1. Scope
The purpose of this Method Statement is to describe the measures and ways of
fan installation at transformer radiator. The works shall be carried out in
compliance with the drawings and project specification.
2. Work Procedure
a) Before installation
Check for quantity, model number, type, physical damage before moving
to the required area.
Check drawings used are latest and approved.
Read carefully the manufacturer instruction.
b) Shift the fan to the place of installation in a safe manner using hand
trolley or fork lift, as applicable.
i) Hardwire the fans to the new fuse terminal blocks installed in the
transformer control cabinet, as shown in the revised wiring diagrams.
Refer to drawings F16‐A8477, F24‐8606 and
F24‐A8052 for proper fan power wiring connections and phasing.
3. Safety
1. All works shall comply with safety procedure
2. Basic PPE to worn by all staff and labour.