Professional Documents
Culture Documents
Manuscript ID JASE-2019-0012
Complete List of Authors: rahman, tamrin; Universitas Mulawarman, Faculity of Civil Engineer
Fo
Keywords: Plastocrete RT6 Plus, , Add Material, Compressive Strength
rR
ev
iew
On
ly
https://mc04.manuscriptcentral.com/jase
Page 1 of 12 Journal of Applied Science and Engineering
concrete arrived at the location, it will make the concrete pass the setting time. This has the
22
potential to reduce the quality of concrete, so that the use of added materials is needed to
23
24 maintain the condition of the concrete according to the plan. This study uses added material
rR
25 Plastocrete RT6 Plus from SIKA on 30 Mpa concrete qualities with a delay time of 120
26 minutes. This study was conducted by testing each concrete constituent up to the concrete mix
27 design in accordance with the SK.sni method.T-15-1990-03, in this test 5 (five) variations were
28
ev
used to add the Plastocrete RT6 Plus with concrete of placement delays up to 120 minutes were
29 0%, 0.4%, 0.5% 0.6%, 0.8%, and a normal concrete without the addition of the Plastocrete
30
31
RT6 Plus with the direct concrete of placement. Based on the results of this study, it was found
iew
32 that if the concrete had passed the sitting time without additional retaider, its strength
33 decreased to a value of 24.03 MPa, whereas if the addition was not provortional at 4% and
34 0.8%, then the value would be 28.51 Mpa and 27 , 21 Mpa, while the ideal addition was at
35 0.5% and 0.6%, where in this condition the strength of the concrete can exceed the strength of
36 the plan, reaching 32.15 Mpa and 33.12 Mpa respectively. This shows the material if there is a
On
37
delayed the placement of concrete due to shipping constraints, then the addition of the
38
39 Plastoctrete RT6 Plus could be recommended as one of the solutions with the addition of 0.5%
40 to 0.6%.
ly
41
42
43 Keywords: Plastocrete RT6 Plus, Add Material, Compressive Strength
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
https://mc04.manuscriptcentral.com/jase
Journal of Applied Science and Engineering Page 2 of 12
guaranteed that whatever obstacles occur during the delivery of concrete, the quality of the
27
concrete must be maintained. However, special handling is needed to ensure the quality of
28
29 concrete as planned in the event late of the placement of concrete. Some researchers have
iew
30 conducted research on this subject, according to BH Ahmadi (2000) in [1] argues that the setting
31 of concrete time in hot areas will faster than the area that is not hot, this will affect the results of
32 concrete of placement, including excessive dehydration that occurs in concrete; Saeed Farzin at
33 all, (2017) in [2] uses Silica and Zeolite for repair of mortar, because it is believed that these two
34 substances can delay cement bond aggregately; RRC Piyasena, at.all [2013] analyzes the setting
On
35
36
time of concrete for various conditions.
37 One of the ingredients that can delay the setting time of concrete is the Plastocrete RT6 plus, by
38 using laboratory media, the effect of adding the Plastocrete RT6 plus on normal concrete will be
ly
39 tested before the setting time takes about 40 minutes and the addition is done again at 80 minutes
40 with each addition of 50% of the volume addition plan, and then the concrete of placement is
41 conducted in the 120th minute.
42
43
44
45 2. The Theoretical Concept
46
47 Concrete is a mixture of a combination of cement, fine aggregate, coarse aggregate and water,
48 and additional materials that will form a solid mass as stated in SNI-03-2847-2002 in [3] [4], the
49 nature and characteristics of concrete depend on the forming material, the way it works and the
50
surrounding conditions when the concrete is worked on. Another thing that can affect is the
51
52 length of stirring, the amount of stirred material, the type and aggregate granules, and the
53 workability of the mixture (Catalin Badea, at.all) [6]. Where the time of stirs concrete must be
54 adjusted to its volume, according to (LJ.Murdock, 1979) in [7] the volume of concrete ≤ 2 m3
55 then it is done 1½ minutes, for 2½ m3 it is done 2 minutes, for 3 m3 stir it 2½ minutes, and 5 m3
56
57
58
59
60 https://mc04.manuscriptcentral.com/jase
Page 3 of 12 Journal of Applied Science and Engineering
30 f. Concrete is difficult to water resistant, perfectly, so water can always be entered and water
31 carrying salt can damage concrete.
32 g. Concrete can expand and shrink if there is a change in temperature, so it needs to be dilated
33 to prevent cracking due to changes in temperature.
34
On
35
36
To support the concrete has quality, there are several physical requirements that must be met, as
37 the following:
38
ly
27
28
Table, Material Testing
29 Agregate Testing Standard
iew
30
31
Filter Analysis SNI-03-1968
32
33 Specific gravity SNI-03-1969
34 SNI-03-1970
On
39
40
Organic content PBI 1971
41
42
43 To simulate the addition of the Plastoctrete RT6 Plus, a concrete of placement of simulation was
44 performed with a 120 minute delay scheme, such as the image flow below.
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60 https://mc04.manuscriptcentral.com/jase
Page 5 of 12 Journal of Applied Science and Engineering
27
increments were gradually done, each of it was accomplished in the 40th minute with an
28 additional 50% of the plan, and the next 50% addition was accomplished at the 80th minute and
29 the concrete of placement was conducted in the 120th minute.
iew
30
31 3.1. Result and Analysis of Fine Aggregate Sieves Testing
32
33 The fine aggregate used is natural sand from Palu (Central of Sulawesi Province), which is
34 included in zone II and British Standard, where the gradation tended to be rough as seen in the
On
35 following graph.
36
37
38
ly
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56 Fic 2. Graph of Results Fine Aggregate Sieves Testing
57
58
59
60 https://mc04.manuscriptcentral.com/jase
Journal of Applied Science and Engineering Page 6 of 12
27
28 .Fic 3. Graph of Results Rough Aggregate Testing
29
iew
30 The aggregate composition examined is feasible, where it included in the British Standard, where
31
from the results of the test, it was found that the mean of MHB average aggregate value was 6.5.
32
33 This value met the standard, where generally coarse aggregates have MHB approximately 5.0 -
34 8.0.
On
35
36 3.3. Mixed Planning Concrete
37
38 The steps for calculating the concrete mix design by using the SK’s method. SNIT-15-1990-03
ly
39 in [31] namely selected concrete compressive strength, which was implied at the age of 28 days
40 (f'c) = 30 Mpa, Standard deviation (S) = (not specified), Added value (m) = 12 Mpa, Average
41 compressive strength target concrete level (f'cr) 42 Mpa, the type of cement is Tonasa Cement
42 (type I), the type of coarse aggregate is gravel/broken stone from Palu, fine aggregate used
43
natural sand from Palu and Cement Water factor (FAS) = 0.48.
44
45
46 And the results of the design are presented below:
47
48
49
50
51
52
53
54
55
56
57
58
59
60 https://mc04.manuscriptcentral.com/jase
Page 7 of 12 Journal of Applied Science and Engineering
27 composition of 0.4%, 0.5%, and 0.6 %, 0.8% were multiplied by the weight of cement and 0% of
28
the normal concrete, and the normal concrete, whose the concrete of placement was late.
29
iew
30
31 3.4 Research Implementation
32
33
34
On
35
36
37
38
ly
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53 Fic 5. Research Implementation
54 The implementation procedures for testing might be conducted with rarities as follows:
55
56
57
58
59
60 https://mc04.manuscriptcentral.com/jase
Journal of Applied Science and Engineering Page 8 of 12
SD = Deviation Standard
30
N = Number of specimens
31
32 Fcm = Average compressive strength at the length of 28 days (Kg / cm)
33
34 4. The results of discussion
On
35 The comparison results of the concrete quality testing with the various compositions might be
36 seen in the following table.
37
38
ly
39
Table 2. Laboratory Observation Results
40 Plastocrete Time
Slump Age Compressive
41 RT6 Plus Mold Observati Dial
42
Observatio (Day Strength 28
Variation Code on KN Kg
43 n (cm) ) Day (Mpa)
(%) (minute)
44 BTND 0 10 28 530 54026.50 30.01
45
46
BTNE 0 10 28 530 54026.50 30.01
0
47 BTNF 0 10 28 540 55045.87 30.57
48 30.20
49 BTNA 120 2 28 490 49949.03 27.74
50
BTNB 120 2 28 570 58103.98 32.27
51 0
52 BTNC 120 2 28 330 33639.14 18.68
53 26.23
54
55 BTA1 120 7 28 530 54026.50 30.01
0.4
56 BTA2 120 7 28 510 51987.77 28.87
57
58
59
60 https://mc04.manuscriptcentral.com/jase
Page 9 of 12 Journal of Applied Science and Engineering
27
Coral were 0.45: 1: 1.37: 2.43 and the addition of the Plastoctrete RT6 Plus with a composition
28 of 0.4%, 0.5%, and 0.6 %, 0.8% were multiplied by the weight of the cement and 0% for the
29 normal concrete, and normal concrete whose the concrete of placement was late.
iew
30
31
32
33
34
On
35
36
37
38
ly
39
40
41
42
43
44
45
46
47
48
49
50
51 Fic 6. Chart of results of testing compressive strength several variations of Plastocrete Plus
52
53
54 From the results of the 28-day test, it was found that placement of concrete without adding
55
retaiders after the 40th minute of the concrete setting time was lower than the concrete quality of
56
57
58
59
60 https://mc04.manuscriptcentral.com/jase
Journal of Applied Science and Engineering Page 10 of 12
27
28
29
iew
30
31
32
33
34
On
35
36
37
38
ly
39
40 Fic7. Chart of time variation of added plastocrete RT6 Plus
41
42
43 From the above chart, it might be seen that the adding time of the Plastocrete RT6 Plus should be
44 done gradually in the 40th minute and 80th minute, when the concrete got the setting time, where
45 the value of concrete compressive strength was higher compared to the addition of the
46
47
Plastocrete RT6 Plus 100% at the beginning of concrete making.
48
49 5. Conclusion
50 1. From the test results, if there is no addition of the Plastocrete RT6 Plus, the concrete of
51 placement’s delay due to constraints has an adverse effect on the normal concrete, where the
52 concrete quality might be reduced continuously, and the delay until 120 minutes without
53
additives reduces the concrete compressive strength only reaching 24.03 Mpa, while in the
54
55
same conditions, the addition of the Plastocrete RT6 Plus 0.5% to 0.6% might maintain the
56 planned concrete mutation of 32.14 Mpa and 33.12 Mpa. While the additions that were not
57
58
59
60 https://mc04.manuscriptcentral.com/jase
Page 11 of 12 Journal of Applied Science and Engineering
27
[5] Rachmad Purwono,Tavio, Iswandi Imran,I Gusti Putu Raka “ Procedure for calculating
28
29 structure for buildings, Surabaya Institute of Technology (SIT) Press, Surabaya, 2019
iew
30 [6] Lect. PhD. Eng. Catalin BADEA, Assist. Prof. PhD. Eng. Liana IURES “Concrete”
31 Politehnica, University of Timisoara, 2017
32 [7] L.J. Murdock dan K.M. Brook. Concrete materials and practice. Erlangga, Jakarta, 1979
33 [8] M. Nili and V. Afroughsabet, “Combined effect of silica fume and steel fibers on the impact
34 resistance and mechanical properties of concrete,” Int. J. Impact Eng, vol. 37, no. 8, p. 879–
On
35
36
886, 2010.
37 [9] General Affairs Department and Electrical Power “ The regulation on Indonesia Recurring
38 Concrete” Directorate of Investigation of Building Problems,
ly
27
2013.
28
29 [26] A. Basheerudeen and S. Anandan, “Simplified mix design procedures for steel fibre
iew
30 reinforced self compacting concrete,” Engineering Journal, vol. 19, no. 1, p. 21–36, 2015.
31 [27] Standard Test Method for Compressive Strength of Hydraulic Cement Mortars (Using 2-in.
32 or [50-mm] Cube Specimens), ASTM C 109 – 07.
33 [28] Standard Test Method for Flexural Strength of Hydraulic-Cement Mortars, ASTM C 348 –
34 02.
On
35
36
[29] Standard Test Method for Splitting Tensile Strength of Cylindrical Concrete Specimens,
37 ASTM C 496 – 04.
38 [30] Wiratman Wangsadipura dkk. “ Indonesia concrete regulation, 1971” General Affairs
ly