You are on page 1of 10

Computer-Aided Design ( ) –

Contents lists available at ScienceDirect

Computer-Aided Design
journal homepage: www.elsevier.com/locate/cad

Complex concrete structures


Merging existing casting techniques with digital fabrication
Ena Lloret a,∗ , Amir R. Shahab b , Mettler Linus b , Robert J. Flatt b , Fabio Gramazio a ,
Matthias Kohler a , Silke Langenberg a
a
Architecture and Digital Fabrication, ETH Zurich, Zurich, Switzerland
b
Institute of Building Materials, Civil Engineering Department, ETH Zurich, Switzerland

highlights
• An overview is given that combine existing casting techniques with digital fabrication for the fabrication of complex concrete structures.
• The focus is set on Smart Dynamic Casting a technique that combines digital fabrication with slipforming and building material science.
• An overview of the experimental set up and procedure is given.
• Experimental prototype results are described.

article info abstract


Keywords: Over the course of the 20th century, architectural construction has gone through intense innovation in
Complex concrete structures
its material, engineering and design, radically transforming the way buildings were and are conceived.
Casting techniques
Technological and industrial advances enabled and challenged architects, engineers and constructors
Formwork
Slipforming to build increasingly complex architectural structures from concrete. Computer-aided design and
Digital fabrication manufacturing (CAD/CAM) techniques have, more recently, rejuvenated and increased the possibilities
Smart Dynamic Casting of realizing ever more complex geometries. Reinforced concrete is often chosen for such structures as
almost any shape can be achieved when placed into a formwork. However, most complex forms generated
with these digital design tools bear little relation to the default modes of production used in concrete
construction today. A large gap has emerged between the possibilities offered by the digital technology
in architectural design and the reality of the building industry, where actually no efficient solutions
exist for the production of complex concrete structures. This paper presents construction methods that
unfold their full potential by linking digital design, additive fabrication and material properties and
hence allow accommodating the construction of complex concrete structures. The emphasis is set on
the on-going research project Smart Dynamic Casting (SDC) where advanced material design and robotic
fabrication are interconnected in the design and fabrication process of complex concrete structures. The
proposed fabrication process is belonging to an emerging architectural phenomenon defined first as
Digital Materiality by Gramazio & Kohler (2008) or more recently as Material Ecologies by Neri Oxman [1].
© 2014 Elsevier Ltd. All rights reserved.

1. Introduction the preferred materials for realizing all kinds of structures, simple
and complex.2 In 2011 alone, 3.4 billion tonnes of cement were
The technological development of reinforced concrete1 has produced to make concrete [5]. However, concrete itself is only
been one great enabler of modern architecture. It is still one of half the picture, since it is the formwork that determines what
is possible to build. It represents 35%–60% of the overall costs of

∗ Corresponding author. Tel.: +41 44 633 49 06; fax: +41 44 633 11 71.
E-mail addresses: lloret@arch.ethz.ch, ena3110@yahoo.com (E. Lloret). 2 ‘‘Complex geometries’’ in this text refers to a large number of distinct parts
1 In 1867 the invention of reinforced concrete changed this material into a fire- where little or no repetition occurs. Complex is not constrained to formal qualities
proof material, which could take both tensile and compressive loads. This invention but also have the intention of projects to be structurally optimized and unique in
has radically changed the way buildings have been conceived throughout the 20th direct contrast to industrial ‘standard’ projects. Complex was discussed in a similar
century. Further information on the topic in the book by [2]. Additional in [3]. way at the exhibition at Centre Pompidou, Paris by [4].

http://dx.doi.org/10.1016/j.cad.2014.02.011
0010-4485/© 2014 Elsevier Ltd. All rights reserved.
2 E. Lloret et al. / Computer-Aided Design ( ) –

concrete structures [6] and represents a significant source of waste, results are exemplified by Le Corbusier’s Domino system or the
given that all formwork is discarded sooner or later, contributing housing by Ernst May (1886–1970) in Praunheim, Germany [2].
to a generally increasing production of waste worldwide.3 The latter example helped laying the basis for prefabrication tech-
By integrating digital technologies and new insights from ma- niques adapted on a larger scale for housing in the 1950s [9].
terial science, well-established casting techniques could be modi- Taking full advantage of the prefabrication technology, the
fied to create formwork-efficient and waste reducing approaches architect Pier Luigi Nervi, mainly known for his innovations in
for the construction of complex concrete structures. This paper de- structural design [10], introduced what he named ‘‘structural
scribes construction techniques – static casting, concrete extrusion prefabrication’’ for the construction of a large number of differently
and slipforming – in a brief historical overview, to emphasize how shaped structural building elements.5 Structural prefabrication
they have influenced the way architecture is conceived today, and was the result of empirical studies, integrating material and
might impact its future by integrating digital design and fabrica- structural properties with fabrication logics. The system was
tion methods. In this context different ongoing research projects used for the construction of some dome structures for the 1960
are discussed, that represent the emerging change in architecture, Rome Olympics, including the spherical vault of the Sports Palace,
where artefacts evolve through interplay between the digital tool a structure composed of 19 different kinds of prefabricated
and physical material properties. elements [11].
The paper is divided into three parts. The first part gives Despite these early examples, the investigation of the archi-
an overview on standard static formwork systems as well as tectural potential of such innovative approaches towards struc-
on the current research, which aims to enhance its versatility ture and fabrication remained isolated phenomena. Resulting in
towards complex concrete forming by applying digital fabrication the fact that, most advances that occurred since the 1950s and up
techniques to traditional casting processes. The second part till today in prefabrication as well as in on-site construction with
presents ongoing research that applies computer-controlled layer concrete have mainly been directed towards more efficient and
based extrusion process with concrete for complex concrete rapid serial mass production of similar and standardized building
structures. The third part, the main subject of this paper, discusses components.
the well-established dynamic construction system, Slipforming
and introduces the pioneering fabrication method Smart Dynamic 2.2. Digital technology in conjunction with static formwork systems
Casting (SDC). SDC is a robotic slipforming process which exploits
the formability of concrete in the delicate period when it changes Rapid developments in CAD technology have in the last decades
from a soft to a hard material. This process is informed by augmented the design possibilities for geometrically complex con-
the physical properties of the material, which are tracked by crete structures. Such non-standard concrete elements are gener-
a feedback system during the production. In this process the ally produced by applying custom made inlays onto a standard
dynamic relationship of the formwork geometry, the robotic static formwork system. A pioneering example using this tech-
trajectory and the material properties directly determine. The nique is the Nationale-Nederlanden Building in Prague by Frank
aim of SDC is to investigate how the cost of forming complex Gehry [12], or more recently the Spencer Dock Bridge in Dublin
concrete elements could be reduced by eliminating the need for by Future Systems [13]. The formwork inlays needed to erect such
custom-made formwork, with the added value of opening up structures are generally fabricated by milling a homogeneous block
completely new and unexpected design possibilities. In addition of foam or wood into shape with a CNC router—a production
this fabrication method has the potential of becoming a low-waste method which allows almost any form to be made. Despite the
and ecologically sustainable construction technique for complex costs and energy consumption resulting from the extensive milling
concrete construction. process and the waste produced by their disposal after a single use,
this wasteful and expensive production process is until date the
2. Static formwork systems in conjunction with digital fabrica- most efficient technique for making custom formwork for concrete
tion constructions with complex geometries.
With regard to these problems, a number of companies and
2.1. Overview of static formwork systems research institutions have developed innovative approaches that
combine digital technology with static formwork systems, such as
The most common casting technique for concrete uses static those developed by PERI [14], a German producer of traditional
formwork systems.4 Static formwork refers to a temporary scaffolding systems; ADAPA6 a Danish spin off company for
structure into which fluid concrete is poured. After the concrete adaptive concrete construction; or TailorCrete, 7 a research project
has cured the formwork is removed. At the end of the 19th century of the Chair for Architecture and Digital Fabrication at ETH
and outset of the 20th century such formwork were custom made Zurich.
out of timber shuttering, supported by wooden frames which were PERI 8 has introduced a flexible mould system illustrated in
discarded after a single use. Fig. 1 which is ideal for the construction of single curved elements,
In order to increase the efficiency of such systems some of the beginning with a minimal radius of 1 m. The system applies a
first standardized, and thus reusable metal formworks were com- re-adjustable scaffold system onto which e.g. fibreboards, metal
mercially produced by 1910 for road construction [8]. Architects plates or plywood can be bent and attached in one direction. For
and engineers of the 1920s took advantage of these new modu- very low curvature, fibreboards can be bent in two directions.
lar formwork systems for concrete construction, both by applying This requires a lot of expertise and is complicated to execute.
them on the construction site as well as in prefabrication. Their

5 The invention of ‘‘ferror cementi’’ consisted of various layers of metal netting


3 According to a study from 2011, 80% of the total waste production is created in formed by small diameter (1 mm or less) steel wire, where mortar was pressed
into by using a trowel for the production of non-standard structural panels. The
the construction industry, of which 1.97% comes from the formwork timber. Further
invention is further described in the article [11].
details can be found in [7].
6 Also described at: www.adapa.dk. (Accessed on 26. 01. 2014.)
4 Examples for typical static forms in construction are: slab cast, jump-form,
7 For further information: http://dfab.arch.ethz.ch/web/d/forschung/164.html33.
wall forms or column forms. Depending on the application, these forms can be
constructed out of steel, wood or plastics, further description can be found in [6]. 8 For further information on PERI flexible formwork system [15].
E. Lloret et al. / Computer-Aided Design ( ) – 3

construction industry which limits its flexible mould catalogue


to single curvature structures, ADAPA, a recently started spin-
off company, limit its catalogue to non-structural double curved
panels. In contrast to these already available technologies Tailor
Crete, although it is an on-going research project that has not
yet reached industrial applicability, has the potential to raise the
productivity of the flexible mould by allowing a high throughput
of prefabricated reusable formwork inlays with complex geometry
and thus to reduce the cost price per element produced. Despite
the differences of the three projects, they all demonstrate how
contemporary digital technologies can integrate with century-
old techniques for the economically and ecologically sustainable
fabrication of complex concrete structures.

Fig. 1. Flexible formwork system from PERI© . 3. Concrete extrusion in conjunction with digital fabrication

3.1. Concrete extrusion


The system of PERI is applied for the construction of silos, water
tanks, pipes or recently for buildings such as ADAC Headquarters In a concrete extrusion process, still formable concrete is
in Munich, by Sauerbruch and Hutton, a building consisting of a continuously pressed through a die10 or nozzle of a predefined
curved 5-storey plinth with an 18-storey curved tower [16,15]. cross-section. The complexity of the produced elements depends
For the construction and planning of such geometries PERI has on the geometry of the used die. One of the first concrete
developed a software tool for architects and planners, which allows extruders was invented in 1884 and applied for the construction
to optimize a structure according to a feasible formwork division, of underground conduits [21].
hence a software which has the potential of influencing both Today concrete extrusion is used for both on-site production
the design and construction process in the early design phase.9 and prefabrication of concrete elements. Common examples here
Nonetheless the formwork system is limited to creating single are large scale pipe elements and pre-stressed elements such as
curvatures. hollow floor slabs [22]. For on-site construction this technique
Another system for a flexible formwork is developed by ADAPA. is extensively used for extrusion of curb stones and paving of
This system aims to efficiently prefabricate non-structural double- roads [23]. In a larger scale this technique has recently been
curved concrete façade panels. The flexible mould consists of reinvented for the construction of the twin-tube metro line in
a membrane that is supported and adjusted by CNC controlled Lyon [24], for which a tunnel boring machine (TBM), with an
actuators. The membrane is flexible enough to form smooth double circumference of ∼6.5 m extruded 300 mm thick steel-reinforced
curved shapes and stiff enough to avoid sagging between the concrete for the construction of a 350 m long tunnel. This in-situ
actuators under the load of the concrete. The concrete is first construction system could in future reduce the need for transport
poured on the planar surface—after it has cured for a while and production of prefabricated elements commonly used in the
the actuators deform the surface into the defined double curved tunnel construction.
geometry [18]. In summary, concrete extrusion is today mainly applied for pro-
To obtain optimal results and avoid cracks a precise timing ducing simple geometrical forms. The use of this technique for the
and control of the viscosity of the concrete is required. This poses production of complex concrete structures has only recently ex-
a major challenge to the fabrication system since it is difficult plored in research context through layer based extrusion systems.
to precisely quantify the precise time to shape due to the fact
that concrete hydration is sensitive to the smallest environmental 3.2. Digital technology in conjunction with extrusion systems
changes. Nonetheless this system demonstrates a high potential
for an integrated digital design and production technique for Only about one decade ago, architectural research projects
producing a large variation of double curved panel elements, began to combine concrete extrusion with digital fabrication
without the need for a custom formwork. techniques for the construction of complex concrete structures.
A similar approach is taken by the research project TailorCrete, Such approaches, which in principle correspond to scaling up a
for which a digitally controlled flexible mould was also developed. desktop 3D-printer to the size of a building, have nonetheless
But in difference to ADAPA this system aims for an in-situ transformed the mono layered extrusion process into a system
construction of double curved structural elements. Instead of that allows extruding multi-layered concrete elements in complex
casting the concrete directly on the mould, TailorCrete uses the geometrical shapes.
flexible mould to cast recyclable double-curved formwork inlays One of the pioneers of this system is Prof. Behrokh Khoshnevis
made of wax. These wax inlays are subsequently brought on from the University of Southern California, whose project Contour
site and applied onto a standard static formwork system. This Crafting [25] uses a digitally controlled die which extrudes a
innovative system for the construction of complex double-curved rather dry cementitious material against trowels in layers of about
concrete structures combines the advantages of standardized 10 cm. The system is constrained by the fact that the deposited
modular in-situ formwork technology with the efficient and material must harden enough to sustain the weight of the next
waste-free production of recyclable wax formwork inlays [19]. deposited layer. This creates a particular challenge on the bonding
The systems described are not exactly comparable. While of the layers, putting various constraints in terms of the size,
PERI is a leading supplier of formwork technologies for the height and geometrical freedom of the elements that can be

9 For further information [17], Peri software, ELPOS and PERI CAD for formwork and 10 Die is the term used in the extrusion industry. The term refers to shaping tool
scaffolding planning. which the material is forces through when it is still in a formable state [20].
4 E. Lloret et al. / Computer-Aided Design ( ) –

Fig. 2. Left, Peavey–Haglin experimental concrete grain elevator, St. Louis Park, 1908 [29,30]. Right: Manually driven slipform [31].

produced. Nevertheless, this technique has succeeded in producing slipforming is mostly applied for the construction of tower cores,
wall elements 2 m high with a width of 13.5 cm, at a speed of bridge piers, power plant cooling towers, chimney shafts, pylons,
approximately one square metre per hour [26–28]. the legs of oil-rig-platforms and structural facades of high-rise
A similar approach is taken in the project Free Form Construction buildings [6]. It is notably used to construct some of the tallest free
at the Construction Research Centre at Loughborough University. standing structures in the world, such as the CN Tower in Toronto,
However, unlike Contour Crafting, this research project applies a Canada, finished in 1974 [33] or more recently for the 245-m-high
wet concrete mixture in thinner layers ranging from 6 to 24 mm. core of the Shard Tower in London [34].
As a proof of concept a curved bench was extruded with a footprint Slipforming is a technique extensively used in practice, as it en-
of 2 m by 0.9 m and 0.8 m tall. It consists of 128 layers, extruded ables a faster rate of construction with little use of formwork. How-
with a velocity of approximately 20 min/layer, which means that ever, it is constrained with respect to the freedom necessary for
the production time of the bench was about 41 h [20]. producing complex concrete geometries. Furthermore, this tech-
These two techniques face three major issues: the first is the nique is generally limited to structures taller than 10 m, because of
bonding between the layers. The second relates to controlling high initial set-up costs.
the processing and hardening time of the material, which has a Re-evaluating this robust and efficient construction technique
direct impact on the third issue; the long production time. This in conjunction with digital fabrication could not only make this
resulted in the fact that the systems discussed above are still not system economically viable for smaller structures, but also help to
ready for an industrial application. Nevertheless, these layer-based unlock the freedom of forming, which is inherent in dynamic pro-
cesses. Such an approach promises an almost waste-free construc-
extrusion techniques hold the promise to develop towards efficient
tion technique for complex concrete structures.
and environmentally sustainable production techniques, capable
of being employed at an architectural and civil engineering scale.
4.2. Smart Dynamic Casting: a robotic slipforming process
4. Dynamic formwork systems in conjunction with digital
Smart Dynamic Casting is a novel patented fabrication process
fabrication resulting from an interdisciplinary research conducted by the re-
search groups of Prof. Dr. Flatt, Prof. Dr. Hermann and Prof. Gra-
4.1. Slipforming mazio & Prof. Kohler at ETH Zurich,12 which has pioneered the first
known combination of slipforming with digital fabrication tech-
The dynamic casting process of slipforming was invented in niques [37].
1899 by the engineer Charles F. Haglin in collaboration with the In this process a formwork, significantly smaller than the struc-
grain company owner Frank Peavey. It is a single-step process, tures produced, is attached to a 6-axis robotic arm. The robotic arm
in which the concrete is continuously placed into a delimited replaces the hydraulic jacks commonly used in slipforming, allow-
formwork that moves vertically at a velocity set according to ing for precise control of velocity and movement in space. This en-
the hydration rate of the concrete, ensuring that the material is hanced robotic control is informed by the physical properties of the
self-supporting when released by the formwork.11 In contrast to material, which are monitored by a feedback system measuring the
extrusion, the concrete is not forced through the formwork with setting and hardening kinetics of the concrete and allowing for op-
pressure. timal formability during the very delicate phase when the material
One of the first known structures erected with this technique is changes from being soft to hard. In this process the complex dy-
a 20-m-high reinforced-concrete grain elevator (Fig. 2), for which namic relationship of the formwork’s geometry, its trajectory and
the slipforming was driven by hand [29,30]. the rheological properties of the material are directly determining
In 1944, the invention of centrally controlled hydraulic jacks the possible geometrical results.
[32] transformed slipforming into an almost automated casting As such, SDC integrates the material properties and the dynamic
system, which enabled to erect tall structures efficiently. Today nature of the process as design parameters, allowing for the
fabrication of complex and custom shapes, which would otherwise
require custom-made formwork for the production of each
11 Jump-forming, which will not be discussed in this text, is often mistaken with
slipforming. But jump-forming is a discontinuous process where the formwork is
jumped or moved to the next level of the construction after the concrete has cured. 12 Further information: [35] Gramazio F., K.M., Lloret Kristensen E., Flatt
Due to high cost jump-forming is mainly applied to simple structures such as cores R.J., http://dfab.arch.ethz.ch/web/e/forschung/223.html, in www.dfab.arch.ethz.ch.
and silos, detailed description on Jump-form or Climbing-forms can be found on [6]. 2012. [36] Shahab, A., http://www.ifb.ethz.ch/pcbm/people/ashahab. 2012.
E. Lloret et al. / Computer-Aided Design ( ) – 5

Fig. 4. The graph shows an example of a test sequence where the red curve shows
increasing force over time. The starting time of the compression is depending on
the material design and is therefore not indicated with a specified time in the
graph. In period A the section was not yet self-supporting; in B the material was
Fig. 3. The research method for the development of the robotic slipforming process. self-supporting, formable, and easy to remove from the mould. In period C the
Iteratively conducted experiments produce the knowledge on the morphology of material started to crack and was no longer formable, generating high friction when
possible geometries D; as well as their dependencies upon robotic fabrication— removing the mould.
movement and shape of the formwork C; and material properties A. In the current
research, the robot’s movement is directly responding to inline measurements of
the evolving material properties (discontinuous line). As more complex geometries experiments focused on the curing time needed for any column
are investigated, material modelling through computer simulation B will mediate
between the measured material properties and the robots movement.
section of the selected concrete to support itself, as well as the
additional load bearing capacity of a column section once the
formwork was removed. In the second stage, this was validated
individual element. This promises an efficient and inherently waste on a prototypical scale in the robotic slipforming process, which
free fabrication technique for complex custom concrete structures. aimed at producing a series of curved column sections using a
cylindrical rigid formwork.
4.3. Research process and experiments
4.4.1. Compression tests
With SDC, the possible formal and structural spectrum of the The compression load tests were performed on a Zwick ma-
fabricated element is defined by the trajectory and velocity of the chine,14 with specimens produced using a cylindrical PVC form-
formwork in relation to hydration rate of the concrete applied. The work (d = 200 mm, h = 200 mm) with a lubricated inlay.
applied research method shown in Fig. 3 consists of empirically After mixing one batch of 80 L, the fresh concrete was cast
conducted experiments aimed at understanding the mutual into 8 individual cylindrical formworks of 10 L each. After the
relationship between material properties, material simulation
material had hydrated just enough to self-sustain the formwork
and digital fabrication. Through multiple production iterations of
was manually slipped off from the first specimen. The specimen
physical architectural prototypes, possible morphologies can be
was then placed centrally in the Zwick machine, whereafter
identified and validated.
pressure was applied vertically onto the column with a constant
This paper discusses two groups of experiments. The first
velocity of 5 mm/min. The test would run until a maximum force
group, which was needed to kick-start the research, focused on
identifying the narrow time frame in which a high strength fibre had been reached which was determined by a decrease in the force
reinforced and self-compacting concrete is both formable and resistance or by visual observation of cracks. In the same tests
self-sustaining. The second set of experiments focused on the sequence the additional 7 specimens where subsequently slipped
implementation of a new concept which integrates a custom made manually and compressed in time intervals of 5 min over a period
feedback system to guide production in accordance to the material of 40 min.
strength evolution of a heavily retarded fibre reinforced concrete. The results of the experiments allowed to identify three
The material applied has been developed during the thesis project distinct periods and material states, which are summarized in
Formwork Free Concrete13 as well as in the on-going research of Fig. 4.
SDC. Details of the material can be found in the first published
paper on this issue by Shahab et al. [39]. 4.4.2. Velocity of the slipping formwork
The compression test results served to determine the time
4.4. Initial experiments: compression and velocity frame in which a column section can sustain its own weight
without formwork as well as its load capacity in that mo-
To prove the fundamental feasibility of the process and ment. Based on this, slipping times were selected for a series of
to collect first insights in the material behaviour, the initial robotic slipforming experiments. These aimed at understanding
the formability of the concrete and identifying the ideal velocity
for slipping and shaping. Following an overview of the experimen-
13 The initial experiments revealed challenges in the formability when using a tal methodology along with the major finding is described:
single batch of fibre reinforced concrete. To solve this problem PI of SDC Prof. Dr. For these preliminary experiments a cylindrical steel formwork
R. J. Flatt, proposed to use a highly retarded concrete which was subsequently
accelerated over time. Based on the concrete used in the first experiments a retarded
with a diameter of 200 mm and a height of 1000 mm, coated
fibre reinforced concrete was developed. This was done during the Bachelor Thesis
project supervised by Prof. Dr. R. J. Flatt, Sara Mantellato, Amir Reza Shahab and
Ena Lloret Kristensen [38], p. 63. In this same bachelor project a validation of new
measuring method for the static yield stress, replaced the large scale compression 14 Zwick, refers to a testing machine which is used for the standard testing of
test with a digital penetrometer. The digital penetrometer is currently used for the tensile and compression tests on a large variety of materials. Further information
feedback system discussed in 4.5. can be found on [40].
6 E. Lloret et al. / Computer-Aided Design ( ) –

with a lubricant foil of polypropylene, was attached to a 6-axis


robotic arm shown in Fig. 5. For each experiment a batch of
30 l of fibre reinforced self-compacting concrete was mixed and
placed to a height of 600 mm in the formwork. After a resting
time of approximately 130 min the robotic slipforming would
start.

Fig. 7. The images from left to right A, B, C are representative to the speed of
production discussed in Fig. 6.

column 650 mm tall in 19 min. This is more than 100 times faster
than the previously discussed layer-based techniques.
Additionally, the experiments revealed that the fibre reinforced
concrete could only be formed optimally for approximately 15 min
after the period of time where the material is sufficiently formable
and self-sustaining. After this period, friction in the formwork is
significant resulting in cracks. Hence, the experiments showed
the necessity of developing concrete in which hydration can be
Fig. 5. The 6-axis robotic arm with a cylindrical slip formwork attached.
controlled over time in order to maintain an optimal formability
during the entire production.

For each experiment the formwork was slipped along the same
4.5. Current experiments: feedback, formwork, dynamic formability
curved trajectory as illustrated in Fig. 6. To evaluate an optimal
speed for slipping and shaping the time-based evolvement of
In order to respond to the limitations in particular in re-
the formworks velocity was individually programmed for each
gards to the formability in the initial experiments, a new concept
experiment based on the following rules: slow in the beginning,
was introduced. The concept employs retarded fibre reinforced
allowing the material to gain strength, then accelerating after self-compacting concrete. In addition it applies a custom-made
the material could carry more than its own weight. The iterative feedback system which measures the material properties during
experiments allowed fine-tuning of the velocity parameters production. Finally, it introduces a new formwork system, which
empirically. allows to easily modify the cross section of the formwork and thus
In summary, the experiments allowed to draw the following to investigate different geometries. The concept has been tested
conclusions: and has allowed fabricating columns with an elliptical section ro-
• velocity A: too high in the initial phase causes the material to tated through 180◦ over its 1800 mm height. Recently this concept
creep has also been used to produce columns with different geometries.
• velocity B: too low, hydration advances too much in the mould
and generates too much friction and therefore breakages occur 4.5.1. Experimental setup
• velocity C: the optimal velocity, slow in the beginning, to allow The 1:1 experiments described in the following chapter uses
the material to obtain the strength with an exponential velocity, the production process, illustrated in Fig. 8: A; a large batch of
adjusted to setting of the mixture used. retarded fibre reinforced self-compacting concrete is prepared. As
the production starts the batch is divided into smaller batches
Despite the discrete curvatures in the columns and the occur- and accelerated at different times with dosages of accelerator B;
rence of creep and cracks, these experiments were still considered the batches of accelerated material are sequentially placed into
as successful, since they identified the narrow time frame in which the formwork E; simultaneously a small sample of the batch is
the selected concrete is both formable and self-supporting. The re- placed into an feedback system, consisting of a digitally controlled
sults revealed an ideal velocity distribution along the slipforming penetrometer, measuring the setting and hardening kinetics of
trajectory (Figs. 6 and 7), which enabled the fabrication of a first the material C; the data measured by the feedback system on the

Fig. 6. Left: graph showing the velocity curves A–C, in relation to the height of three experiments. Right: illustration of the results.
E. Lloret et al. / Computer-Aided Design ( ) – 7

physical material reflect the properties of the material inside the The integrated custom-made feedback system consists of
formwork. The feedback system continuously sends real time data a digital penetrometer attached to a digitally controlled tri-
regarding the material properties via a custom program D; which axial table as illustrated in Fig. 9. The model of the mounted
automatically adjusts the slipping velocity of the formwork along penetrometer is a Mecmesin, (AFG 1000N), using a cylindrical
the path E; and doses the accelerator of the subsequent batch in needle head with a diameter of 19.4 mm and a height 4.1 mm. The
accordance with the current hydration of the concrete batch inside feedback system is controlled via custom software, which performs
the formwork. two functions simultaneously. First, it measures the material
properties of a batch in time intervals of 5 min by submerging
the needle head into the material with a predefined velocity of
2 mm/s. Second, it automatically transmits the data to the robotic
controlling system, which adjusts the slipping and filling velocity
in accordance with the measured setting kinetics of each batch.
To integrate the feedback system into production, quantitative
and qualitative experiments were conducted. These determined
the load bearing capacities of the material using the penetrometer.
Together with the experiments described in Section 4.4 this served
to define the limiting values of section height, shaping time and
rate as well as their interdependence [39,41].
To produce a column with successive batches two main
conditions must be met. First, when a new batch is cast into the
formwork the already present material must still be soft enough
to bond with the new material casted. Second, adding a batch
must not lead to an excess load that cannot be sustained by
the previously placed batch. These two conditions have opposite
requirements with respect to the rate of placing new material. The
first requires adding accelerator and placing batches at a rate that
allows the lower batch to be soft enough to assure good bonding.
The second requires waiting for the placed batch to have enough
strength to sustain itself, avoiding that the material flows because
of its own weight. This is where the measurements performed by
the feedback system play a crucial role in the decision making
during production. However, to implement the feedback system
in the production process and to validate the quantitative and
qualitative results [38,40] additional 1:1 experiments had to be
conducted.

4.5.3. Dynamic formability


The 1:1 experiments had two major objectives. First of all
to produce an elliptical column with a rotation of 180◦ over its
full height (1800 mm), without cracks or flow of material. This
geometry was selected as it offers a well-defined challenge for
the formability approach, while it nevertheless keeps the problem
within well-defined boundaries. The second objective was to
Fig. 8. Schematic illustration of the experimental setup. define the optimal placement rate and height of the batches in
relation to the slipping velocity defined by the feedback system. An
overview of the methodology is given below along with the major
findings.
4.5.2. Material feedback system The 1:1 experiments applied the production process described
To trace the period of time during which the material changes in Section 4.5.1. For this set-up a new formwork system was
from soft to hard the production process relies on continuous developed. It consists of a generic space frame into which a
measurement of the material strength evolution, in order to formwork of any geometry can be inserted e.g. a square, star or
guide production. The measurements determine when to start the triangle. The frame is attached to the robotic arm as illustrated in
production, with which velocity to slip and shape as well as when Fig. 10. In these experiments an elliptical formwork with a radius
to add accelerator to the next batch and place it in the formwork. of 125 mm × 80 mm and a height of 600 mm was used.

Fig. 9. Penetrometer attached to tri-axial table. Data regarding the material properties are sent to the robotic control system.
8 E. Lloret et al. / Computer-Aided Design ( ) –

Fig. 10. Left: illustration of the elliptical formwork attached to the robotic arm. Right: a top view of the elliptical formwork.

For each experiment the formwork was moved vertically and


rotated by 180◦ over the entire height of the column. As the form-
work was moved layers of accelerated concrete were placed in a
rate defined by the measurement provided by the feedback system.
Each experiment examined a particular batch height, placing rate
and slip velocities. The velocity of the robotic slip forming was syn-
chronized to the hydration kinetics of the concrete by the custom-
made feedback system measuring the material properties in real
time. In summary, the velocities were programmed to slip with:
• slow velocity: 0.4 cm/min when feedback measurements sent a
value between 2–4 N/cm2 . Indicating that the material was too
soft to carry its own weight;
• medium velocity: 1.2 cm/min when feedback measurements
sent a value between 4–6 N/cm2 . Indicating that the material
could carry its own weight, hence the optimal period forming;
• fast velocity: 2.4 cm/min when feedback measurements sent a
value between 6–8 N/cm2 . The material could carry more than
its own weight and started to lose its formability. Fig. 11. Left: The 1800 mm elliptical column with a rotation of 180◦ produced with
successive batches [42]. Right: two stages in the production process [43].
Iterations of experiments allowed to conclude that to obtain
the optimal formability the batches had to be reduced to
4.5.4. Future research
approximately 3–5 cm and placed at intervals of 2–5 min. The
optimal slipping velocity ranged between 1.2 to 2.4 cm/min. Here The aim is to develop SDC into a highly predictable and fully
it is important to emphasize that already small variations in the automated feedback driven fabrication system. To reach this goal
concrete composition and in particular in the room temperature a computer model is currently being developed15 by the group
can modify these variables and make the difference between the of Prof. Dr. Herrmann [44]. At the moment this model functions
layers that would fail (flow or crack) and ones that could be as a conditional tool in the feedback system which predicts the
properly shaped. load capacities of the material in the transition from liquid to solid
However, thanks to both quantitative and qualitative load allowing to precisely predict the dosage of chemical admixtures
analyses of the material in the initial experiments along with the needed, the amount of material to cast and to adjust the robotic slip
development of a custom-made measuring and feedback system, velocity accordingly. In a future perspective the aim is to develop
it was possible to develop a robust production process [20], with this tool to a level that it can be used to automatically control this
which, a large elliptical column without cracks or flow of material production. In addition this tool must function as a digital design
could be produced (as illustrated in Fig. 11). tool in which the physical material and fabrication parameters are
To prove the robustness of the system and to validate the integrated. This will allow planners to explore the design space
formability of the material with other geometries, three cross
while producing rationalized and responsive designs which are in
sections (a square, a cross and again an ellipse with the same
sync with the material properties and fabrication parameters of the
volume) were tested, and were used to produce three full-scale
robotic slipforming system.
columns with the method described in Section 4.5.1. The columns
were slipped in a rotational trajectory of 180◦ around the central A challenge will therefore be to validate and optimize this
axis of the formwork with an average velocity of 1.2 cm/min with simulation model based on quantitative and qualitative analyses
layers of approximately 3–5 cm. The results in Fig. 12 show the gathered through the physical experimentation of this on-going
three columns at their final height of 190 cm. research.
These structures clearly demonstrate that the implementation
of feedback-driven, computer-controlled systems, which can de-
termine the physical properties of the concrete, allows new pro- 15 The program is being developed by Ph.D. student Linus Mettler, specialized in
duction and design processes to be employed for the production of computational physics for building materials in the group of Prof. Dr. H. Herrmann
complex concrete structures. who is also research partner in SDC [45].
E. Lloret et al. / Computer-Aided Design ( ) – 9

Another major part of the research relates to the material as an interdisciplinary research project within the ETH Zurich
design, developed in the group of Prof. Dr. Flatt—where a particular between (PI) Prof. Dr. Flatt (Institute for Building Materials), Prof.
focus will be on the adjustment of the chemical admixtures, their Dr. Fisher (Laboratory of Food Process Engineering); Prof. Gramazio
impact on each other and with the cement hydration. and Prof. Kohler (Chair of Architecture and Digital Fabrication); and
Last but not least, the current investigation is focused on the Prof. Dr. Herrmann (Institute for Building Materials). This grant
development of a flexible formwork. This formwork should allow provides financial support for Ms. Ena Lloret, Mr. Amir R. Shahab
to dynamically adjust the formwork geometry during the slipping and Mr. Linus Mettler.
process, hence increasing the range of possible architectural We express our sincere gratitude to all those who have been
morphologies and thus radically enlarge the design space of this and are associated with these efforts in particular for their
robotic fabrication system. remarkable contributions, fruitful discussions and critical reviews.
Heinz Richner, Sara Mantellato, Oliver Glauser, Lex Reiter, René
Käßmann, Andreas Thoma, Beat Lüdi, Adriano Alberti, Lukas
Ambühl, Daniela Christen, Dr. Timothy Wangler, Dr. Ralph Bärtschi,
Dr. Falk Wittel, Prof. Dr. Peter Fischer, and Dr. Jan Willmann.

References

[1] Oxman N. Materialecologie. 2013 (accessed on 08.05.2013)


http://materialecology.blogspot.ch/.
[2] Kierdorf A, Hilsdorf HK. In: Hassler Uta, editor. Was der architekt vom
stahlbeton wissen sollte. Zur Geschichte des Bauens mit Beton, Zurich: gta
Verlag; 2010. p. 11–52.
[3] Langenberg S. Das Konzept Ersatz? Probleme bei der Reparatur industriell
gefertigter Bauteile. Technikgeschichte, Berlin: Verein Deutscher Ingenieure
(VDI) Gesellschaft für Technikgeschichte; 2012. p. 256–8. Bd. Ed sigma e.Kfm.
[4] Migayrou F. Architecture non standard. Centre Pompidou. Paris: Centre
Pompidou; 2003.
Fig. 12. 3 columns produced with a three variation of formworks [44]. [5] Olivier JGJ. et al. Trends in global CO2 emissions. The Hague/Bilthoven. PBL
Netherlands Environmental Assessment Agency; 2012.
[6] Johnston DW. Design and construction of concrete formwork. In: Nawy Ed-
ward G, editor. Concrete construction engineering handbook. New Jersey,
5. Conclusion USA: Boca Raton: CRC Press; 2008. p. 7.1–7.49.
[7] Llatas C. A model for quantifying construction waste in projects according to
The novel fabrication technique presented in this paper, Smart the European waste list. Waste Manage. 2011;6:1083–426. 31.
Dynamic Casting, is the result of an interdisciplinary research effort. [8] Hurd MK. Formwork for concrete. 7th ed. American Concrete Institute; 2005.
[9] Schmidt H, Hassler U. Häuser aus beton. Tübingen: Wasmuth; 2004. p. 211.
It aims at addressing a novel level of complexity in architectural
[10] Nervi PL. Aesthetics and technology in building. Cambridge, Massachusetts:
fabrication technology by capitalizing on the rapid technological Harvard University Press; 1965. 106–7. 130–45.
advances in the field of building material sciences, simulation and [11] Iori T, Poretti S. Pier Luigi Nervi’s works for the 1960 Rome Olympics. SEdHC.
robotic technologies. Arquitectos de Cádiz. COAAT Cádiz; 2005. Actas del Cuarto Congreso Nacional
de Historia de la Construcción, Cádiz.
One key prerequisite of this fundamental research is the
[12] Kolarevic B. Digital production. In: Architecture in the digital age, design and
ability to understand and monitor the hydration process of the manufacturing, Branko Kolarevic. New York: Spoon Press; 2003. p. 36.
concrete by implementing digitally controlled sensor systems in [13] NEDCAM. http://www.nedcam.com, 2011 (accessed on 28.08.2012).
line with robotics and thus to precisely control its evolution [14] PERI. http://www.peri.com/ww/de/index.cfm (accessed on 26.01.2014).
[15] PERI rundflex:
through chemical admixtures. http://www.peri.com/de/loesungen/produkte/schalung/wandschalung/
The second prerequisite is the use of a robot. It is this generic rundflex.cfm, 2012 (accessed on 26.01.2014).
machine that makes it possible to perform precise and digitally [16] Hutton L, Sauerbruch M. ADAC headquarters Munich. 2006–2012.
controlled spatial movements far beyond the skill of a human. http://www.sauerbruchhutton.de/images/adac_headquarters_en.pdf.
(accessed on 28.06.2013).
The robot, which can be driven by custom-made software, is [17] PERI software:
able to interlink the physical reality of the complex material http://www.peri.ltd.uk/products/service/software_/peri_software.cfm.
properties of concrete with the processing requirements of this (accessed on 26.01.2014).
digital fabrication process, and thus enables to accurately explore [18] Kirkegaard C, Raun PH. Reconfigurable double-curved mould. In: Proceedings
of the second international conference on flexible formwork. BRE CICM,
the formability of concrete in the phase when it changes from University of Barth, Claverton Down, BA 7AY, UK; 2012. pp 292–9.
liquid to solid. This has allowed to produce precisely shaped [19] Oesterle S, Vansteenkisten A, Mirjan A. Chair of architecture and digital
complex column structures in 3D space, in line with the physical fabrication, ETH Zurich. Zero waste free-form formwork. In: Proceedings
properties of the material, while using a formwork significantly of the second international conference on flexible formwork. Claverton
Down, BRE CICM, University of Barth, Claverton Down, BA 7AY, UK; 2012.
smaller than the column produced. In these terms SDC genuinely p. 258–67.
relates to the idea of ‘‘Digital Materiality’’, which has been [20] Walter M. Extrusion dies for plastic and rubber, design and engineering
described by Gramazio & Kohler as ‘‘the synthesis of two seemingly computations. 3rd ed. Munich: Hanser Fachbuchverlag; 2008.
distinct worlds, the digital and the material, generating new, self- [21] Howson H. patent 291, 849 United States; 1884.
[22] Elliot KS. Precast concrete structures oxford. 2nd ed. Precast/Prestressed
evident realities as soon as data and material, programming and Concrete Institute; 2002. p. 1998.
construction are interwoven’’ [46]. [23] Delatte N. Concrete pavement design, construction, and performance. 1st ed.
In light of this, SDC promises to become a sustainable and London: Taylor & Francis; 2008.
[24] Wallis S. Hydroshield and extruded lining usage in Lyon; Jan 2013.
waste reducing, additive construction technique, combining dig-
http://www.tunneltalk.com/Discussion-Forum-Jan13-Hydroshield-and-
ital fabrication systems with an existing and well-established con- extruded-lining.php (accessed on 06.06.2013).
struction method. [25] Khoshnevis B. Contour crafting, a robotic construction system,
http://www.contourcrafting.org/ ; 2013 (accessed on 3.06.2013.).
Acknowledgements [26] Zhang J, Khoshnevis B. Optimal machine operations planning for construction
by Contour Crafting. J Autom Constr 2013;29:50–67.
[27] Lim S, et al. Developments in construction-scale additive manufacturing
Based on the initial experiments described in this paper, this processes. Autom Constr 2012.
project received an ETH Research Grant ETH-13 12-1 under the [28] Zhang J, Khonevis B. Optimal machine operations planning for construction by
name Smart Dynamic Casting (SDC). Currently SDC is conducted contour crafting. J Automat Construct 2013;29:50–7.
10 E. Lloret et al. / Computer-Aided Design ( ) –

[29] Peavey-Haglin experimental concrete grain elevator, [38] Alberti A, Ambüh L, Christen D. Bachelor thesis project formwork free concrete.
http://www.mnhs.org/library/tips/history_topics/70peavey.html Supervised by Prof. Dr. R. J. Flatt et al.: D-BAUG, IfB, ETH Zurich, May 2012.
(accessed on 15.12.2012). [39] Shahab AR, Lloret EK, Fischer P, Gramazio F, Kohler M, Flatt RJ. Smart dynamic
[30] Heffelfinger JR. Experiment in concrete: a pioneer venture in grain storage. casting or how to exploit the liquid to solid transition in cementitious
Martz 1960. materials. In: proceedings CD of the 1st international conference on rheology
http://collections.mnhs.org/MNHistoryMagazine/articles/37/v37i01p014- and processing of construction materials and of the 7th international
018.pdf (accessed on the 30.12.2012). conference on self-compacting concrete. Paris, France 2013.
[31] Jegher C. Die gleitschalung im silobau. Heft 7, 1930, Schweizerische [40] Zwick.
Bauzzeitung, Bd. 95/96, p. 86–93. http://www.directindustry.com/prod/zwick/tensile-compression-testing-
[32] Bygging Uddemann.
machines-15660-34872.htm, 2013 (accessed on 3.06.2013).
http://bygging-uddemann.se/about-us/background-history.html.
[41] Lloret EK, Shahab AR, Gramazio F, Kohler M, Flatt RJ. Smart dynamic casting:
http://bygging-uddemann.se, 2011 (accessed 20.12.2012).
a robotic fabrication system for complex structures, Concrete Innovation
[33] Bickley JA. Concrete technology aspects of CN tower. C01. J. Constr. Div. 1975;
101:201–12. Conference Norway, Oslo Norway, 2014 [submitted for publication].
[34] Ferguson H. Building the shard. Ingenia 2012;9:25–30. [42] Breitler C. Elliptical Column after production, Architecture and digital
[35] Web site for Smart Dynamic Casting DFab: fabrication, ETH Zurich, 2013.
http://dfab.arch.ethz.ch/web/d/forschung/223.html [43] Kohler Gramazio. Elliptical Column production, Architecture and digital
(accessed on the 26.01.2014). fabrication, ETH Zurich, 2013.
[36] Web site for Smart Dynamic Casting IbK: http://www.ifb.ethz.ch/pcbm/ [44] Kohler Gramazio. Three columns with rigid formworks, Architecture and
people/ashahab/research. Digital Fabrication, ETH Zurich, 2013.
[37] Lloret EK, Gramazio F, Kohler M, Flatt RJ. Smart dynamic casting for complex [45] Hermann HJ. www.hans-hermann.ethz.ch (acessed on the 26.01.2014).
shaped concrete structures. Patent licence pending, ETH Transfer, ETH Zurich [46] Gramazio F, Kohler M. Digital materiality in architecture. Baden, Switzerland:
Switzerland. Lars Müller Publishers; 2008.

You might also like