Professional Documents
Culture Documents
ON PLOT No IJC 354 (OG). UTM(ZONE 31), OGUN STATE, NIGERIA, SOUTH AFRICA
FOR FLEX FILMS AFRICA PVT. LIMITED
GRAND SUMMARY
ITEM DESCRIPTION AMOUNT
NGN
GRAND SUMMARY
TOTAL -
Add VAT -
SUMMARY
BILL 1: PRELIMINARIES
BILL 2: EARTHWORK
BILL 4: REINFORCEMENT
BILL 7: FINISHES
TOTAL -
Page 2 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
1 CONTRACTOR'S PRELIMINARIES
2 INSURANCES
4 MOBILISATION
5 DEMOBILISATION
6 TENDER FEE
7 HANDING OVER
The founding strata shall be well compacted and shall be tested for
degree of compaction that shall not be less than 98% of MDD.
PRELIMINARIES
Adequate BILL 1 shall be provided wherever there is
retaining measures
Page 2 BILL 1 between finished levels and to suite the profile of
level difference
land. Temporary shoring or retaining structure can be included
BILL 2: depending
EARTHWORK upon the depths. Excess soil shall be carted away for
disposal to dumping ground. (as per Nigerian Laws)
Page 3 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
1 EXCAVATION
FROM EXISTING NATURAL GROUND LEVEL UPTO
m3 5,300 113,600 186,330
FOUNDATION LEVEL 36570 9280 4210 2100 3000 3500 1040 2200 1000 4530
2 BACKFILLING
All back filling shall be carried in layers of not more than 300mm
thickness with degree of compaction not be less than 98% of MDD
a BACKFILLING WITH EXCAVATED SOIL m3 23450 4410 1,140 280 730 400 890 380 310 1420 1,170 17,190 51,770
b BACKFILLING WITH IMPORTED SAND m3 1750 900 2,180 1,290 1610 1500 NIL 40 440 NIL 340 NIL 10,050
4 ANTI-TERMITE TREATMENT m2 20000 5520 1020 1350 1500 1400 180 540 750 1650 1,010 35,430 70,350
HARD ROCK EXCAVATION m3 1,000 300 150 60 80 90 55 60 120 140 150 5,700 7,905
Page 4 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
EARTHWORKS BILL 2
Page 3 BILL 2
e RETAINING BASE SLAB AND WALL m3 390 360 240 60 85 185 NIL 330 30 NIL 100 5 1,785
g RAMP SLAB m3 410 150 5 10 10 10 NIL NIL 1 NIL NIL NIL 596
h STAIRCASE, WAIST SLAB, TREAD&RISER m3 20 8 12 30 30 55 NIL NIL 15 NIL NIL NIL 170
l SLAB m3 150 7 235 295 400 430 30 NIL 210 150 140 NIL 2,047
n DECKING SLAB, BRC A-393 m3 NIL 330 NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL 330
q SOLID MASS CONCRETE m3 30 NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL 30
r SUPER-STRUCTURE RCC WALL m3 NIL NIL 260 190 160 195 NIL NIL NIL NIL NIL NIL 805
s BALCONY UPSTAND AND DROP m3 NIL NIL NIL NIL 15 15 NIL NIL NIL NIL NIL NIL 30
Page 6 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
t CORNICE PROJECTION Rm NIL NIL NIL NIL 600 540 NIL NIL NIL NIL NIL NIL 1,140
u SCREED
Grade of CONCRETE
concrete for substructure for water tank to be S-40/20 m3 NIL NIL 35 35 40 45 NIL NIL 35 NIL NIL NIL 190
with minimum S.R. cement content 380kg/m3 with minimum cube -
3 crushing strength
FINISH RCC of 40N/mm2 WITH
SLAB/FLOOR after 28days.
POWER Cement Grade 42.5
FLOAT/SAW CUT -
ETC WITH FLOOR JOINT FINISHED WITH APPROVED -
4 SEALANT m2 13,670 11,420 40 100 280 650 20 125 295 850 1,100 NIL 28,550
-
-
-
BILL-4 REINFORCEMENT
ALL REINFORCEMENT FOR SUB-STRUCTURE AND
SUPER-STRUCTURE SHALL BE HIGH YEILD STRENGTH
DEFORMED STEEL BARS HAVING YIELD STRESS OF
425KN/SQ.MM
1 REINFORCEMENT – HYSD BARS Kg 535930 ### ### ### ### ### 9,910 56,800 92,060 79,100 117,510 21,650 1,760,530
2 BRC MESH
NOTE: – A252, A142
OVERLAPS, CHAIRS AND SPACERS SHALL BE PAID Kg 108320 20,600 1,180 1,200 1300 1540 300 250 600 160 300 165,170 300,920
IN THE RESPECTIVE ITEM AS PER BBS/DRAWINGS AND -
WILL BE PAID OF RECONCILIATION STATEMENT -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Page 7 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
-
-
-
-
-
-
-
-
-
-
-
-
-
-
REINFORCEMENT BILL 4 -
Page 7 BILL 4
PEB/HOT ROLLED STEEL STRUCRURE FABRICATED,SAND -
BLASTED, PAINTED STEEL
BILL 5 STRUCTURAL AS PER
AND THE SPECIFICATIONS.
METAL WORKS NIL -
1 PAINTING SHOULD BE EPOXY AND OR ENAMEL PAINT. NIL -
PROVIDE ANCHOR BOLTS AS PER PEB SUPPLIER IN
a PEDESTAL ( HOT-DIP GALVANIZED) INCLUDING NIL -
TEMPLATE
-
ROOF PURLINS, CLADDING RUNNER, DIAGONAL ROD,
b CABLE BRACING, BOLTS, NUTS AND PAINTED AS PER NIL -
THE SPECIFICATIONS
-
c SHEETING NIL -
100mm THICK STEEL SANDWICH PANEL ROOF SHEETING,
c.1 NIL -
19200m2
-
75mm THICK STEEL SANDWICH PANEL WALL SHEETING,
c.2 NIL -
7395m2
-
0.7mm THICK GALVANIZED MILL FINISH STEEL PLATE,
d NIL NIL -
330m2
-
e EAVE GUTTER AND DOWNSPUTS NIL -
-
f CRANE RUNWAY BEAM AND BRACKETS NIL -
-
g GANTRY AND RAILS NIL NIL -
-
h STEEL STAIRCASE AS PER DRAWING NIL -
-
I CAGED STAIRCASE AS PER DRAWING NIL NIL -
-
Page 8 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
j STEEL STAIRCASE HANDRAIL AND PLATFORM SAFETY -
HANDRAIL
-
k 6mm THICK CHEQUERED PLATE, 62940Kg NIL NIL -
-
BLOCK 1- PEB AREA BELOW -
1 PEB HAVING PLAN AREA: -
AREA 1 – 29.03m x 272.23m = 7903m2 LS NIL NIL -
-
AREA 2 – 8.50m x 64.218m = 546m2 LS NIL NIL -
STRUCTURAL STEEL AND METAL WORKS BILL 5 -
Page 8 BILL 5
Page 9 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
FRAMED CUTOUTS IN ROOF SHEETS WITH GRP SOAKER
9 PANELS OF SIZE 1500MMX1500MM APPROXIMATELY Nos 70 70
FRAMED CUTOUTS IN WALL SHEETS OF SIZE
10 1500MMX1500MM APPROXIMATELY Nos 30 30
STRUCTURAL STEEL AND METAL WORKS BILL 5 -
Page 9 BILL 5
PVC CURTAIN WITH OVERLAPS, 150mm WIDE AND 1.5mm
11 THICK, 6.2m HEIGHT APPROXIMATELY Rm 60 60
BLOCK 2- PEB AREA BELOW -
1 UTILITY BLOCK AREA – 25.46m x 112.38m = 2861m2 LS NIL NIL -
-
2 FUEL TREATMENT PLANT – 10.46m x 10m = 105m2 LS NIL NIL -
HOT DIP GALVANIZED DUCTILE STEEL TRENCH GRATING -
3 ( INCLUDING ANGLE PLATES, FISH TAIL ANCHORS ETC) m2 545 60 NIL 605
-
4 CRANE RAIL, CR 80 64.2Kg/m Rm 55 55
FRAMED CUTOUTS IN WALL SHEETS OF SIZE -
5 1500MMX1500MM APPROXIMATELY Nos 20 20
4mm THICK FIRE RATED ALUMINIUM COMPOSITE PANEL
CLADDING WITH PVDF
BLOCK 3 – ADMIN COATING ON TOP AND POLYSTER
BUILDING -
1 COATING AT –THE
STAIRCASE MSBOTTOM
POWDERINCLUDING
COATED STEEL FRAMING.
HANDRAIL, WITH m2 NIL NIL 390 NIL 390
CHS 60.3mm DIA TUBULAR WITH MAIN VERTICAL -
2 STAIRCASE
MEMBERS
HANDRAILSAT – 900mm
SS 304 C/C
MIRROR FINISHED
AND OTHER HANDRAIL
VERTICAL OF
TUBES -
a 60.3mm
AT 150mmDIA
C/C TUBULAR WITH 10mm THICK TOUGHEN
. APPROX. 20Kg/m Rm NIL NIL 20 NIL 20
GLASS HANDRAIL
RAMP PANEL. ALL– VERTICAL
MS POWDER TUBE SHALL HANDRAIL,
COATED BE 60.3mm -
b DIA ATCHS
WITH 900mm C/C. APPROX.23Kg/m
60.3mm DIA TUBULAR WITH MAIN VERTICAL Rm NIL NIL 20 NIL 20
MEMBERS AT 900mm C/C AND OTHER VERTICAL TUBES -
c AT 150mm C/C . APPROX. 20Kg/m. Rm NIL NIL 25 NIL 25
-
BLOCK 4 , 5, 6, 9 -
1 STAIRCASE
HANDRAILS:HANDRAIL – POWDER COATED ALUMINIUM, -
APPROX 12Kg/m Rm NIL NIL NIL 50 55 65 NIL 15 185
STRUCTURAL STEEL AND METAL WORKS BILL 5 -
RAMP HANDRAIL – MS POWDER COATED HANDRAIL,
Page 10CHS
WITH BILL 5
60.3mm DIA TUBULAR WITH MAIN VERTICAL
BALCONY
MEMBERS AT HANDRAIL
900mm C/C– AND
SS OTHER
316 MIRROR FINISHED
VERTICAL TUBES -
HANDRAIL
AT 150mm C/C OF. APPROX.
60.3mm DIA TUBULAR WITH 12mm THICK Rm
20Kg/m. NIL NIL NIL 11 NIL NIL NIL 8 19
TOUGHEN GLASS PANEL. GLASS PANEL TO BE -
CONNECTED USING GLASS LAMINATES. Rm NIL NIL NIL NIL 180 110 NIL NIL 290
DECORATIVE GRILL SCREEN SHALL BE OF IRON STEEL -
2
2 MATERIAL WITH HOT DIP GALVANIZED AND POWDER m NIL NIL NIL NIL 210 160 NIL NIL 370
BLOCK 8A
COATED. AND B – ADMIN
THICKNESS SHALLBUILDING
BE BETWEEN 2mm TO 10mm -
PEB Steel Structure fabricated, Sand Blasted, Painted (As per -
1 specification & Drawings. Shop Drawings & Detailed quantified NIL NIL NIL NIL NIL NIL NIL -
BOQ to beFollowing:
Including submitted & approved before fabrication) -
Providing & Fixing of Anchore Bolts (As per PEB supplier in
a NIL NIL NIL NIL NIL NIL NIL -
column Pedestral) Hot-Dip Galvanized with templates etc., all
-
Roof Purlins, Cladding Runners, Diagonal Rod, Cable Bracing,
b NIL NIL NIL NIL NIL NIL NIL -
Bolts, Nuts (Painted as per specification)
Page 10 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
-
c Sheeting Includes: NIL NIL NIL NIL NIL NIL NIL -
c.1) Roof Sheeting-100mm thick Steel Sandwich Panel (Approx
NIL NIL NIL NIL NIL NIL NIL -
Qty: 120 Sqm)
c.2) Wall Cladding/ Sheeting-75mm thick Steel Sandwich Panel
NIL NIL NIL NIL NIL NIL NIL -
(Approx Qty: 140 Sqm)
-
d Eave Gutter & Downspout pipes NIL NIL NIL NIL NIL NIL NIL -
-
1 PEB having Plan Area: -
Area 1 – (W) 8m x (L) 8m = 64 x 2= 128 Sqm, EAVE HEIGHT =
NIL NIL NIL NIL NIL NIL NIL -
6m AT LOWER SIDE LS
-
600mm x 600mm HEAVY DUTY MAN HOLE COVER
2 Item NIL NIL NIL NIL NIL NIL NIL 10 10
(Including Angles, Plates, Fish Tail Anchors etc., all complete)
Page 11 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
-
STRUCTURAL STEEL AND METAL WORKS BILL 5 -
Page 13 BILL 5
-
Page 12 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
BILL 6 BLOCK WORK AND PARTITION -
SOLID BLOCK WORK SHALL BE PROVIDED ALL ALONG
-
TIE BEAM UP TO FOUNDATION LEVEL.
HOLLOW BLOCK WORK SHALL BE PROVIDED ABOVE TIE
-
BEAM UP TO COPING BEAM
-
1 Solid
230mm blockwork shall beBLOCKWALL
THICK SOLID provided all along below tie beam up to m 2 3,800 330 90 NIL NIL NIL 230 NIL 10 55 300 300 5,115
founding level. -
-
2 HOLLOW BLOCKWORK -
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR
a SUPER-STRUCTURE m2 3,000 1,000 690 1,250 1,320 1,550 440 160 710 60 520 600 11,300
-
b 230mm THICK INTERNAL BLOCKWALL m2 3,700 680 160 1,600 1240 1100 NIL 320 410 NIL NIL NIL 9,210
-
c 100mm THICK INTERNAL BLOCKWALL m2 300 NIL 80 330 1390 990 60 NIL NIL NIL NIL NIL 3,150
-
d 100mm THICK GYPSUM PARTITION m2 NIL NIL 870 NIL NIL NIL NIL NIL 45 NIL NIL NIL 915
-
150MM THICK EXTERNAL BLOCKWORK FOR ELEVATION
e NIL NIL NIL NIL NIL NIL 10 NIL NIL NIL NIL NIL 10
FEATURE m2
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
BLOCK WORK AND PARTITION BILL 6 -
Page 14 BILL 6
-
BILL 7 FINISHES -
1 PLASTER -
Page 13 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
a 6,370 2,000 390 2,500 2,640 3,100 550 320 1,420 1,100 20,510
15mm THICK EXTERNAL PLASTER (Cement : Mortar ratio 1:3) m2 120
-
b 8,450 1,400 320 3,860 5,260 4,180 NIL 910 24,740
12mm THICK INTERNAL PLASTER (Cement : Mortar ratio 1:4) m2 360
-
PAINTING -
EXTERNAL WALL – TEXURED PAINT WITH 2 COAT OF
a 6,440 2,150 320 2,680 2,970 6,600 320 1,500 1,340 25,180
POLYURETHANE m2 650 210
-
b INTERNAL WALL – 5 COAT OF EMULSION PAINT m2 3,840 930 2,220 4,510 5,260 8,360 510 NIL 1,340 NIL NIL 26,970
-
c INTERNAL WALL – ENAMEL PAINT m2 5,520 470 NIL NIL NIL NIL NIL NIL NIL NIL NIL 5,990
-
50-75mm THICK
WALL TILING ANDROCKWOOL
FINISHES INSULATION FOR ACP -
a CLADDING, DENSITY APPROX. 50-75Kg/m3 m2 NIL NIL 450 NIL NIL NIL NIL NIL NIL NIL NIL 450
-
b CERAMIC TILE m2 620 85 NIL NIL 1350 1070 NIL NIL 530 NIL NIL 3,655
-
c 2 NIL NIL 420 NIL NIL 90 NIL NIL NIL NIL 1,275
GLAZED CERAMIC TILE m 765
-
d 2 NIL NIL NIL 275 NIL NIL NIL NIL NIL 725
GRANITE TILE m 110 340
-
FLOORING -
a CERAMIC TILE m2 700 NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL 700
-
b ACID PROOF TILES m2 NIL 380 NIL NIL NIL NIL NIL NIL NIL NIL NIL 380
-
c ANTI-SLIP CERAMIC TILE m2 350 28 110 310 480 440 150 NIL 110 NIL NIL 1,978
-
d GRANITI TILE m2 130 NIL 720 1100 1000 1200 NIL NIL 540 NIL NIL 4,690
-
e NATURAL GRANITE m2 NIL NIL 40 NIL 20 12 NIL NIL NIL NIL NIL 72
-
f TERRAZO TILE m2 NIL NIL 540 720 940 610 180 NIL 355 NIL NIL 3,345
-
-
BLOCK WORK AND PARTITION BILL 7 -
Page 15 BILL 7
-
g FLOOR HARDNER m2 1,650 2,400 NIL NIL NIL NIL NIL NIL NIL NIL NIL 4,050
-
h 400 MICRON EPOXY FINISH m2 4,750 NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL 4,750
-
Page 14 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
FALSE CEILING -
VINYL FACED & ALUMINIUM BACK 600mm x 600mm
a m2 220 630 760 670 NIL 270 NIL NIL 4,585
GYPSUM TILE ON EXPOSED GRID 1300 720 15
-
600mm x 600mm CONCEALED GRID METALLIC FALSE
b CEILING m 2 NIL NIL 15 NIL 165 140 NIL NIL NIL NIL NIL 320
-
SKIRTING -
a 100mm HEIGHT CERAMIC TILE Rm 290 80 NIL NIL 295 215 90 NIL 510 NIL NIL 1,480
-
b 100mm HEIGHT NATURAL GRANITE Rm NIL NIL 20 NIL NIL NIL NIL NIL NIL NIL NIL 20
-
c 100mm HEIGHT GRANITI TILE Rm NIL NIL 530 570 1140 650 NIL NIL NIL NIL NIL 2,890
-
d 100mm HEIGHT TERRAZZO TILE Rm NIL NIL NIL 125 145 100 NIL NIL 95 NIL NIL 465
-
e 75mm HEIGHT GRANITI TILE Rm 35 NIL 20 NIL 40 40 NIL NIL 75 NIL NIL 210
-
THRESHOLD -
a 100mm WIDE GRANITE TILE Rm 150 10 25 40 40 50 8 NIL 20 NIL NIL 343
-
GRANITE TSP ON FLOOR CABINET -
a 600mm WIDE GRANITE m2 NIL NIL 15 15 25 25 NIL NIL 45 NIL NIL 125
-
b 750mm WIDE GRANITE m2 15 NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL 15
-
c 950mm WIDE GRANITE m2 15 NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL 15
-
d 1200mm WIDE GRANITE m2 10 NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL 10
-
6mm THICK TOUGHENED GLASS m2 40 NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL 40
-
-
-
-
-
-
-
BLOCK WORK AND PARTITION BILL 7 -
Page 16 BILL 7
-
BILL 8 DOORS AND WINDOWS -
BLOCK – 1 -
RUD'S -
1 1RUD -1 (4m x 4m), ROLL UP DOOR Nos 8 8
-
2 1RUD -2 (3m x 3m), ROLL UP DOOR Nos 6 6
-
3 1SD (2.6m x 3.5m), SPEED DOOR Nos 6 6
-
Page 15 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
ALUMINIUM DOORS AND WINDOWS -
1 1D1 (2m x 2.4m), PARTLY GLAZED ALUMINIUM DOOR Nos 15 15
-
2 1D1' (1.5m x 2.4m), PARTLY GLAZED ALUMINIUM DOOR Nos 5 5
-
3 1D2 (1m x 2.1m), PARTLY GLAZED ALUMINIUM DOOR Nos 25 25
-
4 1D3 (2m x 2.1m), PARTLY GLAZED ALUMINIUM DOOR Nos 14 14
-
5 1D6 (2m x 2.6m), PARTLY GLAZED ALUMINIUM DOOR Nos 5 5
-
6 1D7 (2m x 3.2m), PARTLY GLAZED ALUMINIUM DOOR Nos 5 5
-
2D2 ( 1m
STEEL x 2.1m), POLYSTER POWDER COATED STEEL
DOORS -
1 DOORS Nos NIL 16 16
-
2FED ( 1m x 2.1m), POLYSTER POWDER COATED
2 Nos NIL 4
SECTIONAL STEEL DOOR 4
-
WOODEN DOORS -
1 2D3 ( 1m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL 3 3
-
2 2D4 ( 0.9 x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL 1 1
-
3 2D5 ( 0.8 m x 2.1m), SEMI SOLID WOODEN FLUSH DOOR Nos NIL 4 4
-
RUD'S -
1 2RUD 1 ( 5m x 6m), ROLL-UP SANDWICH DOOR Nos NIL 2 2
-
2 2RUD 2 ( 3m x 4m), ROLL-UP SANDWICH DOOR Nos NIL 6 6
-
BLOCK – 3 -
DOORS AND WINDOWS, CARPENTARY WORKS -
Page 17 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
-
ALUMINIUM WINDOWS -
3D1 ( 1.8m x 2.1m), HEAVY DUTY FULLY GLAZED DOUBLE
1 Nos NIL NIL 2
SWING DOOR 2
-
3SD1 ( 2.1m x 3m), HEAVY DUTY FULLY GLAZED WITH SS
2 Nos NIL NIL 1
MIRROR FINISH FRAME 1
-
3W1 (2.4m x 5m), POLYSTER POWDER COATED
3 ALUMINIUM GLASS WINDOW Nos NIL NIL 8 8
3W2 (2.4m x 4m), POLYSTER POWDER COATED -
4 ALUMINIUM GLASS WINDOW Nos NIL NIL 6 6
3W3 (2m x 2.4m), POLYSTER POWDER COATED -
5 ALUMINIUM GLASS WINDOW Nos NIL NIL 3 3
-
3W4 (0.75m x 0.9m), POLYSTER POWDER COATED
6 ALUMINIUM GLASS WINDOW WITH TOP HUNG Nos NIL NIL 2 2
-
3W5 (6m x 8.1m), 4 WAY STRUCTURAL GLAZING WITH
7 NIL NIL 270
DOUBLE GLAZED PANELS m2 270
DOORS AND WINDOWS BILL 8 -
Page 19 BILL 8
-
WOODEN DOORS -
1 3D3 ( 0.9m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL 2 2
-
2 3D4 ( 0.8m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL 6 6
-
3 3D5 ( 1m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL 1 1
-
4 3D7 ( 1m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL 6 6
5 3D8 ( 0.9m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL 3 3
-
6 3D9 ( 1m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL 2 2
-
7 3D10 ( 1m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL 2 2
-
GLASS DOORS -
1 3D2 ( 1m x 2.1m), 10mm THICK TOUGHENED GLASS DOOR Nos NIL NIL 26 26
-
2 3D6 ( 1.2m x 2.1m), 10mm THICK TOUGHENED GLASS DOOR Nos NIL NIL 1 1
-
3 3W6 (1.1m x 1.2m), FIXED GLASS WINDOW Nos NIL NIL 30 30
-
CARPENTRY WORKS: -
600mm
WOODENWIDE WOODEN FLOOR CABINET INCLUDING
CABINETS -
SINK/WASH TROUGH m2 NIL NIL 20 20
Page 18 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
-
450mm WIDE OVERHEAD WOODEN CABINET m2 NIL NIL 20 20
-
600mm WIDE CABINET
ALUMINIUM ALUMINUM FLOOR CABINET INCLUDING -
SINK/WASH TROUGH m2 NIL NIL 5 5
-
450mm WIDE OVERHEAD ALUMINIUM CABINET m2 NIL NIL 5 5
-
BLOCK – 4 -
DOORS AND WINDOWS, CARPENTRY WORKS -
4D1 (2m x WORKS
ALUMINIUM 2.1m), POLYSTER POWDER COATED -
1 ALUMINIUM DOUBLE SWING DOOR Nos NIL NIL NIL 5 5
-
WOODEN DOORS -
1 4D2 ( 1m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL NIL 38 38
-
2 4D3 ( 0.9 x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL NIL 2 2
-
3 4D4 ( 0.8 m x 2.1m), SEMI SOLID WOODEN FLUSH DOOR Nos NIL NIL NIL 38 38
-
4 4D5 ( 2 m x 2.1m), SEMI SOLID WOODEN FLUSH DOOR Nos NIL NIL NIL 1 1
-
5 4D6 ( 1 m x 2.1m), SEMI SOLID WOODEN FLUSH DOOR Nos NIL NIL NIL 1 1
BLOCK – 6 -
DOORS AND WINDOWS, CARPENTRY WORKS -
ALUMINIUM DOORS AND WINDOWS -
1 6SD1 (2.1m x 2.4m), POLYSTER POWDER COATED Nos NIL NIL NIL NIL NIL 16
ALUMINIUM SLIDING DOOR 16
-
6D6 (1m x 2.1m), MEDIUM DUTY POLYSTER POWDER
2 Nos NIL NIL NIL NIL NIL 2
COATED ALUMINIUM SECTION DOOR 2
6DD (0.6m x 2.1m), POWDER COATED ALUMINIUM -
3 SHUTTER Nos NIL NIL NIL NIL NIL 2 2
6W1 (1.8m x 2.4m), POLYSTER PODWER COATED -
4 ALUMINIUM GLASS WINDOW Nos NIL NIL NIL NIL NIL 32 32
6W2 (1.8m x 2m), POLYSTER POWDER COATED -
5 ALUMINIUM GLASS WINDOW Nos NIL NIL NIL NIL NIL 17 17
6W3 ( 1m x 1.2m), POLYSTER POWDER COATED -
6 ALUMINIUM GLASS WINDOW Nos NIL NIL NIL NIL NIL 8 8
-
6V1 ( 0.6m x 0.6m), POLYSTER POWDER COATED
7 ALUMINIUM FIXED GLASS WITH EXHAUST FAN Nos NIL NIL NIL NIL NIL 32 32
6DD1 ( 0.6m x 2m), POWDER COATED ALUMINIUM -
8 LOUVERED WINDOW Nos NIL NIL NIL NIL NIL 2 2
-
WOODEN DOORS -
1 6D1 ( 1.1m x 2.1m), SOLID WOODEN PANELED DOOR Nos NIL NIL NIL NIL NIL 8 8
-
2 6D2 ( 1m x 2.1m), SEMI SOLID WOODEN FLUSH DOOR Nos NIL NIL NIL NIL NIL 24 24
-
3 6D3 ( 0.9m x 2.1m), SEMI SOLID WOODEN FLUSH DOOR Nos NIL NIL NIL NIL NIL 18 18
-
4 6D4 ( 0.9m x 2.1m), SEMI SOLID WOODEN FLUSH DOOR Nos NIL NIL NIL NIL NIL 8 8
-
5 6D5 ( 0.8m x 2.1m), SEMI SOLID WOODEN FLUSH DOOR Nos NIL NIL NIL NIL NIL 32 32
-
SS DOORS -
1 6ED ( 2.4m x 2.4m), SS FRAME GLASS DOOR Nos NIL NIL NIL NIL NIL 1 1
-
2 6D7 ( 1m x 2.1m), SS FRAME GLASS DOOR Nos NIL NIL NIL NIL NIL 1 1
-
DOORS AND WINDOWS BILL 8 -
Page 23 BILL 8
FIRE DOOR -
1 6FD ( 1m x 2.1m), 90MIN FIRE RATED FIRE EXIT DOOR Nos NIL NIL NIL NIL NIL 10 10
-
CARPENTRY WORKS -
Page 21 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
600mm WIDE WOODEN FLOOR CABINET INCLUDING Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
2
1 SINK/WASH TROUGH m NIL NIL NIL NIL NIL 45 45
-
2 450mm WIDE WOODEN OVERHEAD WALL CABINET m2 NIL NIL NIL NIL NIL 45 45
-
BLOCK – 7 A,B,C -
DOORS AND WINDOWS -
ALUMINIUM WORKS -
-
7W1 (1.2m x 3.8m), POLYSTER POWDER COATED
1 ALUMINIUM GLASS WINDOW Nos NIL NIL NIL NIL NIL NIL 4 4
-
7W2 (1.2m x 3m), POLYSTER POWDER COATED
2 Nos NIL NIL NIL NIL NIL NIL 4 4
ALUMINIUM GLASS WINDOW
-
7W3 (1.2m x 2.7m), POLYSTER POWDER COATED
3 Nos NIL NIL NIL NIL NIL NIL 4 4
ALUMINIUM GLASS WINDOW
-
7V1 (0.6m x 0.6m), POWDER COATED ALUMINIUM FIXED
4 Nos NIL NIL NIL NIL NIL NIL 4 4
GLASS WITH EXHAUST FAN
-
WOODEN DOORS -
1 7D1 ( 1m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL NIL NIL NIL NIL 5 5
-
2 7D2 ( 0.9 x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL NIL NIL NIL NIL 2 2
-
3 7D3 ( 0.8 m x 2.1m), SEMI SOLID WOODEN FLUSH DOOR Nos NIL NIL NIL NIL NIL NIL 3 3
-
BLOCK – 8 A,B -
DOORS AND WINDOWS -
-
8LD1 (2m xWORKS
ALUMINIUM 2.4m), POLYSTER POWDER COATED -
1 ALUMINIUM LOUVERED DOOR Nos NIL NIL NIL NIL NIL NIL NIL 2 2
-
8LW1 (1.2m x 3m), POLYSTER POWDER COATED
2 ALUMINIUM LOUVERED WINDOW Nos NIL NIL NIL NIL NIL NIL NIL 4 4
-
BLOCK 9 -
DOORS AND WINDOWS, CARPENTARY WORKS -
-
ALUMINIUM WORKS -
9D1 (2m x 2.1m), POLYSTER POWDER COATED
1 ALUMINIUM DOUBLE SWING DOOR Nos NIL NIL NIL NIL NIL NIL NIL NIL 1 1
9W1 (1.6m x 1.8m), POLYSTER POWDER COATED -
2 ALUMINIUM GLASS WINDOW Nos NIL NIL NIL NIL NIL NIL NIL NIL 26 26
-
Page 22 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
9W2 (1.6m x 1.6m), POLYSTER POWDER COATED
3 ALUMINIUM GLASS WINDOW Nos NIL NIL NIL NIL NIL NIL NIL NIL 3 3
-
9V1 (0.6m x 0.6m), POLYSTER POWDER COATED
4 Nos NIL NIL NIL NIL NIL NIL NIL NIL 21 21
ALUMINIUM GLASS WINDOW
-
WOODEN DOORS -
1 9D2 ( 1m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL NIL NIL NIL NIL NIL NIL 26 26
-
2 9D3 ( 1 x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos NIL NIL NIL NIL NIL NIL NIL NIL 2 2
-
3 9D4 ( 0.8 m x 2.1m), SEMI SOLID WOODEN FLUSH DOOR Nos NIL NIL NIL NIL NIL NIL NIL NIL 21 21
-
600mm WIDEWORKS
CARPENTRY WOODEN FLOOR CABINET INCLUDING -
1 SINK/WASH TROUGH m2 NIL NIL NIL NIL NIL NIL NIL NIL 75 75
2
-
2 450mm WIDE WOODEN OVERHEAD WALL CABINET m NIL NIL NIL NIL NIL NIL NIL NIL 75 75
-
BLOCK 10 -
DOORS AND WINDOWS -
-
ALUMINIUM WORKS -
1 10ALD1 ( 2m x 3m), ALUMINIUM LOUVERED DOOR Nos 1 1
-
BLOCK 11 NIL -
-
-
-
-
-
-
-
DOORS AND WINDOWS BILL 8 -
Page 25 BILL 8
-
BILL 9 WATERPROOFING WORKS -
-
1 1000 G POLYTHENE SHEET m2 22,560 6,150 1,130 1,500 1700 1600 330 620 825 840 1,190 NIL 38,445
Two layers shall be laid below all concrete works cast directly in -
contact with soil for substructure works.
-
2 COLD BITUMIN PAINT m2 ### 8,300 2,730 2,250 3200 3200 1,260 1460 750 2,040 3,080 NIL 258,470
All RCC works and substructure blockwork which comes directly
in contact with soil shall be waterproofed with two coats of cold -
bitumen paint Nitopruf 10 or equivalent.
-
3 DPC LAYER m2 250 30 15 25 40 60 20 20 20 10 45 NIL 535
Page 23 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
230MM WIDE DPC ABOVE TIE BEAM FOR ALL BLOCK
WORKS. DPC LAYER SHALL BE FLEXIBLE BITUMEN -
MEMBRANE OF THICKNESS BETWEEN 0.25MM TO 0.5MM
25mm THICK FLEXCELL SHEET WITH DRY DENSITY OF -
4 APPROX. 275Kg/m3 m2 1,700 200 30 50 40 90 10 40 15 6 45 20 2,246
-
5 WATER PROOFING: -
a ROOF WATERPROOFING m2 110 32 510 620 700 800 150 NIL 300 NIL NIL NIL 3,222
WET ARE WATERPROOFING SHALL BE OF LIQUID -
b MEMBRANE FROM FOSRCO OR EQUIVALENT m2 400 25 200 240 270 380 15 NIL 115 NIL NIL NIL 1,645
2mm THICK HDPE LINER WITH TENSILE STRENGTH AT -
2
6 BREAK SHALL BE 53N/mm m 20 810 NIL NIL NIL NIL NIL 1240 NIL NIL NIL NIL 2,070
2mm THICK SELF ADHESIVE WITH MASS AS 2.1 Kg/m2 -
2 2
7 AND
4mm TENSILE
THICK STRENGTH
PROTECTIONOF 38N/mm
BOARD WITH SPECIFIC m 35 NIL NIL NIL NIL NIL NIL 800 NIL 1340 NIL NIL 2,175
3 -
GRAVITY OF 1.28Kg/m AND PUNCTURE RESISTANCE OF
8 950N THICK GRP LINING CONSISTING OF RESIN PRIME
3mm m2 35 NIL NIL NIL NIL NIL NIL 800 NIL 1340 NIL NIL 2,175
COAT, MUTIL LAYER MATT OF 450GSM AND GEL COAT -
9 FINISH AT TOP m2 NIL NIL NIL NIL NIL NIL NIL NIL NIL 2300 1000 NIL 3,300
-
50mm THICK CORK SHEET BELOW AND AROUND m2
10 4,100 4,100
MACHINE FOUNDATION
WATERPROOFING WORKS BILL 9 -
Page 26 BILL 9
-
EXTERNAL WORKS -
-
1 SITE CLEARING AND PREPARATORY WORKS LS 1 1
-
2 MANHOLES AND GULLY TRAPS -
900mm x 900mm SIZE Nos 21 21
-
600mm x 600mm SIZE Nos 99 99
-
300mm x 300mm GULLY TRAP Nos 50 50
-
CIVIL WORK INCLUDES: -
a EXCAVATION, BACKFILLING AND CARTAWAYS. -
-
PCC, BASE AND WALL SHALL BE OF SOLID BLOCK
b INCLUDING HEAVY DUTY MANHOLE COVER. EXTERNAL -
AND INTERNAL PLASTERING
-
c ANTI-TERMITE TREATMENT ON FOUNDATION SOIL -
-
Page 24 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
WATERPROOFING AND MOISTURE WORKS SUCH AS
d 1000G POLYTHENE SHEET, COLD BITUMEN PAINT, -
INTERNAL HDPE LINING, EXTERNAL SELF ADHESIVE
AND PROTECTION BOARD
-
3 UPSTAND/FLASH KERBSTONE
SUPPLY AND FIXING WORKS150mm x 300mm x Rm
OF KERBSTONE 1350 1,350
CIVIL WORK
900mm SIZE INCLUDES:
WHICH SHOULD BE EMBEDDED IN RCC -
a EXCAVATION, BACKFILLING
CONCRETE HAUNCH. TO AND CARTAWAYS.
INCLUDE PAINTING ON -
KERBSTONE , SHALL BE BLACK AND YELLOW STRIPS. -
b GARDE/CHARACTERISTIC STRENGTH SHALL BE 20MPa -
-
c ANTI-TERMITE TREATMENT ON FOUNDATION SOIL -
-
4 FIRE HYDRANT WORKS Nos 23 23
CIVIL WORK INCLUDES: -
a EXCAVATION, BACKFILLING AND CARTAWAYS. -
-
Page 25 of 152
Dated-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
Block-1 Block-2 Block-3 Block-4 Block-5 Block-6 Block-7 Block-8 Block-9 Block-10 Block-11 External QUANTITY NGN NGN
EXTERNAL WORK BILL -
Page 28 EXTERNAL WORK
MARKING/SIGNAGE, WARNINGS ETC AS PER THE -
8 DRAWING
ALL CAR PARK SPACES WITH APPROPRIATE SIGNAGE LS 1 1
FOR
CIVILCAR
WORKPARKING, INCLUDE WHEEL STOPPER/ KERB
INCLUDES: -
a STONE PAINTED IN BLACK AND WHITE STRIPS Item -
-
ALL DIRECTION ARROWS, ROAD MARKINGS, SIGNAGES
b SHALL BE MARKED ON ROADS, RAMPS, INTERLOCK Item -
TILES
-
c NECESSARY WARNING SIGNS, EMBEDDED COVERS ETC Item -
ALL THE ABOVE IN LS -
PLANTER BOX FINISHES ETC COMPLETE IN ALL -
9 RESPECT AS PER THE DRAWING Item 1 1
-
10 OIL
RCCSOAK PIT PIT
SOAKING COMPLETE IN ALL
OF SIZE 1.5m RESPECTS
x 1.5m x 2.75m. BASE SLAB Item 1 1
3 3 -
1.5m , WALL 2m
-
11 INTERLOCK PAVING WORKS m2 14,030 14,030
-
12 LANDSCAPING WORKS m2 8,500 8,500
-
13 SAUCER DRAIN Rm 4,640 4,640
CIVIL WORK INCLUDES: -
a EXCAVATION, BACKFILLING AND CARTAWAYS. -
SUPPLY, LAYING AND INSTALLATION OF PRECAST -
b SAUCER DRAIN OF SIZE 100mm x 450mm x 300mm. -
-
-
-
-
-
-
-
0 -
-
-
-
Page 26 of 152
Date-12/12/2018
SUMMARY
BILL 1: PRELIMINARIES
BILL 2: EARTHWORK
BILL 7: FINISHES
TOTAL 0.00
Page 1/ Summary
Page 27 of 152
Date-12/12/2018
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
1 CONTRACTOR'S PRELIMINARIES
2 INSURANCES
4 MOBILISATION
5 DEMOBILISATION
6 TENDER FEE
7 HANDING OVER
PRELIMINARIES BILL 1
Page 2/ BILL 1
Page 28 of 152
Date-12/12/2018
BILL 2: EARTHWORK
there is level difference between finished levels and to suite the profile of land. Temporary
EXCAVATION AND CUTTING FOR PLOT LEVELS SHALL BE IN ALL TYPES OF
SOIL/ROCK ETC, AS PER THE SOIL REPORT:
a PCC AREA SHALL BE MEASURED AND PAID FOR
b SHORING IF REQUIRED WILL NOT BE PAID EXTRA
1 EXCAVATION
FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL m3 36470
2 BACKFILLING
All back filling shall be carried in layers of not more than 300mm thickness with degree of
compaction not be less than 98% of MDD
a BACKFILLING WITH EXCAVATED SOIL m3 23410
b BACKFILLING WITH IMPORTED(laterite)SAND m3 1750
COMPACTED ROADBASE OR EQUIVALENT GRADED MATERIAL SUBJECT
C m3 1800
TO APPROVAL
3 1 TO FORMATION LEVEL AS PER THE DRAWING AND CARTING AWAY SURPLUS m3 12780
EARTHWORK BILL 2
Page 3/ BILL 2
Page 29 of 152
Date-12/12/2018
Page 30 of 152
Date-12/12/2018
Page 31 of 152
Date-12/12/2018
Enamel paint
Page 32 of 152
Date-12/12/2018
SUB-STATION
1 230mm THICK SOLID BLOCKWALL m2 300
MAIN FACTORY
1 230mm THICK SOLID BLOCKWALL m2 1750
HT/LT PANEL
1 230mm THICK SOLID BLOCKWALL m2 70
BLOCKWORK BILL 5
Page 11/BILL 6
Page 33 of 152
Date-12/12/2018
BILL 7: FINISHES
junction of RCC members and block walls, necessary grooves minimum 10mm x 10mm shall
EREMA PANEL ROOM
1 PLASTER
a 15mm THICK PLASTER (External) (Cement : Mortar ratio 1:3) m2 300
b 12mm thick Plaster (Internal) (Cement : Mortar ratio 1:4) m2
2 PAINTING
a INTERNAL WALL – 5 coats of emulsion m2 300
b SLAB TOP AND CEILING– 5 coats of emulsion m2 140
c Enamel paint on walls m2
SUB-STATION
PLASTER
a 15mm THICK PLASTER (External) (Cement : Mortar ratio 1:3) m2 850
b 12mm thick Plaster (Internal) (Cement : Mortar ratio 1:4) m2
PAINTING
a INTERNAL WALL – 5 coats of emulsion m2 1000
b SLAB TOP AND CEILING– 5 coats of emulsion m2 550
c Enamel paint on walls m2
HT/LT PANEL
1 PLASTER
a 15 mm 20mm THICK PLASTER (External) (Cement : Mortar ratio 1:3) m2 170
b 12mm thick Plaster (Internal) (Cement : Mortar ratio 1:4) m2
2 PAINTING
a EXTERNAL WALL – Proprietary Jotashield paint m2 202
b CEILING– 5 coats of emulsion m2 50
c Enamel paint on walls m2
MAIN FACTORY
1 PLASTER
a 15 mm 20mm THICK PLASTER (External) (Cement : Mortar ratio 1:3) m2 6200
b 12mm 15mm THICK INTERNAL PLASTER (Cement : Mortar ratio 1:4) m2 7300
2 PAINTING
a EXTERNAL – RUSH TYROLENE PAINT ON PLASTERED SURFACE m2 6200
b INTERNAL PAINT – 5 COAT OF EMULSION PAINT m2 7300
c Enamel paint on walls m2
2 FLOORING
a CERAMIC TILE m2 1050
3 WALL TILE
a CERAMIC TILE m2 620
4 CEILING
a 600 x 600 GYPSUM BOARD EXPOSED FALSE CEILING m2 1300
5 SKIRTING
a CERAMIC TILE Rm 290
FINISHES BILL 6
Page 12/BILL 7
Page 34 of 152
Date-12/12/2018
RUD'S
1 RUD -1 Nos 5
2 RUD -2 Nos 6
2 D1' Nos 4
3 D2 Nos 21
4 D3 Nos 10
5 D6 Nos 4
6 D7 Nos 3
7 W1 Nos 4
8 W2 Nos 14
9 W3 Nos 6
10 W4 Nos 4
11 V Nos 6
12 FW Nos 17
13 FW1 Nos 4
2 D5 Nos 5
STEEL DOOR
1 SD Nos 8
MS DOOR
1 FED Nos 4
Page 35 of 152
Date-12/12/2018
SILO FOUNDATION
1 1000
Two G POLYTHENE SHEET m2 520 0.00
layers shall be laid below all concrete works cast directly in contact with soil for
substructure works.
2 COLD BITUMIN PAINT m2 800 0.00
All RCC works and substructure blockwork which comes directly in contact with soil shall be
waterproofed with two coats of cold bitumen paint Nitopruf 10 or equivalent.
JUMBO STAND FOUNDATION
1 1000 G POLYTHENE SHEET m2 520 0.00
SUB-STATION
1 1000 G POLYTHENE SHEET m2 960
3 DPC LAYER m 2
25
Page 36 of 152
Date-12/12/2018
TFH FOUNDATION
1 1000 G POLYTHENE SHEET m2 120
TUT FOUNDATION
1 1000 G POLYTHENE SHEET m2 580
RECYCLING FOUNDATION
1 1000 G POLYTHENE SHEET m2 80
HT/LT PANEL
1 1000 G POLYTHENE SHEET m2 105
4 ROOF WATERFROOFING m 2
51
MAIN FACTORY
1 1000 G POLYTHENE SHEET m2 16000
TRANSFORMER PAD
1 1000 G POLYTHENE SHEET m2 40
WATERPROOFING WORKS
Page 15/B8
Page 37 of 152
Date-12/12/2018
3 FLEXCELL SHEET m 2
15
ILC PIT
1 1000 G POLYTHENE SHEET m2 18 0.00
METALLIZER PIT
1 1000 G POLYTHENE SHEET m2 130 0.00
RECYCLING PIT
1 1000 G POLYTHENE SHEET m2 341 0.00
WATERPROOFING WORKS
Page 15/B8
Page 38 of 152
Date-12/12/2018
RMS PIT
1 1000 G POLYTHENE SHEET m2 155 0.00
3 DPC LAYER m 2
230 mm wide DPC above Tie Beam for all blockwork. DPC layer shall be Flexible Bitumen
Membrane of Thickness between 0.25 mm to 0.5 mm
WATERPROOFING WORKS
Page 17/BILL 9
Page 39 of 152
Date-12/12/2018
SUMMARY
TOTAL 0.00
Page 40 of 152
Date-12/12/2018
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
1 CONTRACTOR'S PRELIMINARIES
2 INSURANCES
4 MOBILISATION Included in
Block-1 for
5 DEMOBILISATION complete site
6 TENDER FEE
7 HANDING OVER
Note-Included in Block-1 for complete site. Individual blocks need not to be quoted seperately
Page 41 of 152
Date-12/12/2018
BILL 2: EARTHWORK
there is level difference between finished levels and to suite the profile of land. Temporary
EXCAVATION AND CUTTING FOR PLOT LEVELS SHALL BE IN ALL TYPES OF
SOIL/ROCK ETC, AS PER THE SOIL REPORT:
a PCC AREA SHALL BE MEASURED AND PAID FOR
b SHORING IF REQUIRED WILL NOT BE PAID EXTRA
1 EXCAVATION
a FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL m3 8030
2 BACKFILLING
All back filling shall be carried in layers of not more than 300mm thickness with degree of
compaction
BACKFILLING not beWITH
less than 98% of MDD
EXCAVATED SOIL
a m3 4020
b BACKFILLING WITH IMPORTED SAND m3 490
200mm THICK COMPACTED ROADBASE (laterite) OR WELL GRADED EQUIVALENT
c m3 330
MATERIAL SUBJECTED TO APPROVAL.
3 2 TO FORMATION LEVEL AS PER THE DRAWING AND CARTING AWAY SURPLUS m3 3400
EARTHWORK BILL 2
Page 2/BILL 2
Page 42 of 152
Date-12/12/2018
1 100mm THICK PCC BELOW THE FOOTING AND SOLID BLOCKWORK. m3 110
b SUBSTRUTURE COLUMN m 3
120
c MACHINE FOUNDATION m3 60
e TIE BEAM m3 20
f SUPERSTRUCTURE COLUMN m 3
2
g STIFFENER COLUMN m3 15
I INTERMEDIATE BEAM m 3
32
j COPING BEAM m 3
35
k 200mm THICK RCC GRADE SLAB, BRC A-252 DOUBLE MESH m2 2260
n TRENCH WALL m3 26
o ROOF SLAB m3 7
p PARAPET WALL m 3
3
q RAMP SLAB m 3
150
r RAMP WALL m3 35
CHIMNEY FOUNDATION
1 PCC m3 4
Page 43 of 152
Date-12/12/2018
3 RCC WALL m 3
50
3 RCC WALL m3 21
2 RCC FOUNDATION m 3
18
Page 44 of 152
Date-12/12/2018
8 TRENCH GRATING m2 60
Page 45 of 152
Date-12/12/2018
2 HOLLOW BLOCKWORK
a 230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR SUPERSTRUCTURE m2 1000
BLOCKWORK BILL 5
Page 6/B5
Page 46 of 152
Date-12/12/2018
BILL 6: FINISHES
1 PLASTER
junction of RCC members and block walls,necessary grooves minimum 10mm x 10mm shall
a 15 mm 20mm THICK PLASTER (External) (Cement : Mortar ratio 1:3) m2 2000
2 PAINTING
a EXTERNAL WALL – RUSH TYROLEAN PAINT m2 2000
b INTERNAL PAINT – 5 COAT OF EMULSION PAINT m2 1400
c Enamel paint on walls m2
3 FLOORING
a ACID PROOF TILES m2 380
c SMOOTH POWER FLOAT FINISH with FLOOR HARDNER (applied @ 4 Kg/ Sqm) m2 2400
4 CEILING
VINYL FACED & ALUMINIUM BACK 600mm x 600mm GYPSUM TILE ON EXPOSED
a m2 220
GRID
5 SKIRTING
CERAMIC TILE Rm 80
FINISHES BILL 6
Page 7/B6
Page 47 of 152
Date-12/12/2018
ALUMINIUM WORKS
WOODEN DOORS
1 D3 ( 1m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos 3
RUD'S
1 RUD 1 ( 5m x 6m), ROLL-UP SANDWICH DOOR Nos 3
Page 48 of 152
Date-12/12/2018
1 1000
Two G POLYTHENE SHEET m2 4400
layers shall be laid below all concrete works cast directly in contact with soil for
substructure works.
2 COLD BITUMIN PAINT m2 6600
All RCC works and substructure blockwork which comes directly in contact with soil shall be
waterproofed with two coats of cold bitumen paint Nitopruf 10 or equivalent.
3 DPC LAYER m2 30
230 mm wide DPC above Tie Beam for all blockwork. DPC layer shall be Flexible Bitumen
Membrane of Thickness between 0.25 mm to 0.5 mm
4 25MM THICK FLEXCELL SHEET BETWEEN TWO COLUMNS FOR EVERY 16M C/C m2 200
5 ROOF WATERFROOFING m 2
32
CHIMNEY FOUNDATION
1 1000 G POLYTHENE SHEET m2 48
COOLING TOWER/RADIATOR
1 1000 G POLYTHENE SHEET m2 140
HRU/VAM FOUNDATION
1 1000 G POLYTHENE SHEET m2 70
Page 49 of 152
PROPOSED FILM PACKAGING INDUSTRIAL AND RESIDENTIAL DEVELOPMENT Date-12/12/2018
ON PLOT No IJC 354 (OG). UTM(ZONE 31), OGUN STATE, NIGERIA, SOUTH AFRICA
FOR FLEX FILMS AFRICA PVT. LIMITED
(C) BLOCK 3- ADMIN BUILDING
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
0 0 NGN NGN
BLOCK 3- ADMIN BUILDING
SUMMARY
BILL 1: PRELIMINARIES -
BILL 2: EARTHWORK -
BILL 6: FINISHES -
TOTAL -
Page 50 of 152
(C) BLOCK 3- ADMIN BUILDING Date-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
0 0 NGN NGN
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
1 CONTRACTOR'S PRELIMINARIES
2 INSURANCES
4 MOBILISATION Included in
Block-1 for
5 DEMOBILISATION complete site
6 TENDER FEE
7 HANDING OVER
Note-Included in Block-1 for complete site. Individual blocks need not to be quoted seperately
PRELIMINARIES BILL 1 -
Page 1 BILL 1
Page 51 of 152
(C) BLOCK 3- ADMIN BUILDING Date-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
0 0 NGN NGN
BILL 2: EARTHWORK
there is level difference between finished levels and to suite the profile of land. Temporary
EXCAVATION AND CUTTING FOR PLOT LEVELS SHALL BE IN ALL TYPES OF
SOIL/ROCK ETC, AS PER THE SOIL REPORT:
a PCC AREA SHALL BE MEASURED AND PAID FOR
b SHORING IF REQUIRED WILL NOT BE PAID EXTRA
1 EXCAVATION:
a FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL m3 4100
2 BACKFILLING:
All back filling shall be carried in layers of not more than 300mm thickness with degree of
compaction not be less than 98% of MDD
a BACKFILLING WITH EXCAVATED SOIL m3 1110
b BACKFILLING WITH IMPORTED
COMPACTED ROADBASE SAND
(laterite) OR EQUIVALENT GRADED MATERIAL SUBJECT m3 2180
c m3 194
TO APPROVAL
3 3 TO FORMATION LEVEL AS PER THE DRAWING AND CARTING AWAY SURPLUS m3 2800
EARTHWORK BILL 2 -
Page 2/BILL 2
Page 52 of 152
(C) BLOCK 3- ADMIN BUILDING Date-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
0 0 NGN NGN
c SUBSTRUTURE COLUMN m3 7
d WALL FOOTING m 3
1
e TIE BEAM m3 17
f SUPERSTRUCTURE COLUMN m3 34
o PARAPET WALL m 3
21
Page 53 of 152
(C) BLOCK 3- ADMIN BUILDING Date-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
0 0 NGN NGN
1 STAIRCASE HANDRAIL Rm 40
Page 54 of 152
(C) BLOCK 3- ADMIN BUILDING Date-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
0 0 NGN NGN
2 HOLLOW BLOCKWORK
a 230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR SUPERSTRUCTURE m2 685
BLOCKWORK BILL 5 -
Page 5/B5
Page 55 of 152
(C) BLOCK 3- ADMIN BUILDING Date-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
0 0 NGN NGN
BILL 6: FINISHES
1 PLASTER
junction of RCC members and block walls,necessary grooves minimum 10mm x 10mm shall
a 15 mm 20mm THICK PLASTER (External) (Cement : Mortar ratio 1:3) m2 390
2 PAINTING
a EXTERNAL WALL – TEXURED PAINT WITH 2 COAT OF POLYURETHANE m2 320
b INTERNAL WALL – 5 COAT OF EMULSION PAINT m2 2220
c INTERNAL CEILING – 5 COAT OF EMULSION PAINT m2
d Enamel paint on walls m2
4 FLOORING
a NATURAL GRANITE m2 40
6 FALSE CEILING
a DECORATIVE GYPSUM FALSE CEILING – AIRLOCK LOBBY m2 315
VINYL FACED & ALUMINIUM BACK 600mm x 600mm GYPSUM TILE ON EXPOSED
b m 2
315
GRID
c 600mm x 600mm CONCEALED GRID METALLIC FALSE CEILING m2 15
FINISHES BILL 6 -
Page 6/B6
Page 56 of 152
(C) BLOCK 3- ADMIN BUILDING Date-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
0 0 NGN NGN
ALUMINIUM WINDOWS
1 D1 ( 1.8m x 2.1m), HEAVY DUTY FULLY GLAZED DOUBLE SWING DOOR Nos
WOODEN DOORS
1 D3 ( 0.9m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos 2
GLASS DOORS
1 D2 ( 1m x 2.1m), 10mm THICK TOUGHENED GLASS DOOR Nos 26
Page 57 of 152
(C) BLOCK 3- ADMIN BUILDING Date-12/12/2018
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT
0 0 NGN NGN
1 1000
Two G POLYTHENE
layers SHEET
shall be laid below all concrete works cast directly in contact with soil for m2 1070
substructure works.
2 COLD BITUMIN PAINT m2 2730
All RCC works and substructure blockwork which comes directly in contact with soil shall be
waterproofed with two coats of cold bitumen paint Nitopruf 10 or equivalent.
3 DPC LAYER
230 mm wide DPC above Tie Beam for all blockwork. DPC layer shall be Flexible Bitumen m2 15
Membrane of Thickness between 0.25 mm to 0.5 mm
4 25MM THICK FLEXCELL SHEET m2 30
5 WATER PROOFING:
a ROOF WATERPROOFING m2 510
Page 58 of 152
Date-12/12/2018
SUMMARY
BILL 1: PRELIMINARIES -
BILL 2: EARTHWORK -
BILL 6: FINISHES -
TOTAL -
Page 59 of 152
Date-12/12/2018
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
1 CONTRACTOR'S PRELIMINARIES
2 INSURANCES
4 MOBILISATION Included in
Block-1 for
5 DEMOBILISATION complete site
6 TENDER FEE
7 HANDING OVER
Note-Included in Block-1 for complete site. Individual blocks need not to be quoted seperately
Page 60 of 152
Date-12/12/2018
BILL 2: EARTHWORK
there is level difference between finished levels and to suite the profile of land. Temporary
EXCAVATION AND CUTTING FOR PLOT LEVELS SHALL BE IN ALL TYPES OF
SOIL/ROCK ETC, AS PER THE SOIL REPORT:
a PCC AREA SHALL BE MEASURED AND PAID FOR
b SHORING IF REQUIRED WILL NOT BE PAID EXTRA
1 EXCAVATION
a FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL m3 2100
2 BACKFILLING
All back filling shall be carried in layers of not more than 300mm thickness with degree of
compaction not be less than 98% of MDD
a BACKFILLING WITH EXCAVATED SOIL m3 280
b BACKFILLING WITH IMPORTED(laterite)SAND m3 1290
COMPACTED ROADBASE OR EQUIVALENT GRADED MATERIAL SUBJECT
c m3 270
TO APPROVAL
3 4 TO FORMATION LEVEL AS PER THE DRAWING AND CARTING AWAY SURPLUS
a FROM NGL TILL FFL m3 8760
b FROM FFL TO FOUNDATION LEVEL m3 1820
Page 61 of 152
Date-12/12/2018
b PEDESTAL COLUMN m 3
15
g TIE BEAM m 3
15
h WALL FOOTING m3 11
l PARAPET WALL m3 28
n RAMP SLAB m3 9
Page 62 of 152
Date-12/12/2018
Page 63 of 152
Date-12/12/2018
2 HOLLOW BLOCKWORK
a 230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR SUPERSTRUCTURE m2 1250
Page 64 of 152
Date-12/12/2018
BILL 6: FINISHES
1 PLASTER
junction of RCC members and block walls,necessary grooves minimum 10mm x 10mm shall
a 15 mm 20mm THICK PLASTER (External) (Cement : Mortar ratio 1:3) m2 2500
2 PAINTING
a EXTERNAL WALL – RUSH TYROLEAN PAINT m2 2680
b INTERNAL WALL – 5 COAT OF EMULSION PAINT m2 3860
c INTERNAL CEILING – 5 COAT OF EMULSION PAINT m2 650
d Enamel paint on walls m2
3 WALL TILE
a GRANITE TILE m2 275
b GLAZED CERAMIC TILE m2 765
3 FLOORING
a GRANITI TILE m2 1100
b ANTI-SLIP CERAMIC TILE m2 310
c TERRAZZO TILE m2 720
4 FALSE CEILING
VINYL FACED & ALUMINIUM BACK 600mm x 600mm GYPSUM TILE ON EXPOSED
a m2 760
GRID
5 SKIRTING (100 mm height)
a GRANITI TILE Rm 570
b TERRAZZO TILE Rm 125
Page 65 of 152
Date-12/12/2018
ALUMINIUM WORKS
1 D1 (2m x 2.1m), POLYSTER POWDER COATED ALUMINIUM DOUBLE SWING DOOR Nos 5
WOODEN DOORS
1 D2 ( 1m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos 38
Page 66 of 152
Date-12/12/2018
1 1000
Two G POLYTHENE SHEET m2 1500
layers shall be laid below all concrete works cast directly in contact with soil for
substructure works.
2 COLD BITUMIN PAINT m2 2250
All RCC works and substructure blockwork which comes directly in contact with soil shall be
waterproofed with two coats of cold bitumen paint Nitopruf 10 or equivalent.
3 DPC LAYER m2 25
230 mm wide DPC above Tie Beam for all blockwork. DPC layer shall be Flexible Bitumen
Membrane of Thickness between 0.25 mm to 0.5 mm
4 25mm THICK FLEXCELL SHEET m2 50
5 WATERPROOFING
a ROOF WATERFROOFING m2 620
b WET AREA WATERPROOFING m2 240
Page 67 of 152
Date-12/12/2018
SUMMARY
BILL 1: PRELIMINARIES -
BILL 2: EARTHWORK -
BILL 6: FINISHES -
TOTAL -
Page 68 of 152
Date-12/12/2018
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
1 CONTRACTOR'S PRELIMINARIES
2 INSURANCES
4 MOBILISATION Included in
Block-1 for
5 DEMOBILISATION complete site
6 TENDER FEE
7 HANDING OVER
PRELIMINARIES BILL 1
Page 1 BILL 1
Page 69 of 152
Date-12/12/2018
BILL 2: EARTHWORK
wherever there is level difference between finished levels and to suite the profile of land.
EXCAVATION AND CUTTING FOR PLOT LEVELS SHALL BE IN ALL TYPES OF
SOIL/ROCK ETC, AS PER THE SOIL REPORT:
a PCC AREA SHALL BE MEASURED AND PAID FOR
b SHORING IF REQUIRED WILL NOT BE PAID EXTRA
1 EXCAVATION
a FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL m3 3500
2 BACKFILLING
All back filling shall be carried in layers of not more than 300mm thickness with degree of
a compaction
BACKFILLING not beWITH
less than 98% of MDD
EXCAVATED SOIL 400
m3
b BACKFILLING WITH IMPORTED SAND m3 1500
COMPACTED ROADBASE (laterite) OR EQUIVALENT GRADED MATERIAL
c m3 140
SUBJECT TO APPROVAL
3 BLOCK-6 TO FORMATION LEVEL AS PER THE DRAWING AND CARTING AWAY m3 1620
EARTHWORK BILL 2
Page 2/BILL 2
Page 70 of 152
Date-12/12/2018
b PEDESTAL COLUMN m3
21
c TIE BEAM m3 4
f RCC SLABS:
GROUND FLOOR SLAB m3 45
FIRST FLOOR SLAB m3 90
SECOND FLOOR SLAB m3 87
THIRD FLOOR SLAB m3 87
ROOF SLAB m3 90
UPPER ROOF SLAB m3 18
g RCC WALL:
400mm THICK RCC WALL m3 105
300mm THICK RCC WALL m3 75
230mm THICK RCC WALL m3 195
h INTERMEDIATE BEAM m3 30
i LINTEL BEAM m3 50
l PARAPET WALL m3 33
Page 71 of 152
Date-12/12/2018
m STAIRCASE:
m.1 LANDING, WAIST, TREAD AND RISER m3 54
m.2 STAIRCASE BEAM m3 1
Page 72 of 152
Date-12/12/2018
1 STAIRCASE HANDRAIL Kg
2 BALCONY HANDRAIL Kg
Page 73 of 152
Date-12/12/2018
2 HOLLOW BLOCKWORK
a 230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR SUPERSTRUCTURE m2 1550
BLOCKWORK BILL 5
Page 6/B5
Page 74 of 152
Date-12/12/2018
BILL 6: FINISHES
1 PLASTER
the junction of RCC members and block walls,necessary grooves minimum 10mm x 10mm
a 15 mm 20mm THICK PLASTER (External) (Cement : Mortar ratio 1:3) m2 3100
2 PAINTING
a EXTERNAL WALL – RUSH TYROLEAN PAINT m2 6600
b INTERNAL WALL – 5 COAT OF EMULSION PAINT m2 8360
c INTERNAL CEILING – 5 COAT OF EMULSION PAINT m2 920
d Enamel paint on walls m2
3 FLOORING
a NATURAL GRANITE m2 12
b GRANITE/MARBLE TILE m2 230
c TERRAZO TILE m2 610
d GRANITI TILE m2 1200
e ANTI-SLIP CERAMIC TILE m2 440
4 FALSE CEILING
a DECORATIVE FALSE CEILING m2 90
b 600mm x 600mm CONCEALED GRID METALLIC FALSE CEILING m2 580
c POWDER COATED ALUMINIUM FALSE CEILING m2 140
FINISHES BILL 6
Page 7/B6
Page 75 of 152
Date-12/12/2018
1 SD1 (2.1m x 2.4m), POLYSTER POWDER COATED ALUMINIUM SLIDING DOOR Nos 16
D6 (1m x 2.1m), MEDIUM DUTY POLYSTER POWDER COATED ALUMINIUM
2 Nos 2
SECTION DOOR
3 DD (0.6m x 2.1m), POWDER COATED ALUMINIUM SHUTTER Nos 2
WOODEN DOORS
1 D1 ( 1.1m x 2.1m), SOLID WOODEN PANELED DOOR Nos 8
SS DOORS
1 ED ( 2.4m x 2.4m), SS FRAME GLASS DOOR Nos 1
FIRE DOOR
1 FD ( 1m x 2.1m), 90MIN FIRE RATED FIRE EXIT DOOR Nos 10
Page 76 of 152
Date-12/12/2018
5 WATERPROOFING
a ROOF AND BALCONY WATERFROOFING m2 800
b WET AREA WATERPROOFING m2 300
Page 77 of 152
Dated-12/12/2018
SUMMARY
BILL 1: PRELIMINARIES -
BILL 2: EARTHWORK -
BILL 6: FINISHES -
0 0
TOTAL -
Page 78 of 152
Dated-12/12/2018
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
1 CONTRACTOR'S PRELIMINARIES
2 INSURANCES
4 MOBILISATION Included in
Block-1 for
5 DEMOBILISATION complete site
6 TENDER FEE
7 HANDING OVER
Page 79 of 152
Dated-12/12/2018
BILL 2: EARTHWORK
wherever there is level difference between finished levels and to suite the profile of land.
EXCAVATION AND CUTTING FOR PLOT LEVELS SHALL BE IN ALL TYPES OF
SOIL/ROCK ETC, AS PER THE SOIL REPORT:
PCC AREA SHALL BE MEASURED AND PAID FOR
SHORING IF REQUIRED WILL NOT BE PAID EXTRA
1 EXCAVATION
a FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL m3 890
2 BACKFILLING
All back filling shall be carried in layers of not more than 300mm thickness with degree of
compaction not be less than 98% of MDD
a BACKFILLING WITH EXCAVATED SOIL m3 831
b BACKFILLING
COMPACTED WITH ROADBASEIMPORTED SANDOR EQUIVALENT GRADED MATERIAL
(laterite) m3 NIL
c m3 36
SUBJECT TO APPROVAL
3 BLOCK-7 TO FORMATION LEVEL AS PER THE DRAWING AND CARTING AWAY m3 59
4 ANTI-TERMITE TREATMENT m 2
180
around the column pits, wall trenches, basement excavation, top surface of plinth filling,
Page 80 of 152
Dated-12/12/2018
b PEDESTAL COLUMN m3 5
c STRAP BEAM m3 7
e SUPERSTRUCTURE COLUMN m3 6
f ROOF BEAM m3 11
l PARAPET WALL m3 8
Page 81 of 152
Dated-12/12/2018
1 STAIRCASE HANDRAIL Kg
Page 82 of 152
Dated-12/12/2018
2 HOLLOW BLOCKWORK
a 230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR SUPERSTRUCTURE m2 440
Page 83 of 152
Dated-12/12/2018
BILL 6: FINISHES
1 PLASTER
the junction of RCC members and block walls,necessary grooves minimum 10mm x 10mm
a 15 mm 20mm THICK PLASTER (External) (Cement : Mortar ratio 1:3) m2 440
2 PAINTING
a EXTERNAL WALL – RUSH TYROLEAN PAINT m2 560
b INTERNAL PAINT – 5 COAT OF EMULSION PAINT m2 270
c CEILING – 5 COAT OF EMULSION PAINT m2 45
d Enamel paint on walls m2
3 TILE
a GLAZED CERAMIC WALL TILE DADO m2 25
b ANTI SLIP CERAMIC FLOOR TILE m2 115
5 CEILING
VINYL FACED & ALUMINIUM BACK 600mm x 600mm GYPSUM TILE ON
a m2 12
EXPOSED GRID
6 SKIRTING (100 mm height)
a CERAMIC TILE Rm 29
Page 84 of 152
Dated-12/12/2018
ALUMINIUM WORKS
Page 85 of 152
Dated-12/12/2018
1 1000 G POLYTHENE
Two layers SHEET
shall be laid below all concrete works cast directly in contact with soil for m2 330
substructure works.
2 COLD BITUMIN PAINT m2 1260
All RCC works and substructure blockwork which comes directly in contact with soil shall
be waterproofed with two coats of cold bitumen paint Nitopruf 10 or equivalent.
3 DPC LAYER m2 20
230 mm wide DPC above Tie Beam for all blockwork. DPC layer shall be Flexible
Bitumen Membrane of Thickness between 0.25 mm to 0.5 mm
4 25mm THICK FLEXCELL SHEET m2 10
Page 86 of 152
Dated-12/12/2018
SUMMARY
BILL 1: PRELIMINARIES -
BILL 2: EARTHWORK -
BILL 6: FINISHES -
TOTAL -
Page 87 of 152
Dated-12/12/2018
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
1 CONTRACTOR'S PRELIMINARIES
2 INSURANCES
4 MOBILISATION Included in
Block-1 for
5 DEMOBILISATION complete site
6 TENDER FEE
7 HANDING OVER
Page 88 of 152
Dated-12/12/2018
BILL 2: EARTHWORK
wherever there is level difference between finished levels and to suite the profile of land.
EXCAVATION AND CUTTING FOR PLOT LEVELS SHALL BE IN ALL TYPES OF
SOIL/ROCK ETC, AS PER THE SOIL REPORT:
PCC AREA SHALL BE MEASURED AND PAID FOR
SHORING IF REQUIRED WILL NOT BE PAID EXTRA
1 EXCAVATION
a FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL m3 1000
2 BACKFILLING
All back filling shall be carried in layers of not more than 300mm thickness with degree of
a compaction
BACKFILLING not beWITH
less than 98% of MDD
EXCAVATED SOIL 310
m3
b BACKFILLING WITH IMPORTED SAND m3 440
COMPACTED ROADBASE (laterite) OR EQUIVALENT GRADED MATERIAL
c m3 80
SUBJECT TO APPROVAL
3 BLOCK-9 TO FORMATION LEVEL AS PER THE DRAWING AND CARTING AWAY m3 14730
EARTHWORK BILL 2
Page 2/BILL 2
Page 89 of 152
Dated-12/12/2018
b PEDESTAL COLUMN m3
5.5
d WALL FOOTING m3
10
g RCC SLABS:
220mm THICK RCC GRADE SLAB m2 255
220mm THICK FIRST FLOOR SLAB m3 65
220mm THICK SECOND FLOOR SLAB m3 65
220mm THICK ROOF FLOOR SLAB m3 65
150mm THICK UPPER ROOF SLAB m3 3
l PARAPET WALL m3 17
n RAMP SLAB m3
0.5
Page 90 of 152
Dated-12/12/2018
1 STAIRCASE HANDRAIL Kg
2 RAMP HANDRAIL Kg
2 HOLLOW BLOCKWORK
a 230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR SUPERSTRUCTURE m2 710
Page 91 of 152
Dated-12/12/2018
Page 92 of 152
Dated-12/12/2018
BILL 6: FINISHES
1 PLASTER
the junction of RCC members and block walls,necessary grooves minimum 10mm x 10mm
a 15 mm 20mm THICK PLASTER (External) (Cement : Mortar ratio 1:3) m2 1420
2 PAINTING
a EXTERNAL WALL – RUSH TYROLEAN PAINT m2 1500
b INTERNAL WALL – 5 COAT OF EMULSION PAINT m2 910
c INTERNAL CEILING – 5 COAT OF EMULSION PAINT m2 430
d Enamel paint on walls m2
3 WALL TILE
a CERAMIC TILE m2 530
3 FLOORING
a GRANITE TILE m2 130
4 FALSE CEILING
VINYL FACED & ALUMINIUM BACK 600mm x 600mm GYPSUM TILE ON
a m2 240
EXPOSED GRID
b DECORATIVE GYPSUM FALSE CEILING – STAIRCASE m2 25
Page 93 of 152
Dated-12/12/2018
ALUMINIUM WORKS
D1 (2m x 2.1m), POLYSTER POWDER COATED ALUMINIUM DOUBLE SWING
1 Nos 1
DOOR
2 W1 (1.6m x 1.8m), POLYSTER POWDER COATED ALUMINIUM GLASS WINDOW Nos 26
WOODEN DOORS
1 D2 ( 1m x 2.1m), SEMI SOLID WOOD FLUSH DOOR Nos 26
Page 94 of 152
Dated-12/12/2018
5 WATERPROOFING
a ROOF WATERFROOFING m2 300
b WET AREA WATERPROOFING m2 75
Page 95 of 152
Dated-12/12/2018
SUMMARY
BILL 1: PRELIMINARIES -
BILL 2: EARTHWORK -
BILL 6: FINISHES -
TOTAL -
Page 96 of 152
Dated-12/12/2018
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
1 CONTRACTOR'S PRELIMINARIES
2 INSURANCES
4 MOBILISATION Included in
Block-1 for
5 DEMOBILISATION complete site
6 TENDER FEE
7 HANDING OVER
Page 97 of 152
Dated-12/12/2018
BILL 2: EARTHWORK
wherever there is level difference between finished levels and to suite the profile of land.
EXCAVATION AND CUTTING FOR PLOT LEVELS SHALL BE IN ALL TYPES OF
SOIL/ROCK ETC, AS PER THE SOIL REPORT:
PCC AREA SHALL BE MEASURED AND PAID FOR
SHORING IF REQUIRED WILL NOT BE PAID EXTRA
1 EXCAVATION: m3 4530
FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL
2 BACKFILLING:
All back filling shall be carried in layers of not more than 300mm thickness with degree of
compaction not be less than 98% of MDD
a BACKFILLING WITH EXCAVATED SOIL m3 1420
b BACKFILLING
COMPACTED WITH ROADBASEIMPORTED SANDOR EQUIVALENT GRADED MATERIAL
(laterite) m3 NIL
c m3 330
SUBJECT TO APPROVAL
3 BLOCK-10 TO FORMATION LEVEL AS PER THE DRAWING AND CARTING AWAY m3 3110
4 ANTI-TERMITE TREATMENT m 2
1650
around the column pits, wall trenches, basement excavation, top surface of plinth filling,
0.00
Page 98 of 152
Dated-12/12/2018
1 PCC m3 76
2 RCC CONCRETE
a FOOTINGS m3 3.5
c PEDESTAL COLUMN m3 7
e TIE BEAM m3 2
g BEAM m3 45
h RCC SLAB m 3
150
I PARAPET WALL m3 9
Page 99 of 152
Dated-12/12/2018
3 Structural steel work with I-beams, Channels, plates, Brackets, Girders etc. Kg
BLOCKWORKS 5 0.00
Page 5/B5
BILL 6: FINISHES
1 PLASTER
the junction of RCC members and block walls,necessary grooves minimum 10mm x 10mm
a 15 mm 20mm THICK PLASTER (External) (Cement : Mortar ratio 1:3) m2 120
2 PAINTING
EXTERNAL PAINTING ON WALL – TEXTURED PAINT WITH 2 COAT OF
a m2 155
POLYURATHENE COAT
b INTERNAL WALL – 5 COAT OF EMULSION PAINT m2 NIL
c INTERNAL CEILING – 5 COAT OF EMULSION PAINT m2 55
d Enamel paint on walls m2
ALUMINIUM WORKS
1 ALD ( 2m x 3m), ALUMINIUM LOUVERED DOOR Nos 1
1 1000 G POLYTHENE
Two layers SHEET
shall be laid below all concrete works cast directly in contact with soil for m2 840 0.00
substructure works.
2 COLD BITUMIN PAINT m2 2040 0.00
All RCC works and substructure blockwork which comes directly in contact with soil shall
be waterproofed with two coats of cold bitumen paint Nitopruf 10 or equivalent.
3 3mm THICK GRP LINING m2 2300
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
1 CONTRACTOR'S PRELIMINARIES
2 INSURANCES
4 MOBILISATION
5 DEMOBILISATION
6 TENDER FEE
7 HANDING OVER
PRELIMINARIES BILL 1
Page 1 BILL 1
BILL 2 EARTHWORKS
The founding strata shall be well compacted and shall be tested for degree of compaction that
shall not be less than 98% of MDD. Adequate retaining measures shall be provided wherever
there is level difference between finished levels and to suite the profile of land. Temporary
shoring or retaining structure can be included depending upon the depths. Excess soil shall be
carted away.
SILO FOUNDATION
1 EXCAVATION: m3 49.9 13 1.35 875.75
FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL
2 BACKFILLING: m3
PROPOSED FILM PACKAGING INDUSTRIAL AND RESIDENTIAL DEVELOPMENT
ON PLOT No IJC 354 (OG). UTM(ZONE 31), OGUN STATE, NIGERIA, SOUTH AFRICA
FOR FLEX FILMS AFRICA PVT. LIMITED
All back filling shall be carried in layers of not more than 300mm thickness with degree of
compaction not be less than 98% of MDD
SURPLUS SOIL TO BE CART AWAY FROM SITE FOR PLOT LEVELLING TDO
3 MACHINE m3
Anti-termite treatment shall be carried out on soil prior to commencing any concrete work.
2 BACKFILLING:
EARTHWORKS BILL 2
Page 2/BILL 2
4 ANTI-TERMITE TREATMENT – 1 m2 2 2.4 2 9.60
ANTI-TERMITE TREATMENT – 2 m2 2 2.2 1.8 7.92
ANTI-TERMITE TREATMENT BELOW SOLID BLOCKWORK m2 22.11 1 22.11
ANTI-TERMITE TREATMENT BELOW GRADE SLAB m2 13.83 5.43 75.10
TOTAL m2 114.73
SUB-STATION
2 BACKFILLING: m3
TFH FOUNDATION
1 EXCAVATION m3 2 8 7 0.6 67.20
2 BACKFILLING: m3
2 BACKFILLING: m3
RECYCLING FOUNDATION
1 EXCAVATION m3 16.52 5 0.6 49.56
2 BACKFILLING: m3
HT/LT PANEL
1 EXCAVATION FOR FOOTING m3 4 2.8 2.2 3 73.92
EXCAVATION FOR SOLID BLOCKWALL m3 28 1 3 84.00
EXCAVATION FOR GRADE SLAB m3 58 0.2 11.60
TOTAL m3 169.52
2 BACKFILLING: m3
MAIN FACTORY
1 EXCAVATION FOR FOOTING 1 m3 73 5.8 4.6 3.2 6,232.45
EXCAVATION FOR FOOTING 2 m3 28 3 2.6 3.2 698.88
EXCAVATION FOR FOOTING 3 m3 31 3.8 2.6 3.2 980.10
EXCAVATION FOR FOOTING 4 m3 12 4 3 3.2 460.80
EXCAVATION FOR FOOTING 5 m3 21 3.8 2.4 3.2 612.86
EXCAVATION FOR FOOTING 6 m3 1 4.6 6.53 3.2 96.12
EXCAVATION FOR FOOTING 7 m3 9 2.2 2.2 3.2 139.39
EXCAVATION FOR FOOTING 8 m3 2 3.3 4 3.2 84.48
EXCAVATION FOR FOOTING 9 m3 1 3 3 3.2 28.80
EXCAVATION FOR FOOTING 10 m3 6 2.6 2.6 3.2 129.79
EXCAVATION FOR FOOTING 11 m3 2 4.6 3.4 3.2 100.10
EXCAVATION FOR FOOTING 12 m3 1 11.21 17.53 3.2 628.84
EXCAVATION FOR FOOTING 13 m3 1 10.85 14.13 3.2 490.59
TOTAL m3 10,683.20
EARTHWORKS BILL 2
Page 4/BILL 2
EXCAVATION FOR SOLID BLOCKWALL m3 720 1 3 2,160.00
0.00
3
EXCAVATION FOR CHIMNEY FOUNDATION m 4 4 1.7 27.20
0.00
3
EXCAVATION FOR RETAINING WALL m 205 3 3.2 1,968.00
0.00
EXCAVATION FOR WALL FOOTING m3 387 1.8 0.6 417.96
0.00
EXCAVATION FOR GARDE SLAB m3 114.5 114.5 0.4 5,244.10
0.00
3
EXCAVATION FOR RAMP SLAB, BASE SLAB AND WALL m 257 9 2.1 4,857.30
PROPOSED FILM PACKAGING INDUSTRIAL AND RESIDENTIAL DEVELOPMENT
ON PLOT No IJC 354 (OG). UTM(ZONE 31), OGUN STATE, NIGERIA, SOUTH AFRICA
FOR FLEX FILMS AFRICA PVT. LIMITED
TOTAL m3 27,023.36
2 BACKFILLING
TRANSFORMER PADS
1 EXCAVATION m3 2 25.13 0.9 45.23
2 BACKFILLING m3
2 BACKFILLING m3
30,978.32
EARTHWORKS BILL 2
Page 5/BILL 2
BILL-3 CONCRETE WORKS
Grade of concrete for superstructure to be S-30/20 with minimum cement content 370kg/m3
with minimum cube crushing strength of 30N/mm2 after 28days.
Grade of concrete for substructure to be S-30/20 with minimum S.R. cement content
370kg/m3 with minimum cube crushing strength of 30N/mm2 after 28days.
Grade of concrete for PCC(blinding) to be S-20/20 with minimum cement content 300kg/m3
To include curing and concrete third part test.
SILO FOUNDATION
1 PCC BELOW CAST PIT BASE SLAB m3 49.3 12.4 0.1 61.13
2 RCC MACHINE FOUNDATION m3 48.9 12 1.25 733.50
SUB-STATION
1 PCC -1 m3 11 2.6 1.8 0.1 5.15
CONCRET WORK BILL 3
Page 4/B3
PCC -2 m3 15 2.2 1.80 0.10 5.94
PCC -1 m3 2 3 1.80 0.10 1.08
PCC BELOW RAMP BEAM m3 28.095 0.60 0.10 1.69
PCC BELOW SOLID BLOCKWALL m3 59 0.60 0.10 3.54
PCC BELOW TRENCH BASE SLAB m3 130.061 2.00 0.10 26.01
TOTAL m3 43.41
12 200mm THICK GRADE SLAB, A 252 DOUBLE MESH m3 320.00 0.20 64.00
TFH FOUNDATION
1 PCC m3 2 7.4 6.40 0.10 9.47
2 RCC MACHINE FOUNDATION m3 2 7 6.00 0.50 42.00
RECYCLING FOUNDATION
1 PCC m3 15.92 4.40 0.10 7.00
0.00
3
2 RCC MACHINE FOUNDATION m 15.52 4.00 0.50 31.04
HT/LT PANEL
1 PCC FOR FOOTING m3 4 2.2 1.60 0.10 1.41
PCC FOR SOLID BLOCKWALL m3 28 0.60 0.10 1.68
TOTAL m3 3.09
MAIN FACTORY
1 PCC 1 m3 73 5.2 4.00 0.10 151.84
PCC 2 m3 28 2.4 2.00 0.10 13.44
PCC 3 m3 31 3.2 2.00 0.10 19.84
PCC 4 m3 12 3.4 2.40 0.10 9.79
PCC 5 m3 16 3.2 1.80 0.10 9.22
PCC 6 m3 1 5.93 4.00 0.10 2.37
PCC 7 m3 9 1.6 1.60 0.10 2.30
PCC 8 m3 2 3.4 2.70 0.10 1.84
PCC 9 m3 1 2.4 2.40 0.10 0.58
PCC 10 m3 3 2 2.00 0.10 1.20
PCC 11 m3 2 4 2.80 0.10 2.24
PCC 12 m3 1 16.93 10.61 0.10 17.96
PCC 13 m3 1 13.53 10.25 0.10 13.87
PCC BELOW SOLID BLOCKWALL m3 720 0.60 0.10 43.20
PCC BELOW RETAINING WALL BASE m3 203.92 2.40 0.10 48.94
PCC BELOW RAMP BASE SLAB m3 110.4 1.23 0.10 13.58
PCC BELOW RAMP STAIRCASE BASE SLAB m3 32 1.20 0.10 3.84
12 STAIRCASE
LANDING m3 11 1.5 1.20 0.20 3.96
WAIST SLAB m3 11 1.7 1.20 0.20 4.49
TREAD AND RISER m3 22 1.2 0.20 0.30 1.58
TOTAL m3 10.03
STAIRCASE BASE SLAB m3 22 1.2 0.80 0.30 6.34
STAIIRCASE WALL m3 22 1.2 0.20 1.20 6.34
STAIRCASE BEAM m3 11 1.2 0.20 0.60 1.58
TRANSFORMER PAD
1 PCC m3 2 16.42 0.20 6.57
0.00
2 RCC PAD m3 2 15.62 0.60 18.74
f SUB-STATION
FOOTINGS 40 50.00 2,000.00
PEDSATAL COLUMN 7 70.00 490.00
TIE BEAM 20 150.00 3,000.00
TRENCH BASE SLAB 65 75.00 4,875.00
TRENCH WALL 92 110.00 10,120.00
WALL FOOTING 8 70.00 560.00
COLUMN 11 110.00 1,210.00
ROOF BEAM 30 110.00 3,300.00
ROOF SLAB 120 135.00 16,200.00
PARAPET WALL 11 60.00 660.00
200mm THICK GRADE SLAB, A 252 DOUBLE MESH 2 325 3.95 2,567.50
TOTAL 44,982.50
g SLITTER MACHINE
RCC MACHINE FOUNDATION 90 75.00 6,750.00
TFH FOUNDATION
h RCC MACHINE FOUNDATION 45 75.00 3,375.00
I TUT FOUNDATION
RCC MACHINE FOUNDATION 180 75.00 13,500.00
TRENCH BASE SLAB 55 75.00 4,125.00
TRENCH WALL 20 110.00 2,200.00
TRENCH COVER SLAB 36 75.00 2,700.00
CONCRET WORK BILL 3
Page 10/B3
TOTAL 22,525.00
j RECYCLING FOUNDATION
RCC MACHINE FOUNDATION 32 75.00 2,400.00
k HT/LT PANEL
FOOTING 4 50.00 200.00
PEDASTAL COLUMN 1 70.00 70.00
TIE BEAM 3.5 150.00 525.00
COLUMN 1.1 110.00 121.00
ROOF BEAM 5.2 110.00 572.00
PARAPET WALL 3 60.00 180.00
200mm THICK GRADE SLAB 2 50 3.95 395.00
ROOF SLAB 11 135.00 1,485.00
TOTAL 3,548.00
l MAIN FACTORY
FOOTING 1140 50 57,000.00
PEDASTAL COLUMN 360 70 25,200.00
TIE BEAM 221 150 33,150.00
WALL FOOTING 125 70.00 8,750.00
RETAINING BASE 165 75.00 12,375.00
RETAINING WALL 125 110.00 13,750.00
RAMP SLAB 410 75.00 30,750.00
RAMP WALL BASE SLAB 35 75.00 2,625.00
RAMP WALL 45 110.00 4,950.00
RAMP BEAM 14 150 2,100.00
RCC STAIRCASE LANDING, WAIST SLAB, TREAD AND RISER 11 130 1,430.00
STARIRCASE BASE SLAB 6.5 75.00 487.50
STARIRCASE WALL 6.5 110.00 715.00
STAIRCASE BEAM 2 150 300.00
PROPOSED FILM PACKAGING INDUSTRIAL AND RESIDENTIAL DEVELOPMENT
ON PLOT No IJC 354 (OG). UTM(ZONE 31), OGUN STATE, NIGERIA, SOUTH AFRICA
FOR FLEX FILMS AFRICA PVT. LIMITED
m TRANSFORMER PAD
RCC PAD 19 75.00 1,425.00
q ILC PIT
PIT BASE SLAB 4.3 75.00 322.50
r METALLIZER PIT
PIT BASE SLAB 40 75.00 3,000.00
PIT WALL 58 110.00 6,380.00
TOTAL 9,380.00
s RECYCLING PIT
PIT BASE SLAB 131 75.00 9,825.00
PIT WALL 156 110.00 17,160.00
BEAM 14 150 2,100.00
COLUMN 2.2 150 330.00
TOP COVER SLAB 64 75.00 4,800.00
STAIRCASE LANDING, WAIST SLAB, TREAD&RISER 4.5 130 585.00
TOTAL 34,800.00
RMS PIT
PIT BASE SLAB 53 75.00 3,975.00
PIT WALL 67 110.00 7,370.00
BEAM 8.2 150 1,230.00
TOP COVER SLAB 22 150 3,300.00
STAIRCASE, WAIST SLAB, TREAD&RISER 2 130 260.00
TOTAL 16,135.00
SUB-STATION
1 230mm THICK SOLID BLOCKWALL m2 118 2.50 295.00
2
2 230mm THICK EXTERNAL HOLLOW BLOCKWALL m 118 4.20 495.60
0.00
2
3 230mm THICK INTERNAL HOLLOW BLOCKWALL m 81 4.20 340.20
MAIN FACTORY
HT/LT PANEL
1 230mm THICK SOLID BLOCKWALL m2 28 2.40 67.20
0.00
2 230mm THICK EXTERNAL HOLLOW BLOCKWALL m2 28 3.00 84.00
BLOCKWORK BILL 5
Page 6/B5
BILL 6 FINISHES
1 PAINTING
a INTERNAL WALL – 5 coats of emulsion m2 199 4.80 955.20
HT/LT PANEL
1 PLASTER
a 20mm THICK EXTERNAL PLASTER m2 84.00
PAINTING
a EXTERNAL WALL – Proprietary Jotashield paint m2 2 28 3.60 201.60
b CEILING– 5 coats of emulsion m2 8 6.00 48.00
MAIN FACTORY
1 PLASTER
a 20mm THICK EXTERNAL PLASTER m2 2 885.29 3.50 6,197.03
b 15mm THICK EXTERNAL PLASTER m2 2 1035 3.50 7,245.00
0.00
2 PAINTING 0.00
a EXTERNAL – RUSH TYROLENE PAINT ON PLASTERED SURFACE m2 2 885.29 3.50 6,197.03
b 5 COAT OF EMULSION ON INTERNAL PLASTERED WALL m2 2 1035 3.50 7,245.00
FLOORING
1 CERAMIC TILE – PASSAGE m2 123.34 3.00 370.02
CERAMIC TILE – FIRST AID ROOM m2 7.77 4.00 31.08
CERAMIC TILE – SAMPLE ROOM m2 7.77 8.27 64.26
CERAMIC TILE – LABORATORY m2 15.77 8.27 130.42
CERAMIC TILE – CHANGING ROOM m2 5 3.00 15.00
CERAMIC TILE – SLITTER TRIM ROOM m2 7.77 8.27 64.26
CERAMIC TILE – PRODUCTION PLANNING MEETING ROOM m2 12.54 8.30 104.08
CERAMIC TILE – PLANT OFFICE ROOM m2 15.77 8.30 130.89
CERAMIC TILE – MET OFFICE m2 8.3 7.80 64.74
CERAMIC TILE – ENGG OFFICE ROOM m2 7.8 2.20 17.16
CERAMIC TILE – OFFICE FOR TFH ROOM m2 4 3.00 12.00
CERAMIC TILE – TECH SUPERVISOR ROOM m2 4 3.00 12.00
CERAMIC TILE – TDO OFFICE ROOM m2 4 3.00 12.00
TOTAL 1,027.91
FINISHES BILL 6
Page 7/B6
2 GRANITI TILE – TRAINING HALL m2 15.54 7.80 121.21
0.00
3 400MICRON EPOXY FINISH 0.00
MDO- PUMP ROOM m2 31.8 8.30 263.94
COATING AND DRUM STORAGE ROOM m2 2 8.3 7.80 129.48
PAPER CORE STORE m2 31.8 8.30 263.94
MET WIRE STORE m2 8.3 7.80 64.74
FILTER ROOM m2 15.04 11.80 177.47
EXTRUDED DIE AREA m2 36.17 16.00 578.72
MDO AREA m2 28.6 14.50 414.70
JUMBO STAND m2 22 12.00 264.00
PRIMARY SLITTER m2 14.9 14.50 216.05
FEEDING AREA m2 31.8 40.80 1,297.44
METALIZER AREA m2 16 19.50 312.00
SLITTER AREA m2 33.9 20.80 705.12
RECYCLING AREA m2 23.8 20.80 495.04
PACKING AREA m2 15.8 20.70 327.06
MECH ROOM m2 20.8 7.80 162.24
TFH AREA m2 20.8 15.80 328.64
ENGG AREA m2 20.8 16.00 332.80
TOTAL m2 6,333.38
4 WALL TILE
CERAMIC TILE – RECYCLING ROOM m2 89.2 2.40 214.08
CERAMIC TILE – SAMPLE ROOM m2 32.2 2.40 77.28
CERAMIC TILE – LABORATORY m2 48.2 2.40 115.68
CERAMIC TILE – TOILET m2 2 36 2.40 172.80
CERAMIC TILE – CHANGING ROOM m2 16 2.40 38.40
TOTAL 618.24
5 CEILING
a 600 x 600 GYPSUM BOARD EXPOSED FALSE CEILING
PASSAGE m2 370.02
FIRST AID ROOM m2 31.08
TRAINING ROOM m2 121.21
SAMPLE ROOM m2 64.26
LABORATORY m2 130.42
CHANGING ROOM m2 64.00
TOILET ROOM m2 2 5.3 5.80 61.48
SLITTER TRIM ROOM m2 64.26
PRODUCTION PLANNING MEETING ROOM m2 104.08
PLANT OFFICE ROOM m2 130.89
PROPOSED FILM PACKAGING INDUSTRIAL AND RESIDENTIAL DEVELOPMENT
ON PLOT No IJC 354 (OG). UTM(ZONE 31), OGUN STATE, NIGERIA, SOUTH AFRICA
FOR FLEX FILMS AFRICA PVT. LIMITED
FINISHES BILL 6
Page 15/B6
BILL 7 WATERPROOFING WORKS
SILO FOUNDATION
1 1000 G POLYTHENE SHEET m2 0.00
Two layers shall be laid below all concrete works cast directly in contact with soil for
substructure works.
All RCC works and substructure blockwork which comes directly in contact with soil shall be
waterproofed with two coats of cold bitumen paint Nitopruf 10 or equivalent.
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
Item
1 CONTRACTOR'S PRELIMINARIES
Item
2 INSURANCES
4 MOBILISATION Item
5 DEMOBILISATION Item
PRELIMINARIES BILL 1
Page 1 BILL 1
BILL 2 EARTHWORKS
structure can be included depending upon the depths. Excess soil shall be carted away.
1 EXCAVATION:
a FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL m3
2 BACKFILLING:
compaction not be less than 98% of MDD m3
3 SURPLUS SOIL TO BE CART AWAY FROM SITE FOR PLOT LEVELLING. m3 97.15 26.461 3.3 8,483.26
5 ANTI-TERMITE TREATMENT m2
Anti-termite treatment shall be carried out on soil prior to commencing any concrete work.
CHIMNEY FOUNDATION
1 EXCAVATION
2 BACKFILLING:
2 BACKFILLING: m3
COOLING TOWER/RADIATOR
1 EXCAVATION m3
EARTHWORKS BILL 2
Page 2/BILL 2
2 BACKFILLING: m3
COOLING TOWER/RADIATOR
1 EXCAVATION m3 17 8 2.3 312.80
2 BACKFILLING: m3
4 ANTI-TERMITE TREATMENT m2
HRU/VAM FOUNDATION
1 EXCAVATION m3 2 6 6 0.8 57.60
2 BACKFILLING: m3
2 BACKFILLING: m 3
EARTHWORKS BILL 2
Page 3/BILL 2
e SUPERSTRUCTURE COLUMN m 3
4 0.4 0.23 3.5 1.29
h MACHINE FOUNDATION – 1 m 3
100.86 0.5 50.43
MACHINE FOUNDATION – 2 m3 12.5 0.35 4.38
TOTAL m3 54.81
r STIFFENER COLUMN m 3
30 0.2 0.4 6 14.40
CHIMNEY FOUNDATION
1 PCC m3 2 19.36 0.1 3.87
0.00
2 RCC CHIMNEY FOUNDATION m3 2 16 1.5 48.00
COOLING TOWER
1 PCC m3 21.4 5.4 0.1 11.56
0.00
2 RCC MACHINE FOUNDATION m3 21 5 0.5 52.50
0.00
3 RCC WALL m3 49.6 0.3 3.1 46.13
0.00
4 RCC COVER SLAB m 3
20.4 4.4 0.3 26.93
COOLING TOWER/RADIATOR
1 PCC m3 16.4 7.4 0.1 12.14
0.00
2 RCC MACHINE FOUNDATION m 3
16 7 0.5 56.00
0.00
3 RCC WALL m 3
43.6 0.3 1.6 20.93
0.00
4 TOP COVER SLAB m 3
15.4 6.4 0.3 29.57
HRU/VAM FOUNDATION
1 PCC m3 2 5.4 5.4 0.1 5.83
0.00
2 RCC MACHINE FOUNDATION m3 2 5 5 0.5 25.00
1 STEEL GRATING m2
METAL WORKS BILL 4
Page 4/B4
2 HOLLOW BLOCKWORK
a 230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR SUPERSTRUCTURE m2 24.06 3.30 79.40
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION 1 m2 215.01
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION 2 m2 75.38
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION 3 m2 283.53
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION 4 m2 302.65
TOTAL 955.97
BLOCKWORK BILL 5
Page 5/B5
BILL 6 FINISHES
1 PLASTER
plaster at the junction of RCC members and block walls.
a 20mm THICK EXTERNAL PLASTER m2 651
2 Painting
a EXTERNAL WALL – RUSH TYROLEAN PAINT m2 2 1,000.00 2,000.00
b INTERNAL PAINT – 5 COAT OF EMULSION PAINT m2 2 680.00 1,360.00
3 FLOORING
a ACID PROOF TILES m2 25.00 15.00 375.00
b ANTI SLIP CERAMIC TILE – TOILET m2 5.60 5.00 28.00
c SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – VAMS m2 25.00 16.50 412.50
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – POWER PLANT m2 27.50 25.00 687.50
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – HT/LT PANEL m2 25.00 12.50 312.50
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – FUEL TREATMENT m2 10.00 9.54 95.40
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – STORE ROOM m2 12.50 4.97 62.13
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – CONTROL ROOM m2 19.80 9.40 186.12
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – TANK FARM m2 10.00 9.54 95.40
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – RAMP m2 516.00
TOTAL m2 2,367.55
4 CEILING
a VINYL FACED & ALUMINIUM BACK 600mm x 600mm GYPSUM TILE ON EXPOSED GRID
CONTROL ROOM m2 186.12
TOILET ROOM m2 28.00
TOTAL 214.12
5 SKIRTING
CERAMIC TILE m 80.00
FINISHES BILL 6
Page 6/B6
3 DPC LAYER m2 28
230mm wide DPC above tie beam for all blockworks.
4 25MM THICK FLEXCELL SHEET BETWEEN TWO COLUMNS FOR EVERY 16M C/C. m2
COOLING TOWER
1 1000 G POLYTHENE SHEET m2
COOLING TOWER/RADIATOR
1 1000 G POLYTHENE SHEET m2
HRU/VAM FOUNDATION
1 1000 G POLYTHENE SHEET m2
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
Item
1 CONTRACTOR'S PRELIMINARIES
Item
2 INSURANCES
4 MOBILISATION Item
5 DEMOBILISATION Item
PRELIMINARIES BILL 1
Page 1 BILL 1
BILL 2 EARTHWORKS
structure can be included depending upon the depths. Excess soil shall be carted away.
1 EXCAVATION:
a FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL
EXCAVATION FOR RAFT m3 731 2.8 2,046.80
2 BACKFILLING:
compaction not be less than 98% of MDD m3
5 ANTI-TERMITE TREATMENT m2
Anti-termite treatment shall be carried out on soil prior to commencing any concrete work.
c' COLUMN FROM GROUND TO FIRST FLOOR, C1 m3 3 0.35 0.9 5.25 4.96
COLUMN FROM GROUND TO FIRST FLOOR, C2 m3 3 0.3 0.7 5.25 3.31
COLUMN FROM GROUND TO FIRST FLOOR, C3 m3 10 0.3 0.8 5.25 12.60
COLUMN FROM GROUND TO FIRST FLOOR, C4 m3 5 0.3 0.6 5.25 4.73
COLUMN FROM GROUND TO FIRST FLOOR, C5 m3 5 0.35 0.9 5.25 8.27
COLUMN FROM GROUND TO FIRST FLOOR, C6 m3 1 0.3 0.7 5.25 1.10
TOTAL 34.97
c' COLUMN FROM FIRST TO SECOND FLOOR, C1 m3 3 0.35 0.9 3.6 3.40
COLUMN FROM FIRST TO SECOND FLOOR, C1 m3 3 0.3 0.7 3.6 2.27
COLUMN FROM FIRST TO SECOND FLOOR, C1 m3 10 0.3 0.8 3.6 8.64
COLUMN FROM FIRST TO SECOND FLOOR, C1 m3 5 0.3 0.6 3.6 3.24
COLUMN FROM FIRST TO SECOND FLOOR, C1 m3 5 0.35 0.9 3.6 5.67
COLUMN FROM FIRST TO SECOND FLOOR, C1 m3 1 0.3 0.7 3.6 0.76
TOTAL 23.98
c' COLUMN FROM SECOND TO ROOF SLAB, C1 m3 3 0.35 0.9 3.9 3.69
COLUMN FROM SECOND TO ROOF SLAB, C2 m3 3 0.3 0.7 3.9 2.46
COLUMN FROM SECOND TO ROOF SLAB, C3 m3 10 0.3 0.8 3.9 9.36
COLUMN FROM SECOND TO ROOF SLAB, C4 m3 5 0.3 0.6 3.9 3.51
COLUMN FROM SECOND TO ROOF SLAB, C5 m3 5 0.35 0.9 3.9 6.14
COLUMN FROM SECOND TO ROOF SLAB, C6 m3 1 0.3 0.7 3.9 0.82
TOTAL 25.97
f BEAMS
FIRST FLOOR BEAM 1 m3 31.5 0.23 0.6 4.35
FIRST FLOOR BEAM 2 m3 18.5 0.23 0.6 2.55
FIRST FLOOR BEAM 3 m3 9 0.23 0.6 1.24
FIRST FLOOR BEAM 4 m3 36 0.23 0.6 4.97
FIRST FLOOR BEAM 5 m3 24 0.23 0.6 3.31
FIRST FLOOR BEAM 6 m3 65 0.2 0.7 9.10
FIRST FLOOR BEAM 7 m3 10 0.23 0.6 1.38
FIRST FLOOR BEAM 8 m3 22.5 0.23 0.6 3.11
TOTAL 30.01
g RCC SLAB
180mm THICK SLAB FIRST FLOOR m3 525 0.18 94.50
180mm THICK SLAB SECOND FLOOR m3 525 0.18 94.50
180mm THICK SLAB ROOF SLAB m3 525 0.18 94.50
180mm THICK SLAB UPPER ROOF SLAB m3 39 0.15 5.85
TOTAL
r 100mm THICK RAMP SLAB, A-142 MESH SINGLE LAYER m2 2.6 1.3 0.1 0.34
r ANTI-TERMITE TREATMENT m2
u DPC LAYER m2
x REINFORCEMENT QUANTITY m3 Kg
RAFT Kg 330.00 75.00 24,750.00
PEDESTAL COLUMN Kg 15 70.00 1,050.00
SUB-STRUCTURE RCC WALL Kg 50 100.00 5,000.00
LIFT PIT RAFT Kg 7 75.00 525.00
200mm THCIK RCC LIFT WALL Kg 38 100.00 3,800.00
230mm THCIK RCC STAIRCASE WALL Kg 150 100.00 15,000.00
TIE BEAM Kg 15 150.00 2,250.00
WALL FOOTING Kg 11 70.00 770.00
SUPERSTRUCTURE COLUMNS:
GROUND TO FIRST FLOOR Kg 35 150.00 5,250.00
FIRST TO SECOND FLOOR Kg 25 150.00 3,750.00
SECOND TO ROOF FLOOR Kg 28 150.00 4,200.00
BEAMS
FIRST FLOOR BEAMS Kg 30 150.00 4,500.00
SECOND FLOOR BEAMS Kg 30 150.00 4,500.00
ROOF BEAMS Kg 30 150.00 4,500.00
RCC SLABS:
100mm THICK RCC GRADE SLAB, BRC A-142 MESH SINGLE LAYER Kg 530 2.22 1,176.60
FIRST FLOOR SLAB Kg 95 135.00 12,825.00
SECOND FLOOR SLAB Kg 95 135.00 12,825.00
ROOF SLAB Kg 95 135.00 12,825.00
UPPER ROOF SLAB Kg 6 125.00 750.00
PARAPET WALL Kg 28
STAIRCASE ( landing&waist slab, tread&riser) Kg 30
RAMP SLAB Kg 9
2 HOLLOW BLOCKWORK
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION A m2 267.10
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION B m2 341.71
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION C m2 288.60
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION D m2 344.11
TOTAL 1,241.52
230MM THICK INTERNAL HOLLOW BLOCK GROUND FLOOR m2 72.00 5.00 360.00
230MM THICK INTERNAL HOLLOW BLOCK FIRST FLOOR m2 337.88 3.60 1,216.37
TOTAL 1,576.37
100MM THICK INTERNAL HOLLOW BLOCK GROUND FLOOR m2 23.60 5.00 118.00
100MM THICK INTERNAL HOLLOW BLOCK GROUND FLOOR m2 59.00 3.60 212.40
TOTAL 330.40
BLOCKWORK BILL 5
Page 5/B5
BILL 6 FINISHES
1 PLASTER
plaster at the junction of RCC members and block walls.
a 20mm THICK EXTERNAL PLASTER m2
0.00
b 15mm THICK INTERNAL PLASTER m2
2 PAINTING
a EXTERNAL WALL – RUSH TYROLEAN PAINT m2
b INTERNAL PAINT – 5 COAT OF EMULSION PAINT ON WALLS m2
c INTERNAL PAINT – 5 COAT OF EMULSION PAINT ON CEILING m2
TOILET
3 WALL TILE
GRANITE TILE – LIFT WALL m2 12.50 2.86 35.75
GRANITE TILE – ENTRANCE LOBBY m2 3 15.62 5.00 234.30
TOTAL 270.05
GLAZED CERAMIC TILE – KITCHEN m2 26.06 3.00 78.18
GLAZED CERAMIC TILE – DINNING m2 37.46 3.00 112.38
GLAZED CERAMIC TILE – STORE m2 20.40 3.00 61.20
GLAZED CERAMIC TILE – TOILET m2 170.00 3.00 510.00
TOTAL 761.76
3 FLOORING
GRANITI TILE – ENTANCE LOBBY m2 79.75
GRANITI TILE – PASSAGE m2 160.00
GRANITI TILE – GYMNASIUM, CLUB HOUSE m2 218.00
GRANITI TILE – STUDIOS m2 639.62
TOTAL 1,097.37
ANTI-SLIP CERAMIC TILE – KITCHEN, DINNING, STORE m2 153.61
ANTI-SLIP CERAMIC TILE – TOILETS m2 147.97
TOTAL 301.57
4 FALSE CEILING
a PASSAGE m2
TOILETS m2
TOTAL
DECORATIVE GYPSUM FALSE CEILING – STAIRCASE m2
5 SKIRTING
TERRAZO – TILE Rm
CERAMIC TILE – SERVANT ROOM Rm
FINISHES BILL 6
Page 6/B6
3 DPC LAYER m2
230mm wide DPC above tie beam for all blockworks.
4 25MM THICK FLEXCELL SHEET BETWEEN TWO COLUMNS FOR EVERY 16M C/C. m2
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
Item
1 CONTRACTOR'S PRELIMINARIES
Item
2 INSURANCES
4 MOBILISATION Item
5 DEMOBILISATION Item
PRELIMINARIES BILL 1
Page 1 BILL 1
BILL 2 EARTHWORKS
structure can be included depending upon the depths. Excess soil shall be carted away.
1 EXCAVATION:
a FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL
EXCAVATION FOR RAFT m3 631 5.5 3,470.50
2 BACKFILLING:
compaction not be less than 98% of MDD m3
5 ANTI-TERMITE TREATMENT m2
Anti-termite treatment shall be carried out on soil prior to commencing any concrete work.
2
a 500mm THICK RCC RAFT m3 622 0.5 311.00
600mm THICK RCC RAFT m3 18 0.1 1.80
TOTAL 312.80
c RCC WALL
400mm THICK RCC WALL m3 54 0.4 4.65 100.44
300mm THICK RCC WALL m3 47 0.3 4.65 65.57
300mm THICK RCC WALL m3 16.28 0.3 1.5 7.33
TOTAL 72.89
e BEAM
GROUND BEAM 1 m3 27 0.23 0.6 3.73
GROUND BEAM 2 m3 1.67 0.23 0.6 0.23
GROUND BEAM 3 m3 10 0.4 0.6 2.40
GROUND BEAM 4 m3 8 0.23 0.6 1.10
GROUND BEAM 5 m3 7.1 0.23 0.45 0.73
GROUND BEAM 6 m3 12.32 0.23 0.8 2.27
GROUND BEAM 7 m3 19.29 0.23 0.6 2.66
GROUND BEAM 8 m3 4.56 0.23 0.6 0.63
TOTAL 13.75
f GRADE SLAB
100mm THICK GROUND SLAB m3 m2 178
100mm THICK LOWER GROUND SLAB m3 m2 509
TOTAL 687.00
g SLAB
GROUND FLOOR SLAB – S1 m3 143 0.18 25.74
GROUND FLOOR SLAB – S2 m3 35 0.18 6.30
GROUND FLOOR SLAB – SS1 m3 13 0.18 2.34
GROUND FLOOR SLAB – SS2 m3 19 0.18 3.42
GROUND FLOOR SLAB – CS1 AND CS2 m3 31 0.2 6.20
TOTAL 44.00
j LIFT
230mm THICK RCC WALL m3 9.6 0.23 23 50.78
0.00
k STAIRCASE – 1 0.00
STAIRCASE BEAM m3 3.5 0.2 0.65 0.46
STAIRCASE LANDING m3 10 2.8 2.25 0.2 12.60
0.00
0.00
STAIRCASE WAIST SLAB m3 10 4.1 1.35 0.2 11.07
STAIRCASE TREAD AND RISER m3 46 1.35 0.3 0.15 2.79
TOTAL 26.46
2 HOLLOW BLOCKWORK
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION 1 m2 370.00
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION 2 m2 330.00
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION 3 m2 505.00
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION 4 m2 345.00
TOTAL 1,550.00
230MM THICK INTERNAL HOLLOW BLOCK GROUND TO THIRD FLOOR m2 4 248.47 993.89
230MM THICK INTERNAL HOLLOW BLOCK ROOF FLOOR m2 14.18 3.65 51.76
TOTAL 1,045.65
100MM THICK INTERNAL HOLLOW BLOCK GROUND TO THIRD FLOOR m2 4 67.86 3.65 990.76
BLOCKWORK BILL 5
Page 5/B5
BILL 6 FINISHES
1 PLASTER
plaster at the junction of RCC members and block walls.
a 20mm THICK EXTERNAL PLASTER m2 2 1,550.00 3,100.00
0.00
b 15mm THICK INTERNAL PLASTER m2 0.00
2 Painting
a EXTERNAL WALL – RUSH TYROLEAN PAINT E1 m2 0.00
EXTERNAL WALL – RUSH TYROLEAN PAINT E2 m2
EXTERNAL WALL – RUSH TYROLEAN PAINT E3 m2
EXTERNAL WALL – RUSH TYROLEAN PAINT E4 m2
b INTERNAL PAINT – 5 COAT OF EMULSION PAINT ON WALLS m2 0.00
c INTERNAL PAINT – 5 COAT OF EMULSION PAINT ON CEILING m2 0.00
TOILET 0.00
3 FLOORING
NATURAL GRANITE – ENTRANCE LOBBY m2 5.86 2.00 11.72
GRANITE/MARBLE TILE – LIFT AND ENTRANCE LOBBY m2 4 6.53 3.40 88.81
GRANITE/MARBLE TILE – CORRIDOR m2 4 9.60 3.60 138.24
TOTAL 227.05
TERRAZO TILE – STAIRCASE m2 20 2.80 1.65 92.40
TERRAZO TILE – TERRACE m2 514.00
TOTAL 606.40
GRANITI TILE – LIVING/DINNING ROOM m2 8 7.40 5.77 341.58
GRANITI TILE – BEDROOM AND DRESS m2 4 140.82 563.29
GRANITI TILE – KITCHEN m2 8 4.33 4.00 138.56
GRANITI TILE – FLAT ENTRANCE LOBBY AND INTERNAL PASSAGE m2 4 29.00 116.00
GRANITI TILE – LIFT LOBBY AT TERRACE m2 6.30 3.40 21.42
TOTAL 1,180.85
ANTI-SLIP CERAMIC TILE – TOILET m2
4 40.00 160.00
ANTI-SLIP CERAMIC TILE – BALCONY m2 4 30.90 123.60
TOTAL 283.60
4 CEILING
CEILING PAINT – ENTRANCE LOBBY m2 11.72
CEILING PAINT – LIVING ROOM AND DINNING ROOM m2 341.58
CEILING PAINT – BED ROOM AND DRESS m2 563.29
TOTAL 916.59
DECORATIVE GYPSUM FALSE CEILING m2 4 6.53 3.40 88.81
600mm x 600mm CONCEALED GRID METALLIC FALSE CEILING – CORRIDOR m2 138.24
600mm x 600mm CONCEALED GRID METALLIC FALSE CEILING – KITCHEN m2 138.56
5 SKIRTING
TERRAZO TILE Rm 5 20.00 100.00
GRANITI TILE – LIVING ROOM/DINNING ROOM Rm 4 52.68 210.72
GRANITI TILE – BEDROOM AND DRESS Rm 4 56.32 225.28
GRANITI TILE – FLAT ENTRANCE LOBBY AND INTERNAL PASSAGE Rm 4 50.00 200.00
TOTAL 636.00
CERAMIC TILE – BALCONY Rm 4 47.20 188.80
FINISHES BILL 6
Page 6/B6
3 DPC LAYER m2
230mm wide DPC above tie beam for all blockworks.
4 25MM THICK FLEXCELL SHEET BETWEEN TWO COLUMNS FOR EVERY 16M C/C. m2
BILL 1: PRELIMINARIES
GENERAL AND PRELIMINARIES
Item
1 CONTRACTOR'S PRELIMINARIES
Item
2 INSURANCES
4 MOBILISATION Item
5 DEMOBILISATION Item
PRELIMINARIES BILL 1
Page 1 BILL 1
BILL 2 EARTHWORKS
structure can be included depending upon the depths. Excess soil shall be carted away.
1 EXCAVATION:
a FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL
EXCAVATION FOR FOOTING – 1 m3 5 4.6 2.6 3.2 191.36
EXCAVATION FOR FOOTING – 2 m3 7 4 3.2 3.2 286.72
EXCAVATION FOR FOOTING – 3 m3 2 5.6 3.6 3.2 129.02
EXCAVATION FOR FOOTING – 4 m3 1 3.6 3 3.2 34.56
EXCAVATION FOR FOOTING – 5 m3 1 4.4 3.6 3.2 50.69
EXCAVATION FOR FOOTING – 6 m3 2 6.8 4.2 3.2 182.78
EXCAVATION FOR EXTERNAL TIE BEAM AND SOLID BLOCKWALL m3 64.7 1 3.2 207.04
EXCAVATION FOR INTERNAL TIE BEAM m3 54.8 0.32 0.63 11.05
EXCAVATION FOR GRADE SLAB m3 273.0014 0.22 60.06
TOTAL 1,153.28
2 BACKFILLING:
compaction not be less than 98% of MDD m3
3 SURPLUS SOIL TO BE CART AWAY FROM SITE FOR PLOT LEVELLING. m3
5 ANTI-TERMITE TREATMENT m2
Anti-termite treatment shall be carried out on soil prior to commencing any concrete work.
EARTHWORKS BILL 2
Page 3/BILL 2
1' 100mm THICK PCC BELOW RAFT m3 19.75 17.12 0.1 33.81
100mm THICK PCC BELOW STAIRCASE AND RAMP BLOCKWALL m3 8 0.8 0.1 0.64
TOTAL 34.45
f BEAMS
FIRST FLOOR BEAM 1 AND 2 m3 70 0.23 0.6 9.66
FIRST FLOOR BEAM 3 m3 30 0.23 0.7 4.83
FIRST FLOOR BEAM 4 m3 6 0.4 0.8 1.92
FIRST FLOOR BEAM 5 m3 6 0.23 0.9 1.24
FIRST FLOOR BEAM 6 m3 7.5 0.23 0.4 0.69
TOTAL 18.34
SECOND FLOOR BEAMS m3 18.34
ROOF BEAMS m3 18.34
UPPER ROOF BEAMS m3 15.01 0.23 0.4 1.38
LANDING BEAM m3 18.3 0.23 0.4 1.68
g RCC SLAB
220mm THICK RCC GRADE SLAB m3 14.86 17.49 0.22 57.18
220mm THICK FIRST FLOOR SLAB m3 15.72 18.35 0.22 63.46
220mm THICK SECOND FLOOR SLAB m3 15.72 18.35 0.22 63.46
220mm THICK ROOF SLAB m3 15.72 18.35 0.22 63.46
150mm UPPER ROOF SLAB m3 4.66 3.76 0.15 2.63
r 100mm THICK RAMP SLAB, A-142 MESH SINGLE LAYER m2 2.6 1.3 0.1 0.34
2 HOLLOW BLOCKWORK
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION A m2 160.09
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION B m2 169.17
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION C m2 161.65
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION D m2 209.48
TOTAL 700.39
TOTAL
BLOCKWORK BILL 5
Page 5/B5
BILL 6 FINISHES
1 PLASTER
plaster at the junction of RCC members and block walls.
a 20mm THICK EXTERNAL PLASTER m2 2 710.00 1,420.00
0.00
b 15mm THICK INTERNAL PLASTER m2 2 455.00 910.00
2 PAINTING
a EXTERNAL WALL – RUSH TYROLEAN PAINT m2 2 800.00 1,600.00
b INTERNAL PAINT – 5 COAT OF EMULSION PAINT ON WALLS m2 2 455.00 910.00
c INTERNAL PAINT – 5 COAT OF EMULSION PAINT ON CEILING m2 3 263.32 789.96
TOILET 1,699.96
3 WALL TILE
CERAMIC TILE – TOILET m2 189.00 2.80 529.20
3 FLOORING
GRANITE TILE – PASSAGE m2 127.58
GRANITI TILE – SERVANT ROOM m2 407.00
ANTI-SLIP CERAMIC TILE – TOILETS m2 106.26
TERRAZZO TILE – TERRACE m2 300.00
4 FALSE CEILING
a PASSAGE m2 127.58
TOILETS m2 106.26
TOTAL 233.84
DECORATIVE GYPSUM FALSE CEILING – STAIRCASE m2 21.60
5 SKIRTING
TERRAZO – TILE Rm 91.38
CERAMIC TILE – SERVANT ROOM Rm 508.20
FINISHES BILL 6
Page 6/B6
3 DPC LAYER m2
230mm wide DPC above tie beam for all blockworks.
4 25MM THICK FLEXCELL SHEET BETWEEN TWO COLUMNS FOR EVERY 16M C/C. m2
4 MOBILISATION Item
5 DEMOBILISATION Item
PRELIMINARIES BILL 1
Page 1 BILL 1
BILL 2 EARTHWORKS
structure can be included depending upon the depths. Excess soil shall be carted away.
1 EXCAVATION:
a FROM EXISTING NATURAL GROUND LEVEL UPTO FOUNDATION LEVEL
EXCAVATION FOR RCC BASE SLAB m3 39.7 19.6 5.7 4,435.28
EXCAVATION FOR FOOTING – 2 m3 2.6 2.2 3.2 18.30
EXCAVATION FOR FOOTING – 3 m3 3 2.4 3.2 23.04
EXCAVATION FOR FOOTING – 4 m3 3.2 2.4 3.2 24.58
EXCAVATION FOR GARDE SLAB m3 69 0.3 20.70
EXCAVATION FOR TIE BEAM m3 21.57 0.83 0.5 8.95
TOTAL 4,530.86
2 BACKFILLING:
compaction not be less than 98% of MDD m3
5 ANTI-TERMITE TREATMENT m2
Anti-termite treatment shall be carried out on soil prior to commencing any concrete work.
ANTI-TERMITE TREATMENT BELOW RAFT m2 39.3 19.2 754.56
ANTI-TERMITE TREATMENT BELOW INTERLOCK m2 47.53 18.17 863.62
TOTAL 1,618.18
EARTHWORKS BILL 2
Page 3/BILL 2
d BEAM 1 m3
90 0.4 0.6 21.60
BEAM 2 m3 76.2 0.4 0.6 18.29
BEAM 3 m3 6.53 0.23 0.6 0.90
BEAM 5 m3 8.37 0.4 0.6 2.01
BEAM 7 m3 8.37 0.23 0.6 1.16
TOTAL 43.95
h PARAPET WALL m3
93.39 0.15 0.6 8.41
2 HOLLOW BLOCKWORK
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION A m2
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION B m2
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION C m2
230MM THICK EXTERNAL HOLLOW BLOCKWORK FOR ELEVATION D m2
TOTAL
TOTAL
BILL 6 FINISHES
1 PLASTER
plaster at the junction of RCC members and block walls.
a 20mm THICK EXTERNAL PLASTER m2 2 710.00 1,420.00
0.00
b 15mm THICK INTERNAL PLASTER m2 2 455.00 910.00
2 Painting
a EXTERNAL WALL – RUSH TYROLEAN PAINT m2 2 800.00 1,600.00
b INTERNAL PAINT – 5 COAT OF EMULSION PAINT ON WALLS m2 2 455.00 910.00
c INTERNAL PAINT – 5 COAT OF EMULSION PAINT ON CEILING m2 3 263.32 789.96
TOILET 1,699.96
3 FLOORING
a ACID PROOF TILES m2
b ANTI SLIP CERAMIC TILE – TOILET m2
c SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – VAMS m2
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – POWER PLANT m2
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – HT/LT PANEL m2
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – FUEL TREATMENT m2
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – STORE ROOM m2
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – CONTROL ROOM m2
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – TANK FARM m2
SMOOTH POWER FLOAT FINISH AND FLOOR HARDNER – RAMP m2
TOTAL m2
4 CEILING
a VINYL FACED & ALUMINIUM BACK 600mm x 600mm GYPSUM TILE ON EXPOSED GRID
CONTROL ROOM m2
TOILET ROOM m2
TOTAL
5 SKIRTING
CERAMIC TILE m
FINISHES BILL 6
Page 6/B6
3 DPC LAYER m2
230mm wide DPC above tie beam for all blockworks.
4 25MM THICK FLEXCELL SHEET BETWEEN TWO COLUMNS FOR EVERY 16M C/C. m2