SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
Waterproofing of Roof Slabs SATIP-M-100-02 30-Apr-13 CIVIL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

1.1 Not Applicable

RECEIVING
2.0
INSPECTION

Waterproofing Roofs Receiving and SAIC-M- S. ARAMCO - Witness first two deliveries and one in 5
2.1
Storage Inspection
SAIC-M-1012
1012 W W occurrencies thereafter.

3.0 INSTALLATION

Waterproofing Surface Preparation &


Waterproofing Layer Installation
SAIC-M-
3.1 Inspection (EPDM or Modified Bitumen SAIC-M-1014
1014 H W
membrane systems or TPO or PVC
membrane and Insulation)

SATR-M-
3.2 Leak-Proof Testing/Final Inspection SAIC-M-1018
1014 H H

4.0 PRE-COMMISSIONING

4.1 Not Applicable

Page 1 of 2
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Waterproofing of Roof Slabs SATIP-M-100-02 30-Apr-13 CIVIL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1 adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection/Test

Page 2 of 2