INTERIOR OFFICE, Project

MAKASSAR
2019

PARTISI RUKO CITRALAND MODEL 1


INTERIOR OFFICE, Project

MAKASSAR
2019

PARTISI RUKO CITRALAND MODEL 2


RENCANA ANGGARAN BIAYA
Pekerjaan : Interior Coffe Toffee
Lokasi : Sangata

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME
SATUAN (Rp)

A PEKERJAAN PERSIAPAN
1 Marking 1.00 Ls 500,000.00 500,000.00
2 Pembersihan Lokasi 1.00 Ls 500,000.00 500,000.00
4 Mobilisasi dan Demobilisasi 1.00 Ls 3,500,000.00 3,500,000.00
5 Akomodasi 1.00 Ls 3,000,000.00 2,500,000.00
B PEKERJAAN MEUBEL
1 Outlet Coffe Toffee Exclude blender box,Espresso machine,Knock box,Kulkas
Rak outlet Bahan multipleks fin.HPL Taco,Panjang 7,99M2 1.00 Set 22,430,000.00 22,430,000.00
Zink 1 Lobang bentuk persegi 45x45cm 1.00 Unit 700,000.00 700,000.00
Kran air 1.00 Unit 400,000.00 400,000.00
Instalasi listrik Kabel NYM 2x2,5 3x2,5 Eterna,Fitting ; Panasonic 7.00 Titik 200,000.00 1,400,000.00
Instalasi air Pipa PVC Ex.Wavin/setara 1.00 Ls 500,000.00 500,000.00
Pasang mozaik Mozaik 30x30cm ex.Bella / Venus 4.62 M2 850,000.00 3,927,000.00
Papan menu Bahan multipleks fin.HPL Taco,exclude sticker 5.00 Unit 170,000.00 850,000.00
2 Sofa Single Bahan suede/beludru ex.Amorist,rangka meranti 13.00 Unit 1,750,000.00 22,750,000.00
3 Sofa Duoble Bahan suede/beludru ex.Amorist,rangka meranti 5.00 Unit 2,500,000.00 12,500,000.00
4 Sofa Puff Bahan suede/beludru ex.Amorist,rangka meranti 9.00 Unit 500,000.00 4,500,000.00
5 Meja Sofa Bundar ± 90 cm 7.00 Unit 1,500,000.00 10,500,000.00
6 Meja Sofa Kotak Dimensi 80x50x50cm 3.00 Unit 1,000,000.00 3,000,000.00
7 Kursi Rotan 31.00 Unit 1,750,000.00 54,250,000.00
8 Meja Kaca 10.00 Unit 2,500,000.00 25,000,000.00
9 Rak Majalah & Merchand Bahan multipleks fin.HPL Taco,exclude sticker 1.00 Pcs 1,700,000.00 1,700,000.00
10 Condiment Cart Bahan multipleks fin.HPL Taco,exclude sticker 2.00 Pcs 2,205,000.00 4,410,000.00
11 Pembatas Tanaman Dimensi 60x20x40cm 5.00 Pcs 400,000.00 2,000,000.00
12 Backdrop Kaca Bahan multipleks fin.HPL Taco,exclude sticker,kaca 8mm clear 10.03 M2 550,000.00 5,516,500.00
C PEKERJAAN SEKAT & PLAFON
1 Sekat Gypsum 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 42.40 M2 275,000.00 11,660,000.00
2 Plafon Drop Ceiling + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 139.62 M2 198,000.00 27,644,760.00
RENCANA ANGGARAN BIAYA
Pekerjaan : Interior Coffe Toffee
Lokasi : Sangata

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME
SATUAN (Rp)
3 Ornamen Dinding gypsum Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 9.60 M2 275,000.00 2,640,000.00
4 Partisi Kaca Non Frame,kaca 10mm clear 71.21 M2 495,000.00 35,248,950.00
5 Pintu Kaca Frameles 10mm clear 3.00 M2 3,650,000.00 10,950,000.00
D PEKERJAAN INSTALASI LISTRIK
1 Titik Lampu, MCB & Stop Kontak Kabel NYM 2x2,5 3x2,5 Eterna,Fitting ; Panasonic 45.00 Titik 220,000.00 9,900,000.00
2 Downlight 5" 16.00 Unit 85,000.00 1,360,000.00
3 Neonstick Drop Ceiling 55.00 Unit 85,000.00 4,675,000.00
4 Instalasi AC Kabel NYM 3x2,5 Eterna,Fitting ; Panasonic 7.00 Titik 1,100,000.00 7,700,000.00
5 Instalasi Genset ex. German 1.00 Ls 3,850,000.00 3,850,000.00
E LAIN-LAIN
1 Laminate Floor & leveling ex.kendo,level floor with meranti wood and multipleks 27.50 M2 900,000.00 24,750,000.00
2 Wallcover Biji Kopi Laminate printed/wallpaper 20.00 M2 350,000.00 7,000,000.00
3 Sticker Sandblast Cutting sticker 23.53 M1 200,000.00 4,706,000.00
4 Poster Ukuran Besar 60x120cm 3.00 Lbr 120,000.00 360,000.00
5 Poster Ukuran Sedang 50x70cm 4.00 Lbr 170,000.00 680,000.00
6 Sticker Backdrop Kaca cuting sticker 4.69 M2 135,000.00 633,150.00
7 Neonbox Pintu Masuk Acrilic 5mm fin ducco cat backlight lampu TL,huruf t=45cm 1.00 Ls 8,500,000.00 8,500,000.00
8 Neonbox Bulat Coffe Toffe No Specification 1.00 Ls
9 Letter Timbul Outlet Acrilic 5mm fin ducco cat non backlight 1.00 Ls 2,000,000.00 2,000,000.00
10 Sticker Logo Coffe Toffe Di Outlet Digital print 1.00 Ls 550,000.00 550,000.00

TOTAL 341,141,360.00

Note : - Harga dapat berubah sesuai dengan perubahan spesifikasi dan volume
RENCANA ANGGARAN BIAYA
Pekerjaan : Interior Kantor
Lokasi :

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME
SATUAN (Rp)

A PEKERJAAN PERSIAPAN
1 Marking 1.00 Ls 1,000,000.00 1,000,000.00
2 Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00
4 Mobilisasi dan Demobilisasi 1.00 Ls 3,500,000.00 3,500,000.00
5 Akomodasi 1.00 Ls 3,000,000.00 3,000,000.00
B PEKERJAAN MEUBEL
1 Kursi Tamu Bahan fin. PVC, Veneer 2.00 Unit 2,500,000.00 5,000,000.00
2 Kursi Tamu Panjang Bahan Multipleks Fin.HPL Taco (inc aksesoris) 1.00 Unit 4,550,000.00 4,550,000.00
3 Kursi Staf Bahan Alumunium, Mesh 10.00 Unit 3,700,000.00 37,000,000.00
4 Meja Bundar Tamu Bahan Fibreboard Cat Akrilik, Baja dilapisi serbuk epoxy 1.00 Unit 1,500,000.00 1,500,000.00
5 Meja Foyer Bahan Multipleks Fin. HPL Taco 1.00 Unit 6,600,000.00 6,600,000.00
6 Meja HRD Bahan Rangka Baja, Multipleks Fin.HPL Taco (inc aksesoris) 1.00 Unit 8,900,000.00 8,900,000.00
Bahan Rangka Baja, frame kaca 5mm Multipleks Fin.HPL Taco
7 Meja SDM (inc aksesoris)
1.00 Unit 19,500,000.00 19,500,000.00
Bahan Rangka Baja, frame kaca 5mm Multipleks Fin.HPL Taco
8 Meja Kerja 1 orang (inc aksesoris)
2.00 Unit 7,200,000.00 14,400,000.00
9 Backdrop
- R. Foyer Bahan multipleks fin.HPL Taco (inc instalasi) 7.60 M2 2,050,000.00 15,580,000.00
- R. HRD Bahan multipleks fin.HPL Taco (inc instalasi) 16.00 M2 2,050,000.00 32,800,000.00
- R. SDM Bahan multipleks fin.HPL Taco (inc instalasi) 14.80 M2 2,050,000.00 30,340,000.00
- R. Staf Bahan multipleks fin.HPL Taco (inc instalasi) 12.00 M2 2,050,000.00 24,600,000.00
- Koridor Bahan multipleks fin.HPL Taco (inc instalasi) 8.00 M2 2,050,000.00 16,400,000.00
C PEKERJAAN SEKAT
1 Sekat Gypsum 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara, fin. Wallpaper 12.00 M2 375,000.00 4,500,000.00
2 Partisi Kaca Frameles 10mm clear tempred (inc. aksesoris) 52.80 M2 1,250,000.00 66,000,000.00
3 Pintu Kaca Non Frameles 10mm clear tempred (inc. aksesoris) 19.40 M2 1,250,000.00 24,250,000.00

TOTAL 320,420,000.00

Note : - Harga dapat berubah sesuai dengan perubahan spesifikasi dan volume
- Harga belum termasuk PPN 10%
RENCANA ANGGARAN BIAYA
Pekerjaan : Interior Kantor
Lokasi :

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME
SATUAN (Rp)

A PEKERJAAN PERSIAPAN
1 Marking 1.00 Ls 1,000,000.00 1,000,000.00
2 Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00
4 Mobilisasi dan Demobilisasi 1.00 Ls 3,500,000.00 3,500,000.00
5 Akomodasi 1.00 Ls 3,000,000.00 3,000,000.00
B PEKERJAAN MEUBEL
1 Kursi Tamu Bahan fin. PVC, Veneer 2.00 Unit 2,500,000.00 5,000,000.00
2 Kursi Tamu Panjang Bahan Multipleks Fin.HPL Taco (inc aksesoris) - Unit 4,550,000.00 -
3 Kursi Staf Bahan Alumunium, Mesh - Unit 3,700,000.00 -
4 Meja Bundar Tamu Bahan Fibreboard Cat Akrilik, Baja dilapisi serbuk epoxy - Unit 1,500,000.00 -
5 Meja Foyer Bahan Multipleks Fin. HPL Taco - Unit 6,600,000.00 -
6 Meja HRD Bahan Rangka Baja, Multipleks Fin.HPL Taco (inc aksesoris) - Unit 8,900,000.00 -
Bahan Rangka Baja, frame kaca 5mm Multipleks Fin.HPL Taco
7 Meja SDM (inc aksesoris)
- Unit 19,500,000.00 -
Bahan Rangka Baja, frame kaca 5mm Multipleks Fin.HPL Taco
8 Meja Kerja 1 orang (inc aksesoris)
- Unit 7,200,000.00 -
9 Backdrop
- R. Foyer Bahan multipleks fin.HPL Taco (inc instalasi) 7.60 M2 2,050,000.00 15,580,000.00
- R. HRD Bahan multipleks fin.HPL Taco (inc instalasi) 16.00 M2 2,050,000.00 32,800,000.00
- R. SDM Bahan multipleks fin.HPL Taco (inc instalasi) 14.80 M2 2,050,000.00 30,340,000.00
- R. Staf Bahan multipleks fin.HPL Taco (inc instalasi) 12.00 M2 2,050,000.00 24,600,000.00
- Koridor Bahan multipleks fin.HPL Taco (inc instalasi) 8.00 M2 2,050,000.00 16,400,000.00
C PEKERJAAN SEKAT
1 Sekat Gypsum 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara, fin. Wallpaper 12.00 M2 375,000.00 4,500,000.00
2 Partisi Kaca Frameles 10mm clear tempred (inc. aksesoris) 52.80 M2 1,250,000.00 66,000,000.00
3 Pintu Kaca Non Frameles 10mm clear tempred (inc. aksesoris) 19.40 M2 1,250,000.00 24,250,000.00

TOTAL 227,970,000.00

Note : - Harga dapat berubah sesuai dengan perubahan spesifikasi dan volume
- Harga belum termasuk PPN 10%
RENCANA ANGGARAN BIAYA
Pekerjaan : Interior Kantor
Lokasi :

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME
SATUAN (Rp)

A PEKERJAAN PERSIAPAN
1 Marking 1.00 Ls 1,000,000.00 1,000,000.00
2 Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00
4 Mobilisasi dan Demobilisasi 1.00 Ls 3,500,000.00 3,500,000.00
5 Akomodasi 1.00 Ls 3,000,000.00 3,000,000.00

B Pekerjaan Partisi Kaca


1 Partisi & Pintu Kaca Non Frameles 12mm clear tempred (inc. aksesoris) 52.80 M2 1,550,000.00 81,840,000.00

C Pekerjaan Meubel
1 R. Foyer
- Meja Resepsi Bahan multipleks fin.HPL Taco 1.00 unit 6,600,000.00 6,600,000.00
- Backdrop Company Logo Bahan multipleks fin.HPL Taco 7.60 M2 1,250,000.00 9,500,000.00
- Backdrop Merah Bahan multipleks fin.HPL Taco, Cermin 5mm 7.60 M2 2,250,000.00 17,100,000.00
- Backdrop Abu-abu Bahan multipleks fin.HPL Taco, Cermin 5mm 9.60 M2 1,250,000.00 12,000,000.00
- Plafon Cokelat Bahan multipleks fin.HPL Taco 9.50 M2 1,450,000.00 13,775,000.00

D Pekerjaan Sekat
- Sekat Gudang 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 14.20 M2 415,000.00 5,893,000.00
- Sekat Ruko 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 51.20 M2 415,000.00 21,248,000.00

E Pekerjaan Instalasi Listrik


- Titik Lampu Kabel NYM 2x2,5 Eterna, Panasonic 17.00 Titik 250,000.00 4,250,000.00

TOTAL 180,706,000.00
Discount 20,706,000.00
TOTAL 160,000,000.00
Note : - Harga dapat berubah sesuai dengan perubahan spesifikasi dan volume
- Harga belum termasuk PPN 10%
RENCANA ANGGARAN BIAYA
Pekerjaan : Interior Kantor
Lokasi :

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME
SATUAN (Rp)

A PEKERJAAN PERSIAPAN
1 Marking 1.00 Ls 1,000,000.00 1,000,000.00
2 Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00
4 Mobilisasi dan Demobilisasi 1.00 Ls 3,500,000.00 3,500,000.00
5 Akomodasi 1.00 Ls 3,000,000.00 3,000,000.00

B Pekerjaan Partisi Kaca


1 Partisi & Pintu Kaca Non Frameles 12mm clear tempred (inc. aksesoris) 59.25 M2 1,550,000.00 91,837,500.00

C Pekerjaan Meubel
1 R. Foyer
- Meja Resepsi Bahan multipleks fin.HPL Taco 1.00 unit 6,600,000.00 6,600,000.00
- Backdrop Company Logo Bahan multipleks fin.HPL Taco 6.65 M2 1,250,000.00 8,312,500.00
- Backdrop Merah Bahan multipleks fin.HPL Taco, Cermin 5mm 6.65 M2 2,250,000.00 14,962,500.00
- Backdrop Abu-abu Bahan multipleks fin.HPL Taco, Cermin 5mm 8.40 M2 1,250,000.00 10,500,000.00
- Plafon Cokelat Bahan multipleks fin.HPL Taco 6.65 M2 1,450,000.00 9,642,500.00

D Pekerjaan Sekat
- Sekat Gudang 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 12.43 M2 415,000.00 5,156,375.00
- Sekat Ruko 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 51.20 M2 415,000.00 21,248,000.00

E Pekerjaan Instalasi Listrik


- Titik Lampu Kabel NYM 2x2,5 Eterna, Panasonic 17.00 Titik 250,000.00 4,250,000.00

TOTAL 181,009,375.00
Discount 21,009,375.00
TOTAL 160,000,000.00
Note : - Harga dapat berubah sesuai dengan perubahan spesifikasi dan volume
- Harga belum termasuk PPN 10%
RENCANA ANGGARAN BIAYA
Pekerjaan : Interior Kantor
Lokasi :

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME
SATUAN (Rp)

A PEKERJAAN PERSIAPAN
1 Marking 1.00 Ls 1,000,000.00 1,000,000.00
2 Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00
4 Mobilisasi dan Demobilisasi 1.00 Ls 3,500,000.00 3,500,000.00
5 Akomodasi 1.00 Ls 3,000,000.00 3,000,000.00

B Pekerjaan Partisi Kaca


1 Partisi & Pintu Kaca Non Frameles 12mm clear tempred (inc. aksesoris) 64.05 M2 1,550,000.00 99,277,500.00

C Pekerjaan Meubel
1 R. Foyer
- Meja Resepsi Bahan multipleks fin.HPL Taco 1.00 unit 6,600,000.00 6,600,000.00
- Backdrop Company Logo Bahan multipleks fin.HPL Taco 6.65 M2 1,250,000.00 8,312,500.00
- Backdrop Merah Bahan multipleks fin.HPL Taco, Cermin 5mm 6.65 M2 2,250,000.00 14,962,500.00
- Backdrop Abu-abu Bahan multipleks fin.HPL Taco, Cermin 5mm 8.40 M2 1,250,000.00 10,500,000.00
- Plafon Cokelat Bahan multipleks fin.HPL Taco 6.65 M2 1,450,000.00 9,642,500.00

D Pekerjaan Sekat
- Sekat Gudang 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 12.43 M2 415,000.00 5,156,375.00
- Sekat Ruko 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 51.20 M2 415,000.00 21,248,000.00

E Pekerjaan Instalasi Listrik


- Titik Lampu Kabel NYM 2x2,5 Eterna, Panasonic 17.00 Titik 250,000.00 4,250,000.00

TOTAL 188,449,375.00
Discount 21,009,375.00
TOTAL 167,440,000.00
Note : - Harga dapat berubah sesuai dengan perubahan spesifikasi dan volume
- Harga belum termasuk PPN 10%
RENCANA ANGGARAN BIAYA MODEL 1
Pekerjaan : Interior Kantor
Lokasi : Ruko Citra Land Makassar

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME
SATUAN (Rp)

A PEKERJAAN PERSIAPAN
1 Marking 1.00 Ls 1,000,000.00 1,000,000.00
2 Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00
4 Mobilisasi dan Demobilisasi 1.00 Ls 1,500,000.00 1,500,000.00
5 Akomodasi 1.00 Ls 1,500,000.00 1,500,000.00

B Pekerjaan Pintu & Partisi Kaca


1 Partisi Kaca Non Frameles 12mm clear tempred (inc. aksesoris) 35.46 M2 1,450,000.00 51,418,450.00
2 Pintu Kaca Koboy Non Frameles 12mm clear tempred (inc. aksesoris), Koboy 3.00 bh 5,500,000.00 16,500,000.00

C Pekerjaan Meubel
1 R. Foyer
- Meja Resepsi Bahan multipleks fin.HPL Taco 1.00 unit 5,800,000.00 5,800,000.00
- Backdrop Company Logo Bahan multipleks fin.HPL Taco 6.65 M2 1,050,000.00 6,982,500.00
- Backdrop Merah Bahan multipleks fin.HPL Taco, Cermin 5mm 6.65 M2 1,450,000.00 9,642,500.00
- Backdrop Abu-abu Bahan multipleks fin.HPL Taco, Cermin 5mm 8.40 M2 1,050,000.00 8,820,000.00
- Plafon Cokelat Bahan multipleks fin.HPL Taco 6.65 M2 1,250,000.00 8,312,500.00

D Pekerjaan Sekat
- Sekat Gudang 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 19.00 M2 350,000.00 6,650,000.00
- Sekat Ruko 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 68.40 M2 350,000.00 23,940,000.00
- Sekat Ruangan 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 58.23 M2 350,000.00 20,381,550.00

E Pekerjaan Instalasi Listrik


- Titik Lampu Kabel NYM 2x2,5 Eterna, Panasonic 17.00 Titik 210,000.00 3,570,000.00

TOTAL 167,017,500.00
Note : - Harga dapat berubah sesuai dengan perubahan spesifikasi dan volume
- Harga belum termasuk PPN 10%
RENCANA ANGGARAN BIAYA MODEL 2
Pekerjaan : Interior Kantor
Lokasi : Ruko Citra Land Makassar

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME
SATUAN (Rp)

A PEKERJAAN PERSIAPAN
1 Marking 1.00 Ls 1,000,000.00 1,000,000.00
2 Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00
4 Mobilisasi dan Demobilisasi 1.00 Ls 1,500,000.00 1,500,000.00
5 Akomodasi 1.00 Ls 1,500,000.00 1,500,000.00

B Pekerjaan Pintu & Partisi Kaca


1 Partisi Kaca Frameles 5mm clear non tempred (inc. aksesoris) 44.08 M2 850,000.00 37,466,300.00
2 Pintu Kaca Koboy Frameles 5mm clear non tempred (inc. aksesoris), Koboy 3.00 bh 2,500,000.00 7,500,000.00

C Pekerjaan Meubel
1 R. Foyer
- Meja Resepsi Bahan multipleks fin.HPL Taco 1.00 unit 5,800,000.00 5,800,000.00
- Backdrop Company Logo Bahan multipleks fin.HPL Taco 6.65 M2 1,050,000.00 6,982,500.00
- Backdrop Merah Bahan multipleks fin.HPL Taco, Cermin 5mm 6.65 M2 1,450,000.00 9,642,500.00
- Backdrop Abu-abu Bahan multipleks fin.HPL Taco, Cermin 5mm 8.40 M2 1,050,000.00 8,820,000.00
- Plafon Cokelat Bahan multipleks fin.HPL Taco 6.65 M2 1,250,000.00 8,312,500.00

D Pekerjaan Sekat
- Sekat Gudang 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 19.00 M2 350,000.00 6,650,000.00
- Sekat Ruko 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 68.40 M2 350,000.00 23,940,000.00

E Pekerjaan Instalasi Listrik


- Titik Lampu Kabel NYM 2x2,5 Eterna, Panasonic 17.00 Titik 210,000.00 3,570,000.00

TOTAL 123,683,800.00
Note : - Harga dapat berubah sesuai dengan perubahan spesifikasi dan volume
- Harga belum termasuk PPN 10%
RENCANA ANGGARAN BIAYA MODEL 1
Pekerjaan : Interior Kantor
Lokasi : Ruko Citra Land Makassar

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME
SATUAN (Rp)

A PEKERJAAN PERSIAPAN
1 Marking 1.00 Ls 1,000,000.00 1,000,000.00
2 Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00
4 Mobilisasi dan Demobilisasi 1.00 Ls 1,500,000.00 1,500,000.00
5 Akomodasi 1.00 Ls 1,500,000.00 1,500,000.00

B Pekerjaan Pintu & Partisi Kaca


1 Partisi Kaca Non Frameles 12mm clear tempred (inc. aksesoris) 35.46 M2 1,450,000.00 51,418,450.00
2 Pintu Kaca Koboy Non Frameles 12mm clear tempred (inc. aksesoris), Koboy 3.00 bh 5,500,000.00 16,500,000.00

C Pekerjaan Meubel
1 R. Foyer
- Meja Resepsi Bahan multipleks fin.HPL Taco 1.00 unit 5,800,000.00 5,800,000.00
- Backdrop Company Logo Bahan multipleks fin.HPL Taco 6.65 M2 1,050,000.00 6,982,500.00
- Backdrop Merah Bahan multipleks fin.HPL Taco, Cermin 5mm 6.65 M2 1,450,000.00 9,642,500.00
- Backdrop Abu-abu Bahan multipleks fin.HPL Taco, Cermin 5mm 8.40 M2 1,050,000.00 8,820,000.00
- Plafon Cokelat Bahan multipleks fin.HPL Taco 6.65 M2 1,250,000.00 8,312,500.00

D Pekerjaan Sekat
- Sekat Gudang 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 19.00 M2 350,000.00 6,650,000.00
- Sekat Ruko 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 68.40 M2 350,000.00 23,940,000.00
- Sekat Ruangan 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 58.23 M2 350,000.00 20,381,550.00

E Pekerjaan Instalasi Listrik


- Titik Lampu Kabel NYM 2x2,5 Eterna, Panasonic 17.00 Titik 210,000.00 3,570,000.00

TOTAL 167,017,500.00
Note : - Harga dapat berubah sesuai dengan perubahan spesifikasi dan volume
- Harga belum termasuk PPN 10%
RENCANA ANGGARAN BIAYA MODEL 2
Pekerjaan : Interior Kantor
Lokasi : Ruko Citra Land Makassar

HARGA JUMLAH
NO URAIAN PEKERJAAN SPESIFIKASI VOLUME
SATUAN (Rp)

A PEKERJAAN PERSIAPAN
1 Marking 1.00 Ls 1,000,000.00 1,000,000.00
2 Pembersihan Lokasi 1.00 Ls 1,000,000.00 1,000,000.00
4 Mobilisasi dan Demobilisasi 1.00 Ls 1,500,000.00 1,500,000.00
5 Akomodasi 1.00 Ls 1,500,000.00 1,500,000.00

B Pekerjaan Pintu & Partisi Kaca


1 Partisi Kaca Frameles 5mm clear non tempred (inc. aksesoris) 44.08 M2 850,000.00 37,466,300.00
2 Pintu Kaca Koboy Frameles 5mm clear non tempred (inc. aksesoris), Koboy 3.00 bh 2,500,000.00 7,500,000.00

C Pekerjaan Meubel
1 R. Foyer
- Meja Resepsi Bahan multipleks fin.HPL Taco 1.00 unit 5,800,000.00 5,800,000.00
- Backdrop Company Logo Bahan multipleks fin.HPL Taco 6.65 M2 1,050,000.00 6,982,500.00
- Backdrop Merah Bahan multipleks fin.HPL Taco, Cermin 5mm 6.65 M2 1,450,000.00 9,642,500.00
- Backdrop Abu-abu Bahan multipleks fin.HPL Taco, Cermin 5mm 8.40 M2 1,050,000.00 8,820,000.00
- Plafon Cokelat Bahan multipleks fin.HPL Taco 6.65 M2 1,250,000.00 8,312,500.00

D Pekerjaan Sekat
- Sekat Gudang 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 19.00 M2 350,000.00 6,650,000.00
- Sekat Ruko 2 Sisi + Cat Hollo 4/4,2/4,papan gyp elepht/setara,cat ex.catilax/setara 68.40 M2 350,000.00 23,940,000.00

E Pekerjaan Instalasi Listrik


- Titik Lampu Kabel NYM 2x2,5 Eterna, Panasonic 17.00 Titik 210,000.00 3,570,000.00

TOTAL 123,683,800.00
Note : - Harga dapat berubah sesuai dengan perubahan spesifikasi dan volume
- Harga belum termasuk PPN 10%
ALTERNATIF 1
NO URAIAN TOTAL
1 Pekerjaan A 8,500,000.00
2 Pekerjaan B 81,840,000.00
3 Pekerjaan C 58,975,000.00
4 Pekerjaan D 27,141,000.00
5 Pekerjaan E 4,250,000.00
TOTAL 180,706,000.00
PREDIKSI COST 137,620,000.00
MARGIN HOPE 43,086,000.00

ALTERNATIF 2 - Pekerjaan B & C di discount


NO URAIAN TOTAL
1 Pekerjaan A 8,500,000.00
2 Pekerjaan B 81,840,000.00
3 Pekerjaan C 58,975,000.00
4 Pekerjaan D 27,141,000.00
5 Pekerjaan E 4,250,000.00
TOTAL 180,706,000.00
PREDIKSI COST 137,620,000.00
MARGIN HOPE 43,086,000.00

ALTERNATIF 2 - harga paling aman


NO URAIAN TOTAL
1 Pekerjaan A 8,500,000.00
2 Pekerjaan B 81,840,000.00
3 Pekerjaan C 58,975,000.00
4 Pekerjaan D 27,141,000.00
5 Pekerjaan E 4,250,000.00
TOTAL 180,706,000.00
PREDIKSI COST 137,620,000.00
MARGIN HOPE 43,086,000.00

ALTERNATIF 4 - Banting harga


NO URAIAN TOTAL
1 Pekerjaan A 81,840,000.00
2 Pekerjaan B 58,975,000.00
3 Pekerjaan C 27,141,000.00
4 Pekerjaan D 4,250,000.00
5 Pekerjaan E 180,706,000.00
TOTAL 352,912,000.00
PREDIKSI COST 137,620,000.00
MARGIN HOPE 215,292,000.00