Professional Documents
Culture Documents
It is hereby informed that posting links to any companies or posting any ads in the website as comments will be immediately removed and further posting will lead to blocking of the person to
post any ads to this site, Contact: premmohantkmce@yahoo.in
Add your civil engineering seminar reports to the top civil engg seminar blog and let the world see it. Contact for more details and send your report to:
premmohantkmce@yahoo.in
Moreover, you can get paid when the pageviews of your report reach a threshold limit.
MIVAN TECHNOLOGY
1. INTRODUCTION
Formwork is defined as temporary structure whose purpose is to provide support and containment for fresh concrete until it can support itself. It
moulds the concrete to the desired shape and size and controls its position and alignment. The development of formworks is parallel with the growth of
concrete construction throughout the 20th century. The advancement of technology, increase of population and the space limitation lead the way to construct
high-rise buildings. But the task was not very easy at the beginning but now the man made the task easy by inventing new machinery and new techniques.
The most important factor in terms of cost, quality and speed in a high-rise building construction project is the type of the formwork used in the project. The
first formwork type to be used is the conventional type formwork where the timber planks were supported on timber columns. With the advancement of
technology it developed gradually and people used ply wood sheets instead of timber planks and steel pipes with jacks were used to support the ply wood.
Then people invented small units of formworks and connect the repeating units in the construction. The larger units were invented like formworks for slab
panels, formworks for columns, beams etc. when the same elements are repeating. Then finally the whole system of formwork is made and initially the
material used to it was steel and it was very heavy. Then the aim was to reduce the weight of the system and the materials for formwork have extended to
aluminium, plastic, fibre glass etc. Multi-Bagge
Aluminium formwork system provides aluminium formwork for RCC load bearing or RCC framed multi-storied buildings and enables the walls and
slabs to be poured in same operation. These increases efficiency and also produces an extraordinarily strong structure with excellent concrete finish. Due to
the fine tolerance achieved in the machined metal formwork components, consistent concrete shapes and finishes are obtained floor after floor. This allows Earn 100% Pro
plumbing and electrical fittings to be prefabricated with the certain knowledge that there will be an exact fit when assembled. As described by the Months - Join
manufacturers a low-cost system for housing using aluminium formwork. Aluminium formwork system is construction system for forming cast in place
No Advance P
concrete structure of building. It is also a system for scheduling and controlling the work of other construction trends such as steel reinforcement, concrete
placement and mechanical and electrical conduits. This type of construction requires a restructuring of the entire conventional construction process to enable
interaction between the design phase and production planning in order to improve and speed up the construction. The speed of construction by this system
will surpass speed of most of the other construction method.
2. INNOVATION IN CONSTRUCTION
The traditional mode of construction for individual houses comprising load bearing walls with an appropriate roof above or reinforced concrete (RC)
framed structure construction with infill masonry walls would be totally inadequate for mass housing construction industry in view of the rapid rate of
construction. Further, such constructions are prone to poor quality control even in case of contractors with substantial resources and experience.
Multi-Bagge
“For undertaking mass housing works, it is necessary to have innovative technologies which are capable of fast rate construction and are able to
deliver good quality and durable structure in cost effective manner”.
Several systems are adopted at different places in the world; eventually the systems which are reasonably economical and easy for operation with
Earn 100% Pro
Months - Join
skilled labor are useful in India. Certain systems are in vogue and more and more contractors are trying to bring in new technologies. These are essentially
No Advance P
based on the basis of mode of construction, namely, pre-cast construction or in-situ construction.
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 1/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
An engineered system of building construction, namely “3-S” system was developed by B.G.SHIRKE CONSTRUCTION TECH LTD., for achieving,
speed, strength, safety and economy in construction practices. The system involves structural elements such as pre-cast hollow column shells pre-cast My plans?
concrete beams, light weighed reinforced cellular autoclaved concrete slabs for floor and roofs constituting the basic structural formwork. The “3-S” system No plans.
involves activities for construction of building such as:
I. Cast in-situ sub-structure including foundations, stem columns, plinth beams, plinth masonry.
II. Erection of partial pre-cast components, jointing of these components using cast in-situ concrete with appropriate reinforcement.
III. Lying of reinforced cast in-situ screed over slab panels, construction of panels, construction of walling, flooring, plastering, water proofing etc.
Achieving the “3-S” system in the MIVAN formwork is quite easy. MIVAN formwork has got the unsurpassed speed of construction due to saving time for
required time in masonry and plastering. The strength of raw aluminium is very less but when alloyed with other materials prove to be strong enough to use
as a formwork. To ensure safety in the site, an integrated safety/ working platform is developed which ensures labor safety during erection and striking of the
formwork. Economy is also one of the main factors of any system. The MIVAN formwork proves to cost efficient as it can be used efficiently for 250 times.
3. FORMWORK
When concrete is placed, it is in plastic state. It requires to be supported by temporary supports and castings of desired shape till it becomes
sufficiently strong to support its own weight. This temporary casing is known as the formwork or forms or shuttering. The term moulds is sometimes used to
indicate formwork of relatively small units such as lintels, cornices etc.
* Book before 19 September 2017; Travel until 31 Dec 2017; T&C apply.
a) TIMBER FORMWORK
Timber is required for practically all jobs of formwork. The timber bring used for formwork must satisfy the following requirements. It should be durable
and treatable. It should have sufficient strength characteristics. It should be light weight and well seasoned without warping. It should hold nails well. It is
economical for small construction jobs. It is design flexible and easy to erect. It has good thermal insulation which makes it useful to be used in colder
Regions. It can easily be made into any shape or size. And it is easy for transporting purpose for in between sites.
b) STEEL FORMWORK
Mostly used in large construction projects or in situations where large number of re-uses of the same shuttering is possible. It is Suitable for circular
or curved shaped structures such as tanks, columns, chimneys etc. and also used for structures like sewer tunnel and retaining wall. Strong, durable & have
longer life. Reuses can be assumed to vary from 100 to 120 wares timber varies from 10 to 12.Steel can be installed & dismantled with greater ease & speed GATE 2018 Civil
resulting in saving in labour cost. Excellent quality of exposed concrete surface obtained. No danger of formwork absorbing water from the concrete and Engineering...
minimizing honeycombing. INR 318.00
Shop now
Total Pageviews
7 3
Blog Archive
Fig 3.2 Steel Formwork
► 2011 (17)
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 2/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
disadvantage of using plastic forms is that it does not lend itself to field fabrication hence, the design and planning of this form must be carefully carried out.
BACTERIAL C
Also care must take not to damage the plastic by the heat applied for accelerated curing of the concrete. Trough and waffle units in fiberglass are used in
TWO STAGE M
construction of large floor areas and multistoried office buildings.
ARCHITECHT
CONSTRUC
PRON...
GEOPOLYMER
DEMOLITION
FIBRE REINFO
COMPOSIT
DOUBLE SKIN
MIVAN TECHN
SELF CLEANI
PERVIOUS CO
Fig 3.3 Plastic Formwork
PHOSPHOGY
d) ALUMINIUM FORMWORK SKY BUS TEC
Forms made from aluminum are in many respects similar to those made of steel. However, because of their lower density, aluminum forms are lighter SOLAR PANEL
than steel forms, and this is their primary advantage when compared to steel. As the strength of aluminum in handling, tension and compression is less than
SUBMERGED
the strength of steel, it is necessary to use large sections. The formwork turns out to be economical if large numbers of reuses are made in construction. The TUNNEL
major disadvantage of aluminum forms is that no changes can be made once the formwork is fabricated.
TRANSPAREN
LIST OF SEMI
► 2017 (21)
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 3/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
The formwork system is precisely-engineered system fabricated in aluminium. Using this system, all the elements of a building namely, load bearing
walls, columns, beams, floor slabs, stairs, balconies etc can be constructed with cast in place concrete. The resulting structure has a good quality surface
finish and accurate dimensional tolerances. Further, the construction speed is high and the work can be done in a cost effective manner.
The modular nature of the formwork system allows easy fixing and removal of formwork and the construction can proceed speedily with very little My pla
deviation in dimensional tolerances. Further, the system is quite flexible and can be easily adapted for any variations in the layout.
The availability of concrete from ready mix concrete facility has augured well for the use of this work system. However, the proliferation of RMC No pla
facilities in the cities in India and the willingness to use mechanized means of transport and placing of concrete, the use of aluminium formwork system has
received a boost. The quality of the resulting concrete is found to be superior.
Structurally speaking, the adoption of the closed box system using monolithic concrete construction has been found to be the most efficient
alternatives. The stresses in both the concrete and steel are observed to be much lower even when horizontal forces due to wind or earthquake are taken
into consideration.
The formwork system can be used for construction for all types of concrete systems, that is, for a framed structure involving column beam –slab
elements or for box-type structure involving slab-walls combination.
* Book before 19 September 2017; Travel until 31 Dec 2017; T&C apply.
used in the construction.
1) Wall Panel: - It forms the face of the wall. It is an Aluminium sheet properly cut to fit the exact size of the wall
* Book before 19 September 2017; Travel until 31 Dec 2017; T&C apply.
FIG 4.2 ROCKER
3) Kicker: - It forms the wall face at the top of the panels and acts as a ledge to support.
4) Stub Pin: - It helps in joining two wall panels. It helps in joining two joints
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 4/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
1) Beam Side Panel: - It forms the side of the beams. It is a rectangular structure and is cut according to the size of the beam
2) Prop Head for Soffit Beam: - It forms the soffit beam. It is a V-shaped head for easy dislodging of the formwork.
3) Beam Soffit Panel: - It supports the soffit beam. It is a plain rectangular structure of aluminium.
4) Beam Soffit Bulkhead: - It is the bulkhead for beam. It carries most of the bulk load.
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 5/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
1) Deck Panel: - It forms the horizontal surface for casting of slabs. It is built for proper safety of workers.
2) Deck Prop: - It forms a V-shaped prop head. It supports the deck and bears the load coming on the deck panel.
3) Prop Length: - It is the length of the prop. It depends upon the length of the slab.
4) Deck Mid – Beam: - It supports the middle portion of the beam. It holds the concrete.
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 6/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
5) Soffit Length: - It provides support to the edge of the deck panels at their perimeter of the room.
6) Deck Beam Bar: - It is the deck for the beam. This component supports the deck and beam.
1) Internal Soffit Corner: - It forms the vertical internal corner between the walls and the beams, slabs, and the horizontal internal cornice between the walls
and the beam slabs and the beam soffit.
2) External Soffit Corner: - It forms the external corner between the components
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 7/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
4) Internal Corner: - It connects two pieces of vertical formwork pieces at their exterior intersections.
i. All formwork should be cleaned and coated with approved realize agent.
ii. Ensure wall formwork is erected to the setting out lines.
iii. Check all openings are of correct dimensions, not twist.
iv. Check all horizontal formwork (deck soffit, and beam soffit etc.) in level.
v. Ensure deck and beam props are vertical and there is vertical movement in the prop lengths.
vi. Check wall ties, pins and wedges are all in position and secure.
vii. Any surplus material or items to be cleared from the area to be cast.
viii. Ensure working platform brackets are securely fastened to the concrete.
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 8/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
4.4.4 CLEANING:
All components should be cleaned with scrapers and wire brushes as soon as they are struck. Wire brush is to be used on side rails only. The longer
cleaning is delayed, the more difficult the task will be. It is usually best to clean panels in the area where they are struck.
4.4.5 TRANSPORTING:
There are basic three methods recommended when transporting to the next floor:
i. The heaviest and the longest, which is a full height wall panel, can be carried up the nearest stairway.
ii. Passes through void areas.
iii. Rose through slots specially formed in the floor slab for this purpose. Once they have served their purpose they are closed by casting in concrete filter
4.4.6 STRIKING:
Once cleaned and transported to the next point of erection, panels should be stacked at right place and in right order. Proper stacking is a clean sign
of a wall – managed operation greatly aids the next sequence of erection as well as prevents clutters and impend other activities
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 9/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 10/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
Day 1: -The first activity consists of erection of vertical reinforcement bars and one side of the vertical formwork for the entire floor or a part of one floor.
Day 2: -The second activity involves erection of the second side of the vertical formwork and formwork for the floor
Day 3: - Fixing reinforcement bars for floor slabs and casting of walls and slabs.
Day 4: -Removal of vertical form work panels after 24hours, leaving the props in place for 7 days and floor slab formwork in place for 2.5 days.
3) Cycle Time
High speed of construction can be achieved by this system that means faster completion of project. 7 Days per floor.
4) Striking time
• Vertical (Wall) Formwork – 12 hours after concreting or when concrete strength has reached 2N/mm2.
• Horizontal (Deck) Formwork – 36 hours after concreting or when concrete strength has reached 10N/mm2.
5) Pouring System
Monolithic pouring for:
• Slabs
• Walls
• Columns
• Beams
6) Durability
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 11/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
OR
ii) RC load-bearing walls and slabs.
In the case of RC moment-resisting framed structures, the horizontal forces due to wind or earthquake are resisted by the frames resulting in the
bending moments in columns to resist bending moment and vertical loads would be more than that required to resist vertical loads without bending moment.
Similarly, additional reinforcement will be required in beams at supports. In the case of RC load-bearing walls, monolithic casting of slab along with RC walls
results in a box type structure, which is very strong in resisting horizontal forces due to wind or earthquake. In view of large depth of shear walls, the resulting
stresses due to bending moment and vertical loads are smaller and in many cases, concrete alone is capable of resisting these forces.
On evaluating these alternatives, it is seen that the beam column frame system in
i) Performs poorly against earthquake forces compared to RCC wall and slab construction. Recent changes in the IS Codes, as well as
recommended good practice demand provision of additional reinforcement comply with ductility requirements.
ii) The sizing and detailing of columns needed to be –that they are 20% stronger than beams they support.
4.8 ECONOMY
The cost per flat (or per m² built up area) using MIVAN shuttering system depends upon the number of repetition and period of completion of the
project. As the formwork can be reused over 250 times, the initial cost per unit of forming area is less when compared to traditional methods. The reduction of
cost is also due to the elimination of brickwork and plaster and also due to reduction in time. The cost of the project gets substantially reduced due to shear
wall construction. These are due to the reduced consumption of steel, masonry, and plaster even though the use of concrete decreases. For the same
number of repetition, the cost will be less if the period of completion is longer. This is because for a shorter completion period, the area of formwork is more
than required for longer completion period. Cost of formwork is illustrated in Table 4.1.
The aluminium formwork provides an integrated scaffolding system which reduces the cost of scaffolding requirements. The mechanical and
electrical installation is simplified as conduits are embedded in the structure by precise engineering of outlets and service ducts. Thus, we can conclude that
the overall cost of the project is lesser when compared to project using traditional methods of formwork.
Following the graphical representation of the above study of rates at the different rates of formwork. The chart shows the aluminium formwork is
economical when the use of cycle. The steel formwork is economical than the other formwork.
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 12/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 13/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 14/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
By using admixture the workability of concrete is increased by 120 % whereas the strength of concrete is increased by 13 %
6.1 Advantages:
The MIVAN formwork is specifically designed to allow rapid construction of all types of architectural layouts.
1) Total system forms the complete concrete structure.
2) Custom designed to suit project requirements.
3) Unsurpassed construction speed.
4) High quality finish.
5) Cost effective.
6) Panels can be reused up to 250 times.
7) Erected using unskilled labor.
Quality and speed must be given due consideration along with economy. Good quality construction will never deter to projects speed nor should it be
uneconomical. In fact, time consuming repairs and modifications due to poor quality work generally delay the job and cause additional financial impact on the
project. Some experts feel that housing alternatives with low maintenance requirements may be preferred even if the initial cost is high.
1) Because of small sizes finishing lines are seen on the concrete surfaces.
2) Concealed services become difficult due to small thickness of components.
3) It requires uniform planning as well as uniform elevations to be cost effective.
4) Modifications are not possible as all members are caste in RCC.
5) Large volume of work is necessary to be cost effective i.e. at least 200 repetitions of the forms should be possible at work.
6) The formwork requires number of spacer, wall ties etc. which are placed @ 2 feet c/c; these create problems such as seepage, leakages during monsoon.
7) Due to box-type construction shrinkage cracks are likely to appear.
8) Heat of Hydration is high due to shear walls.
7. CONCLUSION
The task of housing due to the rising population of the country is becoming increasingly monumental. In terms of technical capabilities to face this
challenge, the potential is enormous; it only needs to be judiciously exploited.
Civil engineers not only build but also enhance the quality of life. Their creativity and technical skill help to plan, design, construct and operate the
facilities essential to life. It is important for civil engineers to gain and harness the potent and versatile construction tools.
Traditionally, construction firms all over the world have been slow to adopt the innovation and changes. Contractors are a conservative lot. It is the
need of time to analyze the depth of the problem and find effective solutions. MIVAN serves as a cost effective and efficient tool to solve the problems of the
mega housing project all over the world. MIVAN aims to maximize the use of modern construction techniques and equipments on its entire project.
We have tried to cover each and every aspect related to aluminium (MIVAN) form construction. We thus infer that MIVAN form construction is able to
provide high quality construction at unbelievable speed and at reasonable cost. This technology has great potential for application in India to provide
affordable housing to its rising population.
Thus it can be concluded that quality and speed must be given due consideration with regards to economy. Good quality construction will never deter
to projects speed nor will it be uneconomical. In fact time consuming repairs and modification due to poor quality work generally delay the job and cause
additional financial impact on the project. Some experts feel that housing alternatives with low maintenance requirements may be preferred even if at the
slightly may preferred even if at the higher initial cost.
REFERENCES
1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE), Miss. Patil Dhanashri Suryakant1 , Prof. Desai D B
2. International Journal of Innovative Research in Science, Engineering and Technology Vol. 3, Issue 6, June 2014, Patel Abhiyan S, Neeraj Sharma D,
Bhavin K Kashiyani.
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 15/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
3. International Journal of Innovations In Engineering Research And Technology [IJERT] issn: 2394-3696 volume 2, issue 3 march2015, Mr. Shankar Bimal
Banerjee.
4 Jain and Jain., “(1993)”. “Design of Formwork”. “Design of Concrete Structures.”, Edition 1993, pp 595-606.
5. Kulkarni., D., V., “(2001)”. “ First Rate Forms”. “Times Journal Construction and Design”. Oct-Dec 2001, pp 22-23.
6. International Journal of Engineering and Technical Research, Kushal Patil, Ajitkumar Jadhav, Nikhil Shingate
4 comments:
Thank you for a great article. The plastic formwork picture used in this article is that of our moladi plastic formwork system. Pity no mention or credit was given.
Secondly, the disadvantage of using plastic forms is that it does not lend itself to field fabrication. This is not the case with moladi as the components are small and
are assembled on site or field with ease and can also be removed and replaced if required Plastic is moulded at temperatures above 220 deg Celsius, Cement
kicking off will therefore not have any negative effect on the plastic formwork.
Reply
Replies
Reply
What is the loading percentage in such construction? How to calculate the built up area if the flat carpet area is 600sqft.
Reply
Replies
As per this seminar report, carpet area will be 87.5% of plinth area. Hence plinth area corresponding to 600 sqft carpet area will be around 600/0.875 =
686 sqft.
First question is not clear.
Reply
Publish Preview
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 16/17
9/18/2017 CIVIL ENGINEERING SEMINAR TOPICS: MIVAN TECHNOLOGY
http://civilenggseminar.blogspot.in/2016/06/mivan-technology.html 17/17