8 Coarse Sand MT 155317 45172 29156 80989
9 GSB MT 156782 119115 - 37668
Total Quantity = MT 1113661 606670 139933 367058

1 Cement MT 110067 34260 - 75807


2 Recron MT 231 56 - 175
3 Admixture MT 648 157 - 491
4 HDPE Sheet MT 262 54 - 208
5 Curing compound Lit 77555 33462 - 44092
Executed Stock Available
Total Quantity Balance Quantity
S.no Description of Material Unit Quantity Up to at Site Up to Remarks
Required As per BOQ Required
Sep-18 (RAR-27) Sep

6 Filler board Sqm 9649 739 - 8911


7 Sealant Lit 36735 1322 - 35413
8 Primar Kg - - - -
9 Backup rod 13 mm RM 374440 7570 366870
10 Backup rod 30 mm RM 25760 1970 23790
11 VG-30 MT 7651 4446 - 3205
12 VG-10 MT 614 445 - 169
13 PMB-40 MT 8592 8592 - -

Executed
Quantity as per site Balance Quantity
S.no Description of Item Unit Quantity Up to Stock Remarks
Condition Required
Sep-18 (RAR-27)
PMB-40 Tack
1 SAMI Layer MT 249 202 - 47 coat
2 Glass Grid Sqm 170645 137401 - 33244
3 Reinforcement (TMT) MT 120 0.400 - 119.6
4 Reinforcement (Fe-290) MT 100 - - 100 For FOD Traps

Note : Total Quantity may change after deviation of Quantities as per site conditions and it may impact on Balance
required Quantity of all items.