Professional Documents
Culture Documents
WORK PROCEDURE
BY:
SUBJECT:
QA/QC ENGINEER
APPROVED BY:
EXCAVATION, EARTHWORK AND FILLING
QEHS MANAGER
ACTION VERIFY
1. SCOPE
2. PROCEDURE
.1 All excavation, earthwork and filling will be carried out in accordance with the
specification detailed in the project contract documentation. In any circumstances
where specifications are not provided or they are in any way incomplete, the
matter shall be referred back to consultant for additional information.
A method statement will be prepared and approved where deemed necessary, Project Manager Method
and may include: Statement
i) Site plan showing the location of spoil heaps for temporary storage
and if appropriate permanent storage area.
1. Liaise with all public utility companies e.g. water, electricity, telephone
sewerage and surface water etc. to ensure that all the available
information on the location of utilities and underground services through
and adjacent to the site of the excavation is obtained.
ii) Ensure that utilities and underground services are located on site
using markings, which are clearly visible. Ensure those plant operators Drawing/
Project Manager
and operatives involved with the activity are fully aware of the location of
the various utilities and underground services and their respective depths. N.O.C.
Project Engineer
iii) Where deemed necessary, excavate trial holes to establish the Markings
Project Engineer
precise location and depth of services.
Trial Holes
Site Engr./
iv) Plant operators must be aware of overhead cables. Use height
control indicators where necessary. Survey
Surveyor
.4 Site Survey and Grid of Levels Approval to
Project Manager
Tip
Prior to commencement of any excavation work, a level survey will be carried out
to confirm the information included on the contract drawings and to provide an
accurate record of existing ground levels for the calculation of quantities.
Prior to any surplus excavated material being removed from the site,
documentary evidence of “approval to tip” must be obtained beforehand from the
relevant government/municipal departments and the owner of the land where the
material is to be tipped.
.6 Adjoining Structures and Property