Work Programme Work Programme

For Station & Buildings of


Package-WD1:Bangabandhu Sheikh Mujib Railway Bridge Construction Project
Eastern Part
ID Task Name Duration Start Finish 2019 2020
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 Construction of Bangabandhu Sheikh Mujib Railway Bridge 435 days Mon 01-07-19 Mon 07-09-20
Construction Project (Package-WD1 Eastern Part), Station
Buildings
2 Project Start Date ( Expected Start Date) 0 days Mon 01-07-19 Mon 01-07-19 01-07
3 Station and Buildings 435 days Mon 01-07-19 Mon 07-09-20

4 Building (1) 195 days Mon 01-07-19 Sat 11-01-20

5 Foundation Work Up to Plinth 45 days Mon 01-07-19 Wed 14-08-19

6 Framed Structure 45 days Thu 15-08-19 Sat 28-09-19

7 Construction of Brick & Plaster Work 30 days Sun 29-09-19 Mon 28-10-19

8 Fixing of Doors & Window 15 days Tue 29-10-19 Tue 12-11-19

9 Fixing of Electrical & Plumbing Works 15 days Wed 13-11-19 Wed 27-11-19

10 Tiles Work 10 days Thu 28-11-19 Sat 07-12-19

11 Painting 15 days Sun 08-12-19 Sun 22-12-19

12 Miscellaneous Works 150 days Thu 15-08-19 Sat 11-01-20

13 Building (2) 210 days Mon 01-07-19 Sun 26-01-20

14 Foundation Work Up to Plinth 45 days Mon 01-07-19 Wed 14-08-19

15 Framed Structure 45 days Thu 15-08-19 Sat 28-09-19

16 Construction of Brick & Plaster Work 30 days Sun 29-09-19 Mon 28-10-19

17 Fixing of Doors & Window 15 days Tue 29-10-19 Tue 12-11-19

18 Fixing of Electrical & Plumbing Works 15 days Wed 13-11-19 Wed 27-11-19

19 Tiles Work 30 days Thu 28-11-19 Fri 27-12-19

20 Painting 15 days Sat 28-12-19 Sat 11-01-20

21 Miscellaneous Works 150 days Thu 15-08-19 Sat 11-01-20

22 Platform 90 days Tue 29-10-19 Sun 26-01-20

23 Platform Foundation Work 30 days Tue 29-10-19 Wed 27-11-19

24 RCC Work 30 days Thu 28-11-19 Fri 27-12-19

25 Brick Work 15 days Sat 28-12-19 Sat 11-01-20

26 Tiles Work 15 days Sun 12-01-20 Sun 26-01-20

27 Foot Over Bridge (East Station) 285 days Thu 28-11-19 Mon 07-09-20

28 Foundation Work 30 days Thu 28-11-19 Fri 27-12-19

29 Frame Structure 45 days Sat 28-12-19 Mon 10-02-20

30 Structural Steel Work 90 days Tue 11-02-20 Sun 10-05-20

31 Decking Work 30 days Mon 11-05-20 Tue 09-06-20

32 0.5 mm thick Zinc Aluminum Roof Sheeting Work 90 days Wed 10-06-20 Mon 07-09-20

33 Bridge Security Building 160 days Mon 01-07-19 Sat 07-12-19

34 Foundation Work Up to Plinth 30 days Mon 01-07-19 Tue 30-07-19

35 Framed Structure 45 days Wed 31-07-19 Fri 13-09-19

36 Construction of Brick & Plaster Work 30 days Sat 14-09-19 Sun 13-10-19

37 Fixing of Doors & Window 15 days Mon 14-10-19 Mon 28-10-19

38 Fixing of Electrical & Plumbing Works 15 days Tue 29-10-19 Tue 12-11-19

39 Tiles Work 10 days Wed 13-11-19 Fri 22-11-19

40 Painting 15 days Sat 23-11-19 Sat 07-12-19

41 Miscellaneous Works 130 days Wed 31-07-19 Sat 07-12-19

42 Substation 135 days Mon 01-07-19 Tue 12-11-19

43 Foundation Work Up to Plinth 30 days Mon 01-07-19 Tue 30-07-19

44 Framed Structure 30 days Wed 31-07-19 Thu 29-08-19

45 Construction of Brick & Plaster Work 30 days Fri 30-08-19 Sat 28-09-19

46 Fixing of Doors & Window 15 days Sun 29-09-19 Sun 13-10-19

47 Fixing of Electrical & Plumbing Works 15 days Mon 14-10-19 Mon 28-10-19

48 Painting 15 days Tue 29-10-19 Tue 12-11-19

49 Miscellaneous Works 105 days Wed 31-07-19 Tue 12-11-19

50 Gate Lodge 135 days Mon 01-07-19 Tue 12-11-19

51 Foundation Work Up to Plinth 30 days Mon 01-07-19 Tue 30-07-19

52 Framed Structure 30 days Wed 31-07-19 Thu 29-08-19

53 Construction of Brick & Plaster Work 30 days Fri 30-08-19 Sat 28-09-19

54 Fixing of Doors & Window 15 days Sun 29-09-19 Sun 13-10-19

55 Fixing of Electrical & Plumbing Works 15 days Mon 14-10-19 Mon 28-10-19

56 Painting 15 days Tue 29-10-19 Tue 12-11-19

57 Miscellaneous Works 105 days Wed 31-07-19 Tue 12-11-19

58 Landscape 300 days Mon 01-07-19 Sat 25-04-20

59 Site Development Works 300 days Mon 01-07-19 Sat 25-04-20

Toma Construction Task Split Milestone Summary Project Summary


& Co. Ltd (TCCL)

Note: Assumed date of commencement is 1st July'2019 & the detailed programme will be submitted in compliance with relevent contract clauses in due course. 1 of 2
Work Programme Work Programme

For Station & Buildings of


Package-WD1:Bangabandhu Sheikh Mujib Railway Bridge Construction Project
Eastern Part
ID Task Name Duration Start Finish 2019 2020
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
60 Preparation of Flower Beds & Lawn Grass 60 days Thu 28-11-19 Sun 26-01-20

61 Exposed Brick Works etc 90 days Mon 27-01-20 Sat 25-04-20

Toma Construction Task Split Milestone Summary Project Summary


& Co. Ltd (TCCL)

Note: Assumed date of commencement is 1st July'2019 & the detailed programme will be submitted in compliance with relevent contract clauses in due course. 2 of 2