In order to make sure you have all the information you need, we have included a Product Catalogue and
a Roofing Repair Guide with this Technical Manual.
The Product Catalogue outlines all SOPREMA products available for completing a roofing project in
its entirety.
Available online
All technical documentation, including this technical manual, data sheets, details, specifications and
technical bulletins are available online at www.soprema.ca, in the Technical References section.
We invite you to visit www.soprema.ca regularly to obtain our most recent updates.
In a just few minutes, you can easily find the best roofing system for your project from SOPREMA’s
multiple solutions. All roofing solutions are presented according to the type of deck, the roofing system
specified and the membrane system application method. This classification helps you choose the best
roofing system for your project.
With the goal of building sustainable roofing systems, SOPREMA favours conventional systems
(granulated finish), which allow for quick resurfacing during repair work. They also have other benefits
during installation and for their entire lifespan, especially:
LEED®
STEEL DECK
• BALLASTED
Vapour barrier
Insulation and support panels
Membrane systems
• INVERTED
Membrane systems
CONCRETE DECK
• BALLASTED
Vapour barrier
Insulation and support panels
Membrane systems
• INVERTED
Membrane systems
WOOD DECK
• BALLASTED
Vapour barrier
Insulation and support panels
Membrane systems
• INVERTED
Membrane systems
WITHOUT INSULATION
UNDERLAYMENT PROTECTION
ACCESSORY PRODUCTS
TECHNICAL REFERENCES
1.0.1 The information and specifications contained in this manual are intended to assist in selecting appropriate
roofing systems. Soprema Inc. believes the design and construction of the buildings which receive these products
are best left to the owner, architect and/or contractor. We stress that to obtain a roofing system that will perform
properly, workmanship is equally as important as the use of quality materials properly designed into a good roofing
specification. The most perfectly manufactured product cannot perform its function if it is not properly installed. The
recommendations which are contained in this manual cannot substitute for the knowledge, skill, experience and
integrity expected of a qualified professional roofing contractor or the technical expertise of trained architects and
engineers. It is recommended that the user become familiar with all the relevant material included in this manual
before selecting or installing a particular roof specification.
1.0.2 SOPREMA Inc. is not responsible for and will not accept, under any circumstances, any responsibility for the
adequacy of a building design, including adequacy of any structure supporting the weight of any roofing system. Review
of the plans and specifications by a SOPREMA Inc. representative shall be for the sole purpose of making suggestions
or recommendations concerning details for the application of SOPREMA Inc. roofing systems and products.
1.0.3 We reserve, at our discretion and without prior notice, the right to change or modify any of the information,
recommendations or specifications in this publication. The enclosed recommendations and requirements are directed
to SOPREMA Inc. materials used in the roofing system and to the details of construction which directly affect the
application of the SOPREMA Inc. roofing membrane system and its performance.
1.0.4 SOPREMA Inc. does not assume responsibility for decisions as to when and where vapour retarder systems or
special attachment procedures are advisable. When such decisions are factors, the recommendations and procedures
outlined in this manual are to be used as guidelines only, and shall not be taken as an express or implied warranty to
fit a particular purpose, which SOPREMA Inc. expressly disclaims.
1.0.5 Under no circumstances will SOPREMA Inc. be responsible for any failure of the roofing system due to structural
defects, damage from other building trades or for failure due to errors in design of any building element.
1.0.6 Because all the factors creating abnormal wind conditions on a roof cannot be anticipated by SOPREMA Inc.,
we do not accept wind damage liability.
1.0.7 SOPREMA Inc. is only responsible for its own products, and this, within the conditions and limits of the law.
SOPREMA Inc. shall not incur any responsibility for possible damage or prejudice resulting from the application of
products:
- having been alterated in any way;
- contrarily to principle, standards, and/or specifications of SOPREMA Inc.
in force at the date of delivery.
1.1 Introduction
1.1.1 This manual has been prepared by SOPREMA Inc. for architects, engineers, building owners, and roofing
contractors, as a reference guide in designing, selecting and constructing roofing systems utilizing SOPREMA Inc.
roofing product.
1.1.2 The specifications contained in this manual are designed for “normal” and “typical” conditions. If non-standard
substrates or unusual shapes such as domes, etc., are to be roofed, consultation with SOPREMA Inc. is recommended
regarding appropriate methods of application.
1.1.3 No manual can explicitly cover every detail of a particular roofing system nor anticipate all new products,
roof decks, or building designs. If an unusual condition is encountered that is not explained in this manual, contact
SOPREMA Inc.
1.1.4 All information and specifications contained in this manual supersede all prior data published by SOPREMA Inc.
We reserve the right to change, or modify, at our discretion, without prior notice, any of the information,
recommendations, or specifications contained in this manual. In the case of dispute, the following will be the priority
order of documentation: Technical Data Sheets, Master Specifications, Roofers Guide and Technical Specifications.
1.1.5 The physical properties and characteristics of SOPREMA Inc. products as published in this manual represent
typical, average values obtained in accordance with accepted test methods conducted under controlled laboratory
test conditions. They are subject to normal manufacturing variations and could change without notice.
1.1.6 FIRE SAFETY: It is the responsibility of the installer contractor to become familiar with and abide by all fire safety
regulations applicable and as laid out by the authority having jurisdiction in the location were the work is taking
place. SOPREMA Inc. recommends the use of products and systems designed to reduce the risk of fire. Consult a
SOPREMA Inc. representative for information on these products.
1.1.7 SOPREMA’s complementary line of sealants, mastics, adhesives and primers must always be used jointly with
membranes manufactured by SOPREMA Inc. SOPREMA Inc. assumes no responsibility for damages as a result of
products manufactured or modified by others when used in conjunction with our membrane systems.
1.1.8 Consult the SOPREMA Inc. Roofers Guide for information concerning the application of our materials. Particular
reference should be made to the section, SAFETY MEASURES at the end of the guide.
1.1.9 Any representations, advice, or technical information made by a representative of SOPREMA Inc. shall be subject
to all notices and warnings as stated previously on this notice.
1.1.10 SOPREMA Inc. carries out site visits to aid and assist the installer and review the installation of it’s products
at the time of the visit. These visits should not be considered the final assessment of the installation. SOPREMA Inc.
recommends the services of a professional inspection firm to monitor the installation of the entire roofing system.
1.1.11 All of the 3-D coloured illustrations in this manual are for the purpose of demonstrating a similitude of the roof
construction system described. These illustrations must not be used as true construction details.
SOPREMA, the standard in the waterproofing industry
SOPREMA is an international manufacturing business specialized in making waterproofing products
for the building and civil engineering sectors. Founded in 1908 in Strasbourg, France, SOPREMA now
operates in more than 80 countries.
SOPREMA established operations in Canada in 1978, opening its first production facility and head office
in Drummondville, Quebec in 1984. The Canadian division has shown remarkable growth, and now
includes six North American production facilities manufacturing a wide variety of building envelope
products for industrial, commercial, institutional and residential construction.
SOPREMA has been standing out from the competition with its 100 years roofing system
The design and specifications of today’s roofing systems must take into account the issues of energy
conservation, sustainability, optimal utilization of raw materials and waste reduction. One innovative
SOPREMA solution in this area consists of the re-covering of an existing waterproofing system. This
approach helps prolong the useful life of the roof and reduces the quantity of materials sent to
landfill sites.
Good design, selection of quality materials and proper installation are essential when recovering a
roofing system.
For more information on this subject, consult the Roofing Repair Guide found in this manual.
BEFORE
AFTER
INNOVATION
TECHNICAL SUPPORT
ENVIRONMENT
EN 16001, the standard for energy management systems, guarantees that SOPREMA is complying with
the most recent practices in the area of energy management. Furthermore, its plant in Drummondville, Qc
was the first site in Canada and the first in the SOPREMA group to have successfully completed the
accreditation process for the EN 16001 standard.
SOPREMA has worked for over 20 years to limit the impact of its products and its industrial activities on
the environment and human health through all stages of a building’s life cycle (construction, operation
and demolition).
SOPREMA’S R&D teams work closely with international, private and public research laboratories to
develop innovative solutions that meet new industry requirements.
SOPREMA created the Eco Struction logo to identify its environmentally friendly
products and services.
SOPREMA chose the Ginkgo biloba leaf to symbolize its environmental initiative.
This extremely ancient tree represents sustainability, health, resistance to
aggression, endurance in the face of environmental stress and aesthetics.
BITUMEN
Roofing system Life Repair projects Weight of the system Materials Consumed Potential landfill waste
expectancy for roofing older than (tonnes)** (tonnes)
(years)* 40 years
Ballasted EPDM 13 3.08 17.3 kg/m (11.6 lb/ft) 4,441,816 t (4,897,261 tons) 2,220,907 t (2,448,630 tons)
Multi-ply 16 2.50 11 kg/m (7.4 lb//ft) 2,302,277 t (2,538,343 tons) 1,151,139 t (1,269,172 tons)
Modified bitumen 21 1.90 4.8 kg/m (3.2 lb/ft) 758,536 t (836,314 tons) 379,267 t (418,156 tons)
PVC/TPO 13 3.08 2.5 kg/m (1.7 lb/ft) 650,956 t (717,702 tons) 295,268 t (325,544 tons)
SOPREMA waterproofing membranes are manufactured with three types of reinforcement. A good
roofing system always combines the strengths of each reinforcement type to maximize its properties
and effectively resist roofing movement caused by the drastic temperature extremes of the North
American climate.
COMPOSITE
This three-ply woven polyethylene resists UV rays for up to 90 days, and its anti-skid
surface helps ensure worker safety during installation. As with the reinforcements
described above, this material is very flexible and reacts very well to movement.
DUO SELVEDGE TECHNOLOGY
GRANULATED OTHER
* Some colours are available by special order and require longer delivery times.
Ask your representative for more details.
HIGH PERFORMANCE SYSTEMS
SOPREMA High Performance Roofing/waterproofing systems were designed with one basic criteria
in mind: durability. All these systems are composed of at least one membrane manufactured with
robust composite reinforcement providing the best resistance to movements caused by temperature
variations.
TRAFFIC CAP sheet membranes of the High Performance roofing waterproofing systems are
manufactured with a composite reinforcement that makes them even stronger and more weather
resistant.
Composite reinforcement used in manufacturing membranes for our High Performance systems are
subject to standard ASTM D6162.
SOPREMA provides several membrane combinations in every section of the manual, to build the
waterproofing system tailored to your project. The High Performance logo helps you to discover
SOPREMA’s optimum solution.
You can also discover the benefits of the PLATINUM PRIVILEGE warranty, specific to High
Performance membranes.
XPRESS Heat-welded
Ideal for recovering work With SEBS hot bitumen
Mechanically fastened With adhesive
Self-adhesive
With cold adhesive
SOPRASTAR Heat-welded
Ideal to reduce urban With SEBS hot bitumen Heat-welded
heat island effect With adhesive Self-adhesive
Self-adhesive With SEBS hot bitumen
Mechanically fastened
WARRANTIES
This section concerns certification of SOPREMA Inc. roofing systems obtained from the Underwriters
Laboratories of Canada (ULC). This certification arises from the requirements of Section 3, Article 3.15.1,
of the National Building Code of Canada, which stipulates that roofing systems must be tested according
to the testing procedure in standard CAN/ULC S-107 M87 “Standard test methods for fire tests of roof
coverings.”
Standard ULC S-107 categorizes roofing systems according to their fire resistance performance into three
distinct categories: A, B and C. The National Building Code of Canada requires that roofing systems meet
one of these classifications to comply with the requirements cited in Section 3. SOPREMA systems are
listed at ULC according to classification and are available at www.ulc.ca.
Once you are on the website, here are a few easy steps that you can take to find SOPREMA roofing
systems:
5. Click on the TGFUC.R19921 link, which corresponds to the SOPREMA Inc. file.
This section deals with roofing systems tested in accordance with CSA A123.21-04 Standard Test Method
for Dynamic Wind Uplift Resistance of Mechanically Attached Membrane Roofing Systems.
SOPREMA roofing systems are tested in several combinations and under different pressures. Moreover,
contrary to the Factory Mutual (FM) publications, there is no minimum for the published pressures.
Systems tested in accordance with the CSA A123.21 standard that have satisfied its requirements are
listed under the CSA A123.21-04 tab on the Laboratoires Shermont website (www.labo-shermont.com).
APPROVALS
This section concerns certification of SOPREMA Inc. roofing systems by the Factory Mutual (FM)
Insurance Company. This certification is related to standard 4470 developed by FM that was designed
to evaluate the performance of roofing systems with respect to pressure exerted by wind on buildings.
The pressure exerted during the 4470 standard simulation tests is static.
SOPREMA roofing systems are certified in several possible combinations with various exerted pressures.
Minimum acceptable pressure for the FM standard is 60 psf (2.87 kPa). Our systems are listed for steel
and concrete decks.
Systems that have received FM certification are entered in the RoofNav database that lists all roofing
systems from various manufacturers. This database can be found at www.roofnav.com. For more
information, please ask to your technical representative.
CERTIFICATIONS
Management systems are ISO 9001 certified for quality and ISO 14001 for the environment.
STANDARDS
The number of private and governmental organizations that are adopting LEED® certification in their
policies, programs and operations is growing. They are adopting LEED® with the objective of achieving
and demonstrating sustainability. Their reasons for certification may include:
Please note that the solutions proposed in this LEED® section of the binder are only intended as
suggestions. SOPREMA strongly recommends that you involve a LEED® accredited professional
(LEED® AP) as a resource person who can recognize and confirm the efforts needed to obtain LEED®
credits. These experts will be able to advise you and simplify the steps involved in the inscription and
certification process.
We invite you to visit www.soprema.ca/leed to learn about the LEED® solutions proposed by SOPREMA.
In the TECHNICAL REFERENCES section of the website, you will also be able to consult the LEED® product
data sheets.
EXISTING BUILDINGS
The LEED® credit system is divided into several sections. Here are the categories in which SOPREMA
products can contribute:
Indoor Environmental Quality (IEQ) IEQ Credit 3.2 Possible points (1)
LEED®: new construction and major renovations (LEED® NC) and core and shell buildings (LEED® CS)
The LEED® point system is divided into several sections. Here are the categories in which SOPREMA
products can contribute:
STEEL
Cold adhesive
• Vapour barrier
• Insulation and support panels
• Membrane systems
Self-adhesive
• Vapour barrier
• Insulation and support panels
• Membrane systems
Mechanically fastened
• Vapour barrier
• Insulation and support panels
SUMMARY
• Membrane systems
Composite panels
• Vapour barrier
• Insulation and support panels
• Membrane systems
Heat-welded
• Vapour barrier
• Insulation and support panels
• Membrane systems
Multi II
• Vapour barrier
• Insulation and support panels
• Membrane systems
BALLASTED
• Vapour barrier
• Insulation and support panels
• Membrane systems
INVERTED
• Membrane systems
GRANULAR CAP SHEET
(self-protected)
GRANULAR CAP SHEET
(self-protected)
GRANULAR
CAP SHEET
SELF-PROTECTED
GRANULATED FINISH (self-protected)
Cold adhesive
• Vapour barrier
• Insulation and support panels
• Membrane systems
Self-adhesive
• Vapour barrier
• Insulation and support panels
• Membrane systems
Mechanically fastened
• Vapour barrier
• Insulation and support panels
• Membrane systems
Composite panels
• Vapour barrier
• Insulation and support panels
• Membrane systems
GRANULAR
Heat-welded
• Vapour barrier
• Insulation and support panels
• Membrane systems
CAP SHEET
SELF-PROTECTED
COLD ADHESIVE
COLD ADHESIVE
COLD
ADHESIVE
Sopravap’R
Steel deck
STEP 1 — Vapour barrier
Steel deck
Xpress Board Sanded
Elastocol 500
Steel deck
VAPOUR BARRIER – STEEL DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive Optional Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None None Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None None XPRESS BOARD panels can be installed directly
¾ minimum on all types of deck. The last 25 mm (1 in)
of longitudinal overlap must be heat-welded.
The transversal overlap must by covered
with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
COLPLY BASE 410 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 40 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 100 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
BARAL Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
Sopraboard
Colgrip B
Sopravap’R
Duotack
Steel deck
Soprarock DD Plus
STEP 2 — Insulation and support panels
Steel deck
Xpress Board Sanded
Sopraboard
Colgrip B
Elastophene SP 2.2
Gypsum
Elastocol 500
Steel deck
INSULATION AND SUPPORT PANELS – STEEL DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraboard
Colgrip B
Sopravap’R
Duotack
Sopraflash Stick
Steel deck Colphene HR GR
Soprarock DD Plus
STEP 3 — Membrane systems
Steel deck
Xpress Board Sanded
Sopraflash Stick
Colphene HR GR
Elastocol Stick
Colply Traffic Cap 460
Sopraboard
Colgrip B
Elastophene SP 2.2
Gypsum
Elastocol 500
Steel deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With cold adhesive base sheet installed
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
Cold adhesive COLPLY BASE 410 Cold adhesive COLPLY TRAFFIC CAP 460
SELF-ADHESIVE
SELF-ADHESIVE
SELF-
SELF-ADHESIVE
ADHESIVE
Sopravap’R
Steel deck
STEP 1 — Vapour barrier
Steel deck
Xpress Board Sanded
Elastocol 500
Steel deck
VAPOUR BARRIER – STEEL DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive Optional Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None None Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None None XPRESS BOARD panels can be installed directly
¾ minimum on all types of deck. The last 25 mm (1 in)
of longitudinal overlap must be heat-welded.
The transversal overlap must by covered
with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
COLPLY BASE 410 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 40 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 100 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
BARAL Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
Colgrip A
Sopravap’R
Duotack
Steel deck
Sopraboard
STEP 2 — Insulation and support panels
Soprarock DD
Steel deck
Xpress Board Sanded
Sopraboard
Colgrip B
Elastophene SP 2.2
Gypsum
Elastocol 500
Steel deck
INSULATION AND SUPPORT PANELS – STEEL DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• The COLVENT 810 membrane can be installed without primer directly onto the COLGRIP A insulation.
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Soprastar Flam HD GR
Elastocol Stick
Colvent 810
Colgrip A
Sopravap’R
Duotack
Elastocol Stick
Sopraboard
Soprarock DD
STEP 3 — Membrane Systems
Steel deck
Xpress Board Sanded
Colvent 810
Elastocol Stick
Sopraboard
Colgrip B
Elastophene SP 2.2
Gypsum
Elastocol 500
Steel deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With self-adhesive base sheet
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
Self-adhesive COLPHENE HR GR
SEBS/OXIDIZED
HOT BITUMEN
SEBS/OXIDIZED
HOT
BITUMEN
SEBS/OXIDIZED
Sopravap’R
Steel deck
STEP 1 — Vapour barrier
Steel deck
Xpress Board Sanded
Elastocol 500
Steel deck
VAPOUR BARRIER – STEEL DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive Optional Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None None Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None None XPRESS BOARD panels can be installed directly
¾ minimum on all types of deck. The last 25 mm (1 in)
of longitudinal overlap must be heat-welded.
The transversal overlap must by covered
with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
COLPLY BASE 410 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 40 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 100 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
BARAL Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
Sopraboard
Colgrip B
Sopravap’R
Steel deck
Soprarock DD Plus
STEP 2 — Insulation and support panels
Steel deck
Xpress Board Sanded
Sopraboard
Colgrip B
Hot bitumen
Elastophene SP 2.2
Gypsum
Elastocol 500
Steel deck
INSULATION AND SUPPORT PANELS – STEEL DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Sopraply 510
Hot bitumen
Sopraboard
Colgrip B
Sopravap’R
Sopraflash Flam Stick
Steel deck
Colply Traffic Cap 460
Elastocol Stick Soprasphalte M
Hot bitumen
STEP 3 — Membrane systems
Elastophene PS
Soprasphalte M
Hot bitumen
Sopraboard
Colgrip B
Gypsum
Elastophene SP 2.2
Elastocol 500
Steel deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With hot bitumen base sheet installed
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
Oxidized/SEBS hot bitumen SOPRAPLY BASE 510 Heat-welded SOPRAPLY TRAFFIC CAP 560
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
MECHANICALLY
FASTENED
MECHA
NICALLY
FASTENED
Sopravap’R
Steel deck
Steel deck
Xpress Board Sanded
STEP 1 — Vapour barrier
Steel deck
Sopravap’R
VAPOUR BARRIER – STEEL DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive Optional Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None None Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None None XPRESS BOARD panels can be installed directly
¾ minimum on all types of deck. The last 25 mm (1 in)
of longitudinal overlap must be heat-welded.
The transversal overlap must by covered
with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
COLPLY BASE 410 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 40 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 100 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
BARAL Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
Colgrip B
Sopravap’R
Steel deck
Xpress Board Sanded
Sopravap’R
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
• Please refer to FM Global 1-29 LDPS or CSA A123.21 systems tested for numbers of fasteners used to attach insulation or support pannels.
SOPRAROCK MD No No Yes No
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Soprastar Flam HD GR
Elastocol Stick
Colgrip B
Sopravap’R
Unilay 750
Colgrip B
Sopravap’R
Steel deck
Elastocol Stick
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With mechanically fastened base sheet
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
* The N/A response applies to the base sheet since it is a single-ply system.
COMPOSITE PANELS
COMPOSITE
PANELS
COMPOSITE
PANELS
Sopravap’R
Steel deck
STEP 1 — Vapour barrier
Steel deck
Xpress Board Sanded
Elastophene SP 2.2
Gypsum
Elastocol 500
Steel deck
VAPOUR BARRIER – STEEL DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive Optional Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None None Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None None XPRESS BOARD panels can be installed directly
¾ minimum on all types of deck. The last 25 mm (1 in)
of longitudinal overlap must be heat-welded.
The transversal overlap must by covered
with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
COLPLY BASE 410 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 40 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 100 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
BARAL Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
Xpress Board
Colgrip B
Sopravap’R
Steel deck
Xpress ISO
STEP 2 — Insulation and support panels
Duotack
Soprabase FR 180
Duotack
Duotack Colgrip B
Elastophene SP 2.2
Gypsum
Elastocol 500
Steel deck
INSULATION AND COMPOSITE PANELS – STEEL DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Soprastar Flam HD GR
Elastocol Stick
Xpress Board
Colgrip B
Sopravap’R
Xpress ISO
STEP 3 — Membrane systems
Duotack
Soprabase FR 180
Duotack
Duotack Colgrip B
Elastophene SP 2.2
Steel deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With composite panels
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
THERMOFUSIBLE
THERMO
FUSIBLE THERMOFUSIBLE
Sopravap’R
Steel deck
STEP 1 — Vapour barrier
Steel deck
Xpress Board Sanded
Elastophene SP 2.2
Gypsum
Elastocol 500
Steel deck
VAPOUR BARRIER – STEEL DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive Optional Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None None Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None None XPRESS BOARD panels can be installed directly
¾ minimum on all types of deck. The last 25 mm (1 in)
of longitudinal overlap must be heat-welded.
The transversal overlap must by covered
with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
COLPLY BASE 410 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 40 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 100 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
BARAL Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
Sopraboard
Colgrip B
Sopravap’R
Duotack
Steel deck
Sopraboard
STEP 2 — Insulation and support panels
Colgrip B
Hot bitumen
Steel deck
Xpress Board Sanded
Soprarock DD Plus
Elastophene SP 2.2
Gypsum
Elastocol 500
Steel deck
INSULATION AND SUPPORT PANELS – STEEL DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Sopraboard
Colgrip B
Sopravap’R
Duotack
Sopraflash Flam Stick
Colgrip B
STEP 3 — Membrane systems
Hot bitumen
Steel deck
Xpress Board Sanded
Soprarock DD Plus
Elastophene SP 2.2
Gypsum
Elastocol 500
Steel deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With heat-welded base sheet
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR HD GR
SOPRASTAR FLAM WF
ASPHALT AND
GRAVEL
ASPHALT AND GRAVEL
ASPHALT
AND GRAVEL
ASPHALT AND GRAVEL (multi-ply)
Multi II
• Vapour barrier
• Insulation and support panels
• Membrane systems
ASPHALT
AND GRAVEL
MULTI II
MULTI II
MULTI II
MULTI II
Elastophene 180 Sanded
Gypsum
Soprasphalte M
Steel deck
Elastophene Sanded
STEP 1 — Vapour barrier
Gypsum
Hot bitumen
Steel deck
VAPOUR BARRIER – STEEL DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive Optional Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None None Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None None XPRESS BOARD panels can be installed directly
¾ minimum on all types of deck. The last 25 mm (1 in)
of longitudinal overlap must be heat-welded.
The transversal overlap must by covered
with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
COLPLY BASE 410 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 40 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 100 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
BARAL Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
Soprarock DD Plus
Soprasphalte M
Soprasphalte M
Steel deck
STEP 2 — Insulation and support panels
Sopraboard
Colgrip B
Elastophene Sanded
Gypsum
Hot bitumen
Steel deck
INSULATION AND SUPPORT PANELS – STEEL DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Colply Traffic Cap 460
Colply 410
Ballast
Soprasphalte M
Soprasphalte M
Soprarock DD Plus
Soprasphalte M
Gypsum
Elastophene 180 Sanded
Soprasphalte M
Steel deck
Hot bitumen
Ballast
Hot bitumen
Elastophene 180 Sanded
Elastophene Sanded
Sopraboard
Colgrip B
Hot bitumen
Hot bitumen
Steel deck
ASPHALT AND GRAVEL SYSTEMS – STEEL DECK
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
Oxidized/SEBS hot bitumen COLPLY BASE 410 Oxidized/SEBS hot bitumen COLPLY BASE 410
+ a coat of sealant
and gravel
BALLASTED
BAL
BALLASTED
LASTED
BALLASTED
• Vapour barrier
• Insulation and support panels
• Membrane systems
BAL
BALLASTED
LASTED
STEP 1 — Vapour barrier
Steel deck
Sopravap’R
VAPOUR BARRIER – STEEL DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive Optional Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive Mandatory Gypsum ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None None Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None None XPRESS BOARD panels can be installed directly
¾ minimum on all types of deck. The last 25 mm (1 in)
of longitudinal overlap must be heat-welded.
The transversal overlap must by covered
with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
ELASTOPHENE SANDED Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
COLPLY BASE 410 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 40 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
SOPRAGLASS 100 Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
BARAL Hot bitumen Mandatory Gypsum ELASTOCOL 500 primer is required prior to applying
the vapour barrier membrane.
STEP 2 — Insulation and support panels
Steel deck
Sopravap’R
Colgrip B
INSULATION AND SUPPORT PANELS – STEEL DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Filter fabric
Colgrip B
Sopravap’R
Steel deck
BALLASTED SYSTEMS – STEEL DECK
APPLICATION METHOD BASE SHEET APPLICATION CAP SHEET MEMBRANE HIGH BALLAST
MEMBRANE METHOD PERFORMANCE
SYSTEM
Loose laid SOPRAPLY BASE 510 Heat-welded SOPRAPLY BASE 520 A separating layer
is recommended
between the cap
sheet membrane
SOPRAPLY BASE 520 Heat-welded SOPRAPLY BASE 520 and the ballast.
INVERTED
INV
INVERTED
ERTED
INVERTED
• Membrane systems
INV
INVERTED
ERTED
Sopralene Flam 180
Elastocol 500
Steel deck
Sopraflash
Flam Stick
Steel deck
Sopralene Flam 180
Elastocol 500
Gypsum
Sopralene Flam 250 GR
Metal flashing
Sopraflash Flam Stick
Ballast
Elastocol Stick
Filter fabric
Gypsum
INVERTED SYSTEMS – STEEL DECK
SUPPORT APPLICATION BASE SHEET APPLICATION CAP SHEET HIGH BALLAST
PANEL METHOD MEMBRANE METHOD MEMBRANE PERFORMANCE
SYSTEM
MANDATORY Heat-welded SOPRAPLY BASE 520 Heat-welded SOPRAPLY BASE 520 • F ilter fabric
or
Acceptable loose laid • T ype IV
support extruded
panels: SOPRALENE FLAM 180 Heat-welded SOPRALENE FLAM 180 polystyrene
- Gypsum
ELASTOCOL 500
primer is required
SOPRALENE FLAM 180 Heat-welded SOPRALENE 180 SP 3.5 mm
prior to applying
the base sheet
membrane if
welded or
applied with Oxidized/SEBS SOPRAPLY BASE 510 Heat-welded SOPRAPLY BASE 520
oxidized/SEBS hot bitumen
hot bitumen. or
loose laid
COLPLY BASE 410 SEBS hot bitumen COLPLY BASE 410
CONCRETE
CONCRETE DECK
CONCRETE
GRANULATED FINISH (self-protected)
Cold adhesive
• Vapour barrier
• Insulation and support panels
• Membrane systems
Self-adhesive
• Vapour barrier
• Insulation and support panels
• Membrane systems
Mechanically fastened
• Vapour barrier
• Insulation and support panels
SUMMARY
• Membrane systems
Composite panels
• Vapour barrier
• Insulation and support panels
• Membrane systems
Heat-welded
• Vapour barrier
• Insulation and support panels
• Membrane systems
Multi II
• Vapour barrier
• Insulation and support panels
• Membrane systems
BALLASTED
• Vapour barrier
• Insulation and support panels
• Membrane systems
INVERTED
• Membrane systems
GRANULAR CAP SHEET
(self-protected)
GRANULAR CAP SHEET
(self-protected)
GRANULAR
CAP SHEET
SELF-PROTECTED
GRANULATED FINISH (self-protected)
Cold adhesive
• Vapour barrier
• Insulation and support panels
• Membrane systems
Self-adhesive
• Vapour barrier
• Insulation and support panels
• Membrane systems
Mechanically fastened
• Vapour barrier
• Insulation and support panels
• Membrane systems
Composite panels
• Vapour barrier
• Insulation and support panels
• Membrane systems
GRANULAR
Heat-welded
• Vapour barrier
• Insulation and support panels
• Membrane systems
CAP SHEET
SELF-PROTECTED
COLD ADHESIVE
COLD ADHESIVE
COLD
ADHESIVE
Sopravap’R
Elastocol Stick
Concrete deck
Concrete deck
Elastophene SP 2.2
Elastocol 500
Concrete deck
VAPOUR BARRIER – CONCRETE DECK
PRODUCT TYPE OF APPLICATION RECOMMENDATIONS
SOPRAVAP’R Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRALENE STICK ADHESIVE Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRAFLASH STICK Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
XPRESS BOARD SANDED Mechanically fastened XPRESS BOARD panels can be installed directly on all types of decks.
1/2 minimum The last 25 mm (1 in) of longitudinal overlap must be heat-welded.
Hot bitumen The transversal overlap must by covered with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRALENE 180 SP 3.5 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE 180 SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
COLPLY BASE 410 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 40 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 100 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
BARAL Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
Sopraboard
Colgrip B
Duotack
Sopravap’R
Elastocol Stick
Concrete deck
Soprarock DD Plus
STEP 2 — Insulation and support panels
Hot bitumen
Hot bitumen
Concrete deck
Xpress Board Sanded
Sopraboard
Colgrip B
Duotack
Elastophene SP 2.2
Elastocol 500
Concrete deck
INSULATION AND SUPPORT PANELS – CONCRETE DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraboard
Colgrip B
Duotack
Sopravap’R
Elastocol Stick
Elastocol Stick
Concrete deck
Colphene HR GR
Sopraflash Stick
Colply Traffic Cap 460
Colply Brush Grade
Hot bitumen
Soprarock DD Plus
Concrete deck
Hot bitumen
Elastocol Stick
Colphene HR GR
Sopraflash Stick
Colply Traffic Cap 460
Colply Brush Grade
Sopraboard
Duotack Colgrip B
Elastophene SP 2.2
Elastocol 500
Concrete deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With adhesive base sheet installed
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
Cold adhesive COLPLY BASE 410 Cold adhesive COLPLY TRAFFIC CAP 460
SELF-ADHESIVE
SELF-ADHESIVE
SELF-
SELF-ADHESIVE
ADHESIVE
Sopravap’R
Elastocol Stick
Concrete deck
Concrete deck
Elastophene SP 2.2
Elastocol 500
Concrete deck
VAPOUR BARRIER – CONCRETE DECK
PRODUCT TYPE OF APPLICATION RECOMMENDATIONS
SOPRAVAP’R Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRALENE STICK ADHESIVE Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRAFLASH STICK Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
XPRESS BOARD SANDED Mechanically fastened XPRESS BOARD panels can be installed directly on all types of decks.
1/2 minimum The last 25 mm (1 in) of longitudinal overlap must be heat-welded.
Hot bitumen The transversal overlap must by covered with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRALENE 180 SP 3.5 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE 180 SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
COLPLY BASE 410 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 40 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 100 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
BARAL Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
Colgrip A
Duotack
Sopravap’R
Elastocol Stick
Concrete deck
Sopraboard
STEP 2 — Insulation and support panels
Hot bitumen
Xpress Board Sanded
Concrete deck
Sopraboard
Colgrip B
Duotack
Elastophene SP 2.2
Elastocol 500
Concrete deck
INSULATION AND SUPPORT PANELS – CONCRETE DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• The COLVENT 810 membrane can be installed without primer directly onto the COLGRIP A insulation.
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Soprastar Flam HD GR
Elastocol Stick
Colvent 810
Colgrip A
Duotack
Sopravap’R
Elastocol Stick
Elastocol Stick
STEP 3 — Membrane systems
Sopraboard
Duotack
Soprarock DD Plus
Hot bitumen
Xpress Board Sanded
Concrete deck
Elastocol Stick
Sopraboard
Duotack Colgrip B
Elastophene SP 2.2
Elastocol 500
Concrete deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With self-adhesive base sheet
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
Self-adhesive COLPHENE HR GR
SEBS/OXIDIZED
HOT BITUMEN
SEBS/OXIDIZED
HOT
BITUMEN
SEBS/OXIDIZED
Sopravap’R
Elastocol Stick
Concrete deck
Concrete deck
Elastophene SP 2.2
Elastocol 500
Concrete deck
VAPOUR BARRIER – CONCRETE DECK
PRODUCT TYPE OF APPLICATION RECOMMENDATIONS
SOPRAVAP’R Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRALENE STICK ADHESIVE Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRAFLASH STICK Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
XPRESS BOARD SANDED Mechanically fastened XPRESS BOARD panels can be installed directly on all types of decks.
1/2 minimum The last 25 mm (1 in) of longitudinal overlap must be heat-welded.
Hot bitumen The transversal overlap must by covered with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRALENE 180 SP 3.5 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE 180 SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
COLPLY BASE 410 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 40 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 100 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
BARAL Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
Sopraboard
Colgrip B
Duotack
Sopravap’R
Elastocol Stick
Concrete deck
Soprarock DD Plus
STEP 2 — Insulation and support panels
Concrete deck
Xpress Board Sanded
Sopraboard
Hot bitumen
Colgrip B
Elastocol 500
Elastophene SP 2.2
Concrete deck
INSULATION AND SUPPORT PANELS – CONCRETE DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Sopraply 510
Hot bitumen
Sopraboard
Duotack Colgrip B
Sopravap’R
Elastocol Stick
Sopraflash Stick
Concrete deck
Colply Traffic Cap 460
Elastocol Stick
Soprasphalte M
Hot bitumen
STEP 3 — Membrane systems
Soprarock DD Plus
Concrete deck
Hot bitumen
Sopraboard
Colgrip B
Elastocol 500
Elastophene SP 2.2
Concrete deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With hot bitumen base sheet installed
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
Oxidized/SEBS hot bitumen SOPRAPLY BASE 510 Heat-welded SOPRAPLY TRAFFIC CAP 560
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
MECHANICALLY
FASTENED
MECHA
NICALLY
FASTENED
Sopravap’R
Elastocol Stick
Concrete deck
Concrete deck
Elastophene SP 2.2
Elastocol 500
Concrete deck
VAPOUR BARRIER – CONCRETE DECK
PRODUCT TYPE OF APPLICATION RECOMMENDATIONS
SOPRAVAP’R Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRALENE STICK ADHESIVE Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRAFLASH STICK Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
XPRESS BOARD SANDED Mechanically fastened XPRESS BOARD panels can be installed directly on all types of decks.
1/2 minimum The last 25 mm (1 in) of longitudinal overlap must be heat-welded.
Hot bitumen The transversal overlaps must by covered with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRALENE 180 SP 3.5 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE 180 SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
COLPLY BASE 410 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 40 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 100 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
BARAL Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
Colgrip B
Sopravap’R
Elastocol Stick
Concrete deck
Soprarock DD
STEP 2 — Insulation and support panels
Hot bitumen
Xpress Board Sanded
Concrete deck
Sopraboard
Colgrip B
Elastocol 500
Elastophene SP 2.2
Concrete deck
INSULATION AND SUPPORT PANELS – CONCRETE DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
SOPRAROCK MD No No Yes No
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Soprastar Flam HD GR
Elastocol Stick
Colgrip B
Elastocol Stick
Hot bitumen
Soprarock DD
Concrete deck
Sopraboard
Colgrip B
Elastocol 500
Elastophene SP 2.2
Concrete deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With mechanically fastened base sheet
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
* The N/A response applies to the base sheet since it is a single-ply system.
COMPOSITE PANELS
COMPOSITE
PANELS
COMPOSITE
PANELS
Sopravap’R
Elastocol Stick
Concrete deck
Concrete deck
Elastophene SP 2.2
Elastocol 500
Concrete deck
VAPOUR BARRIER – CONCRETE DECK
PRODUCT TYPE OF APPLICATION RECOMMENDATIONS
SOPRAVAP’R Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRALENE STICK ADHESIVE Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRAFLASH STICK Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
XPRESS BOARD SANDED Mechanically fastened XPRESS BOARD panels can be installed directly on all types of decks.
1/2 minimum The last 25 mm (1 in) of longitudinal overlap must be heat-welded.
Hot bitumen The transversal overlaps must by covered with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRALENE 180 SP 3.5 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE 180 SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
COLPLY BASE 410 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 40 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 100 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
BARAL Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
Xpress ISO
Duotack
Sopravap’R
Elastocol Stick
Concrete deck
Xpress Board
STEP 2 — Insulation and support panels
Hot bitumen
Hot bitumen
Colgrip B
Concrete deck
Xpress Board Sanded
Soprabase FR 180
Duotack
Duotack Colgrip B
Elastophene SP 2.2
Elastocol 500
Concrete deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With composite panels
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR HP
SOPRASTAR FLAM WF HP
SOPRASTAR FLAM HD GR HP
SOPRASTAR FLAM WF HP
SOPRASTAR FLAM HD GR HP
SOPRASTAR FLAM WF HP
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Sopraflash Flam Stick
Xpress ISO
Duotack
Xpress Board
STEP 3 — Membrane systems
Hot bitumen
Hot bitumen
Soprabase FR 180
Duotack
Duotack Colgrip B
Elastophene SP 2.2
Elastocol 500
Concrete deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With composite panels
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR HP
SOPRASTAR FLAM WF HP
SOPRASTAR FLAM HD GR HP
SOPRASTAR FLAM WF HP
SOPRASTAR FLAM HD GR HP
SOPRASTAR FLAM WF HP
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
THERMOFUSIBLE
THERMO
FUSIBLE THERMOFUSIBLE
Sopravap’R
Elastocol Stick
Concrete deck
Concrete deck
Elastophene SP 2.2
Elastocol 500
Concrete deck
VAPOUR BARRIER – CONCRETE DECK
PRODUCT TYPE OF APPLICATION RECOMMENDATIONS
SOPRAVAP’R Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRALENE STICK ADHESIVE Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRAFLASH STICK Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
XPRESS BOARD SANDED Mechanically fastened XPRESS BOARD panels can be installed directly on all types of decks.
1/2 minimum The last 25 mm (1 in) of longitudinal overlap must be heat-welded.
Hot bitumen The transversal overlaps must by covered with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRALENE 180 SP 3.5 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE 180 SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
COLPLY BASE 410 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 40 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 100 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
BARAL Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
Sopraboard
Colgrip B
Duotack
Sopravap’R
Elastocol Stick
Concrete deck
Sopraboard
STEP 2 — Insulation and support panels
Colgrip B
Concrete deck
Xpress Board Sanded
Soprarock DD Plus
Hot bitumen
Elastocol 500
Elastophene SP 2.2
Concrete deck
INSULATION AND SUPPORT PANELS – CONCRETE DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Sopraboard
Duotack Colgrip B
Elastocol Stick
Sopralene Flam 180
Sopraboard
STEP 3 — Membrane systems
Colgrip B
Hot bitumen
Hot bitumen
Concrete deck
Soprarock DD Plus
Hot bitumen
Elastocol 500
Elastophene SP 2.2
Concrete deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With heat-welded base sheet
APPLICATION MEHTOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM WF
ASPHALT AND
GRAVEL
ASPHALT AND GRAVEL
ASPHALT
AND GRAVEL
ASPHALT AND GRAVEL
Multi II
• Vapour barrier
• Insulation
• Membrane systems
ASPHALT
AND GRAVEL
MULTI II
MULTI II
MULTI II
MULTI II
Sopralene 180 Sanded
Concrete deck
Soprasphalte M
STEP 1 — Vapour barrier
Elastophene Sanded
Concrete deck
Hot bitumen
VAPOUR BARRIER – CONCRETE DECK
PRODUCT TYPE OF APPLICATION RECOMMENDATIONS
SOPRAVAP’R Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRALENE STICK ADHESIVE Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRAFLASH STICK Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
XPRESS BOARD SANDED Mechanically fastened XPRESS BOARD panels can be installed directly on all types of decks.
1/2 minimum The last 25 mm (1 in) of longitudinal overlap must be heat-welded.
Hot bitumen The transversal overlaps must by covered with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRALENE 180 SP 3.5 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE 180 SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
COLPLY BASE 410 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 40 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 100 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
BARAL Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
Soprarock DD Plus
Soprasphalte M
Concrete deck
Soprasphalte M
STEP 2 — Insulation and support panels
Sopraboard
Colgrip B
Elastophene Sanded
Concrete deck
Hot bitumen
INSULATION AND SUPPORT PANELS – CONCRETE DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• The application of a hot bitumen base sheet does not require a support panel when it is installed on SOPRAROCK DD PLUS insulation.
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Colply Traffic Cap 460
Sopraflash Flam Stick
Hot bitumen Ballast
Soprasphalte M
Soprarock DD Plus
Soprasphalte M
Concrete deck
Soprasphalte M
Hot bitumen
Elastophene 180 Sanded
Elastophene Sanded
Sopraboard
Colgrip B
Hot bitumen
Elastophene Sanded
Concrete deck
Hot bitumen
ASPHALT AND GRAVEL SYSTEMS – CONCRETE DECK
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
Oxidized/SEBS hot bitumen COLPLY BASE 410 Oxidized/SEBS hot bitumen COLPLY BASE 410
+ a coat of sealant
and gravel
BALLASTED
BAL
BALLASTED
LASTED
Ballasted
• Vapour barrier
• Insulation
• Membrane systems
BAL
BALLASTED
LASTED
Sopravap’R
STEP 1 — Vapour barrier
Elastocol Stick
Concrete deck
VAPOUR BARRIER – CONCRETE DECK
PRODUCT TYPE OF APPLICATION RECOMMENDATIONS
SOPRAVAP’R Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRALENE STICK ADHESIVE Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
SOPRAFLASH STICK Self-adhesive ELASTOCOL STICK or ELASTOCOL STICK H2O primers are required
prior to applying the membrane.
XPRESS BOARD SANDED Mechanically fastened XPRESS BOARD panels can be installed directly on all types of decks.
1/2 minimum The last 25 mm (1 in) of longitudinal overlap must be heat-welded.
Hot bitumen The transversal overlaps must by covered with a SOPRALAP cover strip.
ELASTOPHENE SP 2.2 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRALENE 180 SP 3.5 Heat-welded ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE 180 SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
ELASTOPHENE SANDED Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
COLPLY BASE 410 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 40 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
SOPRAGLASS 100 Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
BARAL Hot bitumen ELASTOCOL 500 primer is required prior to applying the membrane.
Colgrip B
STEP 2 — Insulation and support panels
Elastocol Stick
Sopravap’R
Concrete deck
INSULATION AND SUPPORT PANELS – CONCRETE DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
SOPRAROCK MD No No Yes No
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Elastocol Stick
Ballast
Filter fabric
STEP 3 — Membrane systems
Elastocol Stick
Colgrip B
Sopravap’R
Concrete deck
BALLAST SYSTEMS – CONCRETE DECK
SUPPORT APPLICATION BASE SHEET APPLICATION CAP SHEET HIGH BALLAST
PANEL METHOD MEMBRANE METHOD MEMBRANE PERFORMANCE
SYSTEM
MANDATORY Heat-welded SOPRAPLY BASE 520 Heat-welded SOPRAPLY BASE 520 • F iltering layer
or
Acceptable loose laid • T ype IV
support extruded
panels: SOPRALENE FLAM 180 Heat-welded SOPRALENE FLAM 180 polystyrene
- Gypsum
ELASTOCOL 500
primer is required
SOPRALENE FLAM 180 Heat-welded SOPRALENE 180 SP 3.5 mm
prior to applying
the base sheet
membrane if
welded or
applied with COLPLY BASE 410 SEBS hot bitumen COLPLY BASE 410
oxidized/SEBS
hot bitumen.
INVERTED
INV
INVERTED
ERTED
Inverted
• Membrane systems
INV
INVERTED
ERTED
Sopralene Flam 180
Elastocol 500
Elastocol 500
Sopralene Flam 250 GR
Metal flashing
Concrete deck
Elastocol 500
INVERTED SYSTEMS –CONCRETE DECK
SUPPORT APPLICATION BASE SHEET APPLICATION CAP SHEET HIGH BALLAST
PANEL METHOD MEMBRANE METHOD MEMBRANE PERFORMANCE
SYSTEM
MANDATORY Heat-welded SOPRAPLY BASE 520 Heat-welded SOPRAPLY BASE 520 • F iltering layer
or
Acceptable loose laid • T ype IV
support extruded
panels: SOPRALENE FLAM 180 Heat-welded SOPRALENE FLAM 180 polystyrene
- Gypsum
ELASTOCOL 500
primer is required
SOPRALENE FLAM 180 Heat-welded SOPRALENE 180 SP 3.5 mm
prior to applying
the base sheet
membrane if
welded or
applied with Oxidized/SEBS SOPRAPLY BASE 510 Heat-welded SOPRAPLY BASE 520
oxidized/SEBS hot bitumen
hot bitumen. or
loose laid
COLPLY BASE 410 SEBS hot bitumen COLPLY BASE 410
WOOD
WOOD DECK
WOOD
GRANULATED FINISH (self-protected)
Cold adhesive
• Vapour barrier
• Insulation and support panels
• Membrane systems
Self-adhesive
• Vapour barrier
• Insulation and support panels
• Membrane systems
Mechanically fastened
• Vapour barrier
• Insulation and support panels
SUMMARY
• Membrane systems
Composite panels
• Vapour barrier
• Insulation and support panels
• Membrane systems
Heat-welded
• Vapour barrier
• Insulation and support panels
• Membrane systems
Multi II
• Vapour barrier
• Insulation and support panels
• Membrane systems
BALLASTED
• Vapour barrier
• Insulation and support panels
• Membrane systems
INVERTED
• Membrane systems
GRANULAR CAP SHEET
(self-protected)
GRANULAR CAP SHEET
(self-protected)
GRANULAR
CAP SHEET
SELF-PROTECTED
GRANULATED FINISH (self-protected)
Cold adhesive
• Vapour barrier
• Insulation and support panels
• Membrane systems
Self-adhesive
• Vapour barrier
• Insulation and support panels
• Membrane systems
Mechanically fastened
• Vapour barrier
• Insulation and support panels
• Membrane systems
Composite panels
• Vapour barrier
• Insulation and support panels
• Membrane systems
GRANULAR
Heat-welded
• Vapour barrier
• Insulation and support panels
• Membrane systems
CAP SHEET
SELF-PROTECTED
COLD ADHESIVE
COLD ADHESIVE
COLD
ADHESIVE
Sopravap’R
Elastocol Stick
Wood deck
STEP 1 — Vapour barrier
Elastocol 500
Wood deck
VAPOUR BARRIER – WOOD DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None N/A Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None N/A XPRESS BOARD panels can be installed directly on
1/2 minimum all types of deck. The last 25 mm (1 in) of longitudinal
overlap must be heat-welded. The transversal
overlap must by covered with a SOPRALAP
cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
COLPLY BASE 410 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 40 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 100 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
BARAL Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
Sopraboard
Colgrip B
Duotack
Sopravap’R
Elastocol Stick
Wood deck
Soprarock DD Plus
STEP 2 — Insulation and support panels
Sopraboard
Colgrip B
Elastocol 500
Wood deck
INSULATION AND SUPPORT PANELS – WOOD DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraboard
Colgrip B
Duotack
Sopravap’R
Elastocol Stick
Elastocol Stick
Soprarock DD Plus
STEP 3 — Membrane systems
Elastocol Stick
Sopraboard
Colgrip B
Elastophene SP 2.2
Gypsum
Elastocol 500
Wood deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With cold adhesive base sheet installed
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
Cold adhesive COLPLY BASE 410 Cold adhesive COLPLY TRAFFIC CAP 460
SELF-ADHESIVE
SELF-ADHESIVE
SELF-
SELF-ADHESIVE
ADHESIVE
Sopravap’R
Elastocol Stick
Wood deck
Elastocol Stick
STEP 1 — Vapour barrier
Wood deck
Elastocol Stick
Elastocol 500
Wood deck
VAPOUR BARRIER – WOOD DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None N/A Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None N/A XPRESS BOARD panels can be installed directly on
1/2 minimum all types of deck. The last 25 mm (1 in) of longitudinal
overlap must be heat-welded. The transversal
overlap must by covered with a SOPRALAP
cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
COLPLY BASE 410 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 40 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 100 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
BARAL Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
Colgrip A
Duotack
Sopravap’R
Elastocol Stick
Wood deck
Sopraboard
STEP 2 — Insulation and support panels
Soprarock DD
Elastocol Stick
Sopraboard
Elastocol Stick
Colgrip B
Elastocol 500
Wood deck
INSULATION AND SUPPORT PANELS – WOOD DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• The COLVENT 810 membrane can be installed without primer directly onto the COLGRIP A insulation.
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Soprastar Flam HD GR
Elastocol Stick
Colvent 810
Colgrip A
Duotack
Sopravap’R
Elastocol Stick
Sopraflash Flam Stick
Elastocol Stick
Sopraboard
STEP 3 — Membrane systems
Soprarock DD
Colvent 810
Elastocol Stick
Sopraboard
Colgrip B
Elastophene SP 2.2
Gypsum
Elastocol 500
Wood deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With self-adhesive base sheet
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
Self-adhesive COLPHENE HR GR
Self-adhesive COLPHENE HR GR
SEBS/OXIDIZED
HOT BITUMEN
SEBS/OXIDIZED
HOT
BITUMEN
SEBS/OXIDIZED
Sopravap’R
Elastocol Stick
Wood deck
STEP 1 — Vapour barrier
Elastocol 500
Wood deck
VAPOUR BARRIER – WOOD DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None N/A Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None N/A XPRESS BOARD panels can be installed directly on
1/2 minimum all types of deck. The last 25 mm (1 in) of longitudinal
overlap must be heat-welded. The transversal
overlap must by covered with a SOPRALAP
cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
COLPLY BASE 410 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 40 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 100 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
BARAL Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
Sopraboard
Colgrip B
Sopravap’R
Elastocol Stick
Wood deck
Soprarock DD Plus
STEP 2 — Insulation and support panels
Sopraboard
Colgrip B
Hot bitumen
Gypsum
Elastophene SP 2.2
Elastocol 500
Wood deck
INSULATION AND SUPPORT PANELS – WOOD DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Sopraply 510
Sopraboard
Hot bitumen
Colgrip B
Sopravap’R
Elastocol Stick
Sopraflash Flam Stick
Hot bitumen
Soprarock DD Plus
STEP 3 — Membrane systems
Elastophene PS
Soprasphalte M
Hot bitumen
Sopraboard
Colgrip B
Gypsum
Elastophene SP 2.2
Elastocol 500
Wood deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With hot bitumen base sheet installed
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
Oxidized/SEBS hot bitumen SOPRAPLY BASE 510 Heat-welded SOPRAPLY TRAFFIC CAP 560
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
MECHANICALLY
FASTENED
MECHA
NICALLY
FASTENED
Sopravap’R
Elastocol Stick
Wood deck
Wood deck
Sopravap’R
VAPOUR BARRIER – WOOD DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None N/A Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None N/A XPRESS BOARD panels can be installed directly on
1/2 minimum all types of deck. The last 25 mm (1 in) of longitudinal
overlap must be heat-welded. The transversal
overlap must by covered with a SOPRALAP
cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
COLPLY BASE 410 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 40 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 100 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
BARAL Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
Colgrip B
Sopravap’R
Elastocol Stick
Sopravap’R
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
SOPRAROCK MD No No Yes No
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Soprastar Flam HD GR
Elastocol Stick
Colgrip B
Sopravap’R
Elastocol Stick
Sopraflash Flam Stick
Soprarock DD
STEP 3 — Membrane systems
Unilay 750
Colgrip B
Sopravap’R
Wood deck
Elastocol Stick
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With mechanically fastened base sheet
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
* The N/A response applies to the base sheet since it is a single-ply system.
COMPOSITE PANELS
COMPOSITE
PANELS
COMPOSITE
PANELS
Sopravap’R
Elastocol Stick
Wood deck
STEP 1 — Vapour barrier
Elastocol 500
Wood deck
VAPOUR BARRIER – WOOD DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None N/A Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None N/A XPRESS BOARD panels can be installed directly on
1/2 minimum all types of deck. The last 25 mm (1 in) of longitudinal
overlap must be heat-welded. The transversal
overlap must by covered with a SOPRALAP
cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
COLPLY BASE 410 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 40 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 100 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
BARAL Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
Xpress Board
Colgrip B
Sopravap’R
Elastocol Stick
Wood deck
Xpress ISO
STEP 2 — Insulation and support panels
Duotack
Soprabase FR 180
Duotack
Duotack
Colgrip B
Gypsum
Elastophene SP 2.2
Elastocol 500
Wood deck
INSULATION AND COMPOSITE PANELS – WOOD DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Soprastar Flam HD GR
Elastocol Stick
Xpress Board
Colgrip B
Sopravap’R
Elastocol Stick
Xpress ISO
Duotack
STEP 3 — Membrane systems
Wood deck
Soprabase FR 180
Duotack
Duotack
Colgrip B
Elastophene SP 2.2
Gypsum
Elastocol 500
Wood deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With composite panels
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
XPRESS BOARD SANDED With cold adhesive or COLPLY TRAFFIC CAP 460
SEBS hot bitumen
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
XPRESS ISO SANDED With cold adhesive or COLPLY TRAFFIC CAP 460
SEBS hot bitumen
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
XPRESS EPS SANDED With cold adhesive or COLPLY TRAFFIC CAP 460
SEBS hot bitumen
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
Self-adhesive COLPHENE HR GR
SOPRASTAR STICK HD GR
THERMOFUSIBLE
THERMO
FUSIBLE THERMOFUSIBLE
Sopravap’R
Elastocol Stick
Wood deck
STEP 1 — Vapour barrier
Elastocol 500
Wood deck
VAPOUR BARRIER – WOOD DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None N/A Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None N/A XPRESS BOARD panels can be installed directly on
1/2 minimum all types of deck. The last 25 mm (1 in) of longitudinal
overlap must be heat-welded. The transversal
overlap must by covered with a SOPRALAP
cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
COLPLY BASE 410 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 40 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 100 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
BARAL Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
Sopraboard
Colgrip B
Duotack
Sopravap’R
Elastocol Stick
Wood deck
Sopraboard
STEP 2 — Insulation and support panels
Colgrip B
Soprarock DD Plus
Elastocol 500
Wood deck
INSULATION AND SUPPORT PANELS – WOOD DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Sopraboard
Colgrip B
Duotack
Sopravap’R
Elastocol Stick
Wood deck
Sopralene Flam 250 GR
Elastocol Stick
Sopraboard
Colgrip B
STEP 3 — Membrane systems
Soprarock DD Plus
Elastocol 500
Wood deck
GRANULATED FINISH – SELF-PROTECTED SYSTEMS
With heat-welded base sheet
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM HD GR
SOPRASTAR FLAM WF
SOPRASTAR FLAM WF
ASPHALT AND
GRAVEL
ASPHALT AND GRAVEL
ASPHALT
AND GRAVEL
ASPHALT AND GRAVEL (multi-ply)
Multi II
• Vapour barrier
• Insulation and support panels
• Membrane systems
ASPHALT
AND GRAVEL
MULTI II
MULTI II
MULTI II
MULTI II
Elastophene 180 Sanded
Gypsum
Soprasphalte M
Wood deck
Elastophene Sanded
STEP 1 — Vapour barrier
Gypsum
Hot bitumen
Wood deck
VAPOUR BARRIER – WOOD DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None N/A Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None N/A XPRESS BOARD panels can be installed directly on
1/2 minimum all types of deck. The last 25 mm (1 in) of longitudinal
overlap must be heat-welded. The transversal
overlap must by covered with a SOPRALAP
cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
COLPLY BASE 410 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 40 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 100 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
BARAL Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
Soprarock DD Plus
Soprasphalte M
Soprasphalte M
Wood deck
STEP 2 — Insulation and support panels
Sopraboard
Colgrip B
Elastophene Sanded
Gypsum
Hot bitumen
Wood deck
INSULATION AND SUPPORT PANELS – WOOD DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Soprasphalte M Ballast
Soprasphalte M
Soprarock DD Plus
Soprasphalte M
Elastophene 180
Gypsum
Sanded
Soprasphalte M
Wood deck
Hot bitumen
Elastophene 180 Sanded
Elastophene Sanded
Sopraboard
Colgrip B
Hot bitumen
Elastophene Sanded
Gypsum
Hot bitumen
Wood deck
ASPHALT AND GRAVEL SYSTEMS – WOOD DECK
APPLICATION METHOD BASE SHEET MEMBRANE APPLICATION METHOD CAP SHEET MEMBRANE HIGH PERFORMANCE
SYSTEM
Oxidized/SEBS hot bitumen COLPLY BASE 410 Oxidized/SEBS hot bitumen COLPLY BASE 410 + a coat of
sealant and gravel
BALLASTED
BAL
BALLASTED
LASTED
BALLASTED
• Vapour barrier
• Insulation and support panel
• Membrane system
BAL
BALLASTED
LASTED
Sopravap’R
Elastocol Stick
STEP 1 — Vapour barrier
Wood deck
VAPOUR BARRIER – WOOD DECK
PRODUCT TYPE OF APPLICATION SUPPORT PANEL RECOMMENDATIONS
SOPRAVAP’R Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRALENE STICK ADHESIVE Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRAFLASH STICK Self-adhesive N/A N/A ELASTOCOL STICK or ELASTOCOL STICK H2O primer
is required before applying the membrane
to the support panel.
SOPRASTOP Cold adhesive None N/A Unroll SOPRASTOP membrane loose laid directly
onto the deck. The overlaps must be sealed
using SOPRASTOP ADHESIVE.
SOPRASTOP vapour barrier must be used only
on roofing systems where a component
is mechanically fastened.
XPRESS BOARD SANDED Mechanically fastened None N/A XPRESS BOARD panels can be installed directly on
1/2 minimum all types of deck. The last 25 mm (1 in) of longitudinal
overlap must be heat-welded. The transversal
overlap must by covered with a SOPRALAP
cover strip.
ELASTOPHENE SP 2.2 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRALENE 180 SP 3.5 Heat-welded Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE 180 SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
ELASTOPHENE SANDED Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
COLPLY BASE 410 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 40 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
SOPRAGLASS 100 Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
BARAL Hot bitumen Mandatory Sopraboard ELASTOCOL 500 primer is only required prior to
Gypsum applying the membrane over the gypsum.
Colgrip B
STEP 2 — Insulation and support panels
Elastocol Stick
Sopravap’R
Wood deck
INSULATION AND SUPPORT PANELS – WOOD DECK
INSULATION ACCEPTED ADHESIVES MECHANICALLY OXIDIZED / SEBS
FASTENED BITUMEN
COLTACK DUOTACK
SOPRAROCK DD No No Yes No
NOTES:
• COLGRIP A is a closed-cell, polyiso foam core covered by 2 inorganic coated glass facers.
• COLGRIP B is a closed-cell, polyiso foam core covered by 2 fiber-reinforced organic felt facers.
• With SOPRAROCK DD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
SOPRAROCK MD No No Yes No
NOTE:
• With SOPRAROCK MD PLUS, an overlay board is not required if the base sheet is thermofusible, adhered with cold adhesive or mopped with hot bitumen.
Sopraflash Flam Stick
Elastocol Stick
Ballast
Filter fabric
STEP 3 — Membrane systems
Colgrip B
Loose laid SOPRAPLY BASE 510 Heat-welded SOPRAPLY BASE 520 A separating layer
is recommended
between the cap
sheet membrane
SOPRAPLY BASE 520 Heat-welded SOPRAPLY BASE 520 and the ballast.
INVERTED
INV
INVERTED
ERTED
INVERTED
• Membrane systems
INV
INVERTED
ERTED
Sopralene Flam 180
Elastocol 500
Wood deck
Sopraflash
Flam Stick
Wood deck
Sopralene Flam 180
Gypsum
Elastocol 500
Sopralene Flam 250 GR
Metal Flashing
Sopraflash Flam Stick
Ballast
Elastocol Stick
Filter fabric
Type IV extruded polystyrene
Sopralene Flam 180
Wood deck
Elastocol 500
Gypsum
INVERTED SYSTEMS –WOOD DECK
SUPPORT APPLICATION BASE SHEET APPLICATION CAP SHEET HIGH BALLAST
PANEL METHOD MEMBRANE METHOD MEMBRANE PERFORMANCE
SYSTEM
MANDATORY Heat-welded SOPRAPLY BASE 520 Heat-welded SOPRAPLY BASE 520 • F ilter fabric
or
Acceptable loose laid • T ype IV
support extruded
panels: SOPRALENE FLAM 180 Heat-welded SOPRALENE FLAM 180 polystyrene
-Gypsum
ELASTOCOL 500
primer is required
SOPRALENE FLAM 180 Heat-welded SOPRALENE 180 SP 3.5 mm
prior to applying
the base sheet
membrane if
heat-welded or
applied with Oxidized/SEBS SOPRAPLY BASE 510 Heat-welded SOPRAPLY BASE 520
oxidized/SEBS hot bitumen
hot bitumen. or
loose laid
COLPLY BASE 410 SEBS hot bitumen COLPLY BASE 410
NO INSULATION
Sopraflash Flam Stick
Colphene HR GR
Elastocol Stick
Colply Traffic Cap 460
Sopraboard
Wood deck
Elastocol Stick
Wood deck
Membrane systems
Hot bitumen
Sopraboard
Wood deck
WITHOUT INSULATION SYSTEMS
DECK AND APPLICATION BASE SHEET APPLICATION CAP SHEET HIGH
SUPPORT PANEL METHOD MEMBRANES METHOD MEMBRANES PERFORMANCE
SYSTEM
Steel: Adhesive COLPLY BASE 410 Adhesive COLPLY TRAFFIC CAP 460
- Gypsum
Wood:
- Gypsum
- Sopraboard
Steel: Oxidized/SEBS SOPRAPLY BASE 510 Heat-welded SOPRAPLY TRAFFIC CAP 560
- Gypsum hot bitumen
Sopraglass 46
Fire-stop (optional)
Elastocol Stick
Soprabase FR
Wood deck
Membrane systems
Sopraflash Stick
Elastocol Stick
Wood deck
DECK AND APPLICATION BASE SHEET APPLICATION CAP SHEET HIGH
SUPPORT PANEL METHOD MEMBRANES METHOD MEMBRANES PERFORMANCE
SYSTEM
Steel: Mechanically SOPRAFIX BASE 630 Heat-welded SOPRAFIX TRAFFIC CAP 660
- Gypsum fastened
In the case of Composite panels XPRESS BOARD Heat-welded SOPRAPLY TRAFFIC CAP 560
composite panels,
they are installed
directly on XPRESS BOARD Heat-welded SOPRASTAR FLAM HD GR
the wood or
steel decks.
SOPRABASE FR 180 Heat-welded SOPRALENE FLAM 250 GR
Xpress Board
Sopraglass 40
Fire-stop (optional)
Soprabase FR
Wood deck
Sopraglass 40
Fire-stop (optional)
Membrane systems
Sopraboard
Wood deck
DECK AND APPLICATION BASE SHEET APPLICATION CAP SHEET HIGH
SUPPORT PANEL METHOD MEMBRANES METHOD MEMBRANES PERFORMANCE
SYSTEM
In the case of Composite panels XPRESS ISO SANDED Adhesive or COLPLY TRAFFIC CAP 460
composite panels, hot bitumen
they are installed
directly on SOPRABASE FR 180 SANDED Adhesive or SOPRALENE 180 GR
the wood or hot bitumen
steel decks.
SOPRABASE FR 180 SANDED Self-adhesive COLPHENE HR GR
Steel: Heat-welded SOPRAPLY BASE 520 Heat-welded SOPRAPLY TRAFFIC CAP 560
- Gypsum
EAVE PROTECTORS
UNDERLAYMENT PROTECTION
LASTOBOND roof underlayment membranes are often used on residential roofs and under metal clading
materials to ensure waterproofing of high-risk areas. SOPREMA has designed a complete line of self-
adhesive waterproofing membranes offering unique performance.
LASTOBOND 195 Yes The LASTOBOND 195 and 240 roof underlayment membranes are composed
of self-adhesive SBS modified bitumen, glass mat reinforcement and have
a sanded surface.
LASTOBOND 240 Yes The LASTOBOND 195 membrane has a width of 910 mm (36 in).
LASTOBOND SHIELD Yes The LASTOBOND SHIELD self-adhesive roof underlayment membrane provides
increased performance thanks to a flexible self-adhesive and self-sealing
bitumen composition. The surface of the membrane is covered with a
three-ply woven polyethylene.
LASTOBOND SHIELD HT Yes In addition to offering all the advantages of the LASTOBOND SHIELD membrane,
the LASTOBOND SHIELD HT waterproofing membrane is resistant to temperatures
as high as 105°C. This makes LASTOBOND SHIELD HT the perfect solution for
ensuring the waterproofing of the roof under metal panels, since its
bituminous mass is more resistant to the heat conducted by the metal.
COMPLEMENTARY
PRODUCTS
ACCESSORY PRODUCTS
For further information about the products offered by SOPREMA, we invite you to consult the Product Catalogue.
INSULATION ADHESIVES
COLTACK
DUOTACK
MEMBRANE ADHESIVES
COLPLY ADHESIVE BRUSH GRADE
COLPLY ADHESIVE TROWEL GRADE
SOPRASTOP
SOPRASPHALTE M
ROOF COATINGS
ALSAN FLASHING
OTHERS
SOPRAFIX SCREWS AND PLATES
ROUND TOP NAILS
PAVER PEDESTALS
BULK FINISHING GRANULES
SOPRAJOINT
SOPRAWALK
SOPRASOLIN HD
SOPRATAPE
SOPRALAP
TECHNICAL REFERENCES
REFERENCES
TECHNICAL
REFERENCE
TECHNICAL REFERENCES
TECHNICAL
SUMMARY
DETAILS
DETAILS
DETAILS
SEPARATING JOINT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SOP21
ROOF AREA DIVIDERS (PARAPET) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SOP09
ROOF AREA DIVIDER (flat) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SOP38
ROOF AREA DIVIDER (flat) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SOP38
EXPANSION JOINT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SOP19
DETAILS
EXPANSION JOINT - SINGLE-PLY SYSTEM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SOP19-01
FLAT EXPANSION JOINT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SOP34
ROOF/WALL EXPANSION JOINT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SOP28
ROOF TO WALL JUNCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SOP06
ROOF TO WALL JUNCTION - SINGLE-PLY SYSTEM . . . . . . . . . . . . . . . . . . . . . . . . . SOP06-01
ROOF TO WALL JUNCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SOP07
ROOF TO WALL JUNCTION - SINGLE-PLY SYSTEM . . . . . . . . . . . . . . . . . . . . . . . . . SOP07-01
ELASTOMERIC TWO-PLY JUNCTION SYSTEM / SINGLE-PLY . . . . . . . . . . . . . . . . . SOP31
ELASTOMERIC TWO-PLY JUNCTION SYSTEM /
EXISTING MULTI-PLY (cold-installed) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SOP32
DETAILS
DETAILS
DETAILS
1.877.MAMMOUTH
www.soprema.ca