You are on page 1of 1

Feature

No.
(Function)

Works with file format in stand-alone mode


1 Database or with SQL database in EPM mode.
Works on multiple types of Database.

Multiple User Allow multiple users to work on an online Allow multiple users to work on a single project
2
Access database (using Microsoft Project Server). at the same time.

Activity Helps users to steps break down a complex


4 Not available. activity into smaller parts, while maintaining the
Steps simplicity of a Gantt Chart.

Allows you to have complete overview of the


Allows planned, remaining and actual project
5 Expenses project budget and costs during project
expenses to be entered at the activity level.
execution.

Custom Formulas for custom fields are possible and


6 Formulas cannot be set to custom fields.
Fields add additional values to it.

It comes installed with over 200 columns each


In Microsoft project there are around 500
7 Columns default fields for tasks and resources.
giving you different information. Column
categories include EVM, Budgeting, costs, etc.

Multiple
Only one relationship can be made between
9 activity activities.
Same activities can have multiple relationships.
relationships

WBS levels and activities are all the same, WBS is created separately from the activities
10 WBS you can even link an activity to a WBS level. with its own codes for each level.

User can be create sheet-like reports with


Creation of graphical reports can be default forms that can be customized. The look
11 Reports customized to any form you want to. of the reports is only in tabular form without to
have graphical charts and dashboards.

Assigning Allows the user assign logic directly to the Either create relationships in the Gantt view
12 Gantt chart or in predecessors/successors with a click and drag feature or with
Relationships columns. Predecessor/Successors tabs.

Tracking and Multiple projects creation, Multiple project


13 Multiple projects can be created and viewed. tracking, multiple project or WBS comparisons,
Comparing cost and unit calculations are possible.

Multiple baselines can be created on project


Baselines Multiple projects creation, Multiple project
or task level and viewed in specially created
13 tracking, multiple project or WBS comparisons,
Assignments view called Multiple Baseline Gantt. Costs cost and unit calculations are possible.
and unit calculations are possible.

Import/Export Communicate project data with other Communicate project data with other
14 applications. Supports different file formats applications. Supports different file formats for
Function for importing and exporting. importing and exporting.

You might also like