RISK ASSESSMENT‐ FOR ELECTRICAL SYSTEM TESTING AND COMMISSIONING 

PROJECT NAME: CONSTRUCTION OF 10 VILLAS @ GIARDINO VILLAGE
LOCATION: THE PEARL QATAR
 

LIKELIHOOD 
Certain 5 5 10 15 20 25
Probable 4 4 8 12 16 20
Possible 3 3 6 9 12 15
Improbable 2 2 4 6 8 10
 
Negligible 1 1 2 3 4 5

 
CONSEQUENCE Slight 1 Minor 2 Significant 3 Severe 4 Major 5
INTOLERABLE (15 TO 25)
Operations must not proceed: alternative methods to conduct this task must be implemented.
 

INTERMEDIATE (4 TO 12)
Risks should be reduced to as low as reasonably practicable (ALARM). The higher the risk. The more effort must be given to reducing the risk.
 
This task should be reassessed at regular intervals to evaluate that the existing control measures are adequate.
TOTERABLE (1 TO 4)
This task may proceed with or without additional control measures. But if measures can be implemented to further reduce risk these should be
 
implemented.
Possible multiple deaths and/or serious structural An event which is certain to occur unless immediate
 MAJOR  CERTAIN
damage controls are applied
Possible death, severe multiple injuries (LTI – An event which is likely to occur unless control
 SEVERE  PROBABLE
Medevac) measures are improved
Possible significant injuries / multiple minor injuries An event which may occur despite existing control
 SIGNIFICANT  POSSIBLE
(Probable LTI) measures
Possible significant injuries (Medical treatment/first An improbable event, but could occur it control
 MINOR  IMPROBABLE
Aid) measures are disregarded
Possible slight/no potential risk of injuries(Possible
 SLIGHT  NEGLIGIBLE A highly unlikely event.
first Aid)
Any number 15 or above is intolerable and the task must not commence until alternative methods have been introduced. Any number 4 to 12 
risks are deemed as tolerable, risks must have been reduced to as low as reasonably practicable (ALARM). Additional control measures may be 
required and the tasks should be re‐assessed at regular intervals. Numbers 1 to 4 are tolerable, but risks should be reduced further if easily 
 
achievable.

Page 1 of 6 
 
ACTIVITY : TESTING AND COMMISSIONING OF ELECTRICAL SYSTEMS 
 
ACTIVITIES  POTENTIAL  Who or  RISK RATING  CONTROL MEASURES Residual  Risk 
HAZARDS  What  Risk  Response 
might be  S  L  RR C  S  L RR  Owner 
harmed 
Task 1 : Mobilization of Materials ,Manpower & Testing of Electrical System) 
1. manual   Human Error  Workers  4  4  16     HSE Inducted workers  2  1  2 Site 
handling of   Personal  assigned     Experienced supervisor is assigned  engineer 
Electrical   Injury     Manual Handling techniques – SEC internal training  and 
Equipments   Property   Cover all and steel toe is provided  Foreman 
and   Damage   TBT is conducted every Saturday  assigned 
Accessories       STARRT Talk will be conducted by assigned 
  supervisor 
   Safe access and egress is provided. 
   HSE Coverage is provided 
  Unsafe access  Workers  4  3  12     Access and egress shall be cleared before mobilizing  2  1  2 Safety 
  causing  slips,  assigned   officer and  
materials. 
  trips and fall of   Loading bay for materials shall be identified and  Supervisor 
  material  made it known to workers. 
     Whenever materials are found un‐attended along 
    the access, immediately worked on clearing the 
 
access before mobilizing materials, or report to 
 
assigned safety officer to escalate the need to clear 
 
the access. 
 
 HSE officer is making daily site safety inspection. 
 
  Passing through  Workers  4  3  12     HSE Induction will cover designated access for safe  2  1  2 Safety 
  undesignated  assigned   offices and welfare facilities and work zone area.  officer and  
  footpath and   Safe access 1 meter is provided along site offices  Supervisor 
  walkways  and welfare facilities. 
     Access marked and protected. 
   Work zone are provided with scaffold access and 
  ramp (with 1 m in width of pedestrian access) 
  High / Cold  Assigne 5  3  15     Heat Related illness awareness shall be given to the  2  1  2 Safety 
  Temperature  d    workers.  officer and  
  Dehydration  worker   Sufficient rest shall be provided.  Supervisor 

Page 2 of 6 
 
     Cotton and light color clothes shall be worn. 
Heat stress /   Follow the approved heat stress management plan. 
stroke and   Be familiar with flag system and when to stop work 
cramps   due to high temperature. 
   Calibrated environmental meter is provided 
   Cool water is provided on site. 
 Approved oral rehydration supplement is provided. 
 Trained nurse of emergency response is assigned. 
Task 2 : Working at Heights with Ladder & Scaffolding  
Working at  UN‐safe  Assigned  4  4  16    Working Platform and works area to be barricaded  2  2  4  Safety 
heights  working  worker    and scaffolding to be inspected by HSE  officer and 
platform, un‐  Only Double lanyard safety harness to be used   Supervisor 
inspected and   All Tools to be secured with Lanyard  
un‐verified   Helmet provided to all workers 
 Ensure the worker’s fitness to work 
 Only certified scaffolders  are allowed to erect 
scaffolding on site. 
 Internal works mobile scaffold will be use if the 
condition requires and engineers will approve. 
 Mobile scaffold when in used shall ensure that the 
caster wheel is locked at all times.  
 Scaffold shall not be moved if the worker stands on 
the platform 
 Scaffold shall be erected by competent person 
 Heat related awareness shall be provided 
 Appropriate PPE shall be worn 
 STARRT Talk to be conducted along with daily safety 
task instruction 
Task 3 : Use of Hand Tools 
Use of hand tools  Presence of  Assigned  4  3  12    Appropriate PPE shall be worn.  2  1  2  Safety 
  sharp edges  worker     Leather hand gloves are provided  officer and  
     Suitable full body protective clothing  Supervisor 
 Leather hand gloves and provided 
 Toolbox Talks to be conducted along with daily 

Page 3 of 6 
 
safety task instruction 
 Work To be carried out under competent 
supervision 
Use of  Assigned  4  3  12    Visual inspection shall be conducted before each  2  1  2  Safety 
damaged hand   worker    use  officer and 
tools   Damage hand tools shall not be used and  Supervisor 
replacement of new hand tolls shall be made by 
storekeeper. 
 Appropriate PPE shall be worn 
 Toolbox Talks to be conducted along with daily 
safety task instruction 
 Work To be carried out under competent 
supervision 
Use of  Assigned  4  3  12    Correct Tools shall be used for the job  2  1  2  Safety 
Incorrect Tools  worker     Appropriate PPE shall be worn  officer and 
 Toolbox Talks to be conducted along with daily  Supervisor 
safety task instruction 
 Work To be carried out under competent 
supervision 
Task 4 : Lifting Equipment /  Use of Power Tools  
Lifting  Incompetent &  Lifting  4  4  16    Competent supervisor is assigned on site  2  2  4  Safety 
Unskilled crew  supervisor     Certified rigger and banksman  officer and  
and   Trained , Competent & Experienced crew shall be  Supervisor 
Assigned  involved  
worker   Lifting permit is required 
 Load chart of the equipment shall be made available 
on site at all times 
 Toolbox Talks to be conducted along with daily safety 
task instruction 
 Work To be carried out under competent supervision 
Substandard  Lifting  4  4  16    Third party inspected and certified crane shall be use.  2  2  4  Safety 
Lifting  supervisor     Internal inspection and tagging of lifting equipment  officer and  
Equipment  and  and accessories is regularly made by assigned person  Supervisor 
Assigned  (HSE Officer and foreman) 

Page 4 of 6 
 
worker   Pre‐use checklist is provided to operator. 
 Operator is trained on how important and how to fill 
the pre‐use checklist. 
 All equipments and lifting gears with visible defects 
shall immediately escalate to supplier for 
replacement or rectification. 
 No major mechanical repair to be made on site, 
otherwise replace the equipment. 
 Work will be executed under close supervision 
Wrong  Lifting  4  4  16    Construction Manager recommended equipment only  2  2  4  Safety 
selection of  supervisor    shall be use.  officer and  
lifting  and   No short cuts or use of non lifting equipment for the  Supervisor 
equipment  Assigned  task, right and suitable equipment should be as per 
worker  the approved plan and method statement. 
 Lifting equipment shall be designated by competent 
lifting supervisor. 
 Work will be executed under close supervision 
 STARRT Talk to be conducted along with daily safety 
task instruction 
 Mandatory PPE’s shall be used  
Use of power  Excessive  Assigned  4  3  12    Proper and regular maintenance  of powered tools  2  1  2  Safety 
tools  Noise  worker     As much as possible use the newly acquirement  officer and 
powered tools  Supervisor 
 If applicable low noisy equipment shall be used  
 For minor issue of noise experienced electrician shall 
do the maintenance otherwise it shall be made by 
suppliers designated technician. 
 Adequate PPE’s ( Ear defender ,Ear Plug ) Shall be 
used 
Heat & Dust  Assigned  4  4  16    Approval oral re‐hydration supplement is provided to  1  1  1  Safety 
worker    workers  officer and  
 Entry cycle / rest cycle shall be strictly followed  Supervisor 
 Constantly monitoring that heat index and flag 
system to prevent possible exposure to heat stress 

Page 5 of 6 
 
 Awareness shall be delivered by TBT and Training 
 Make sure to availability of cool water,  shelter to be 
provided as required  
 Trained and competent site nurse is provided. 
 First aid room is provided 
 Adequate PPE’s (Ear defender, Ear Plug ) Shall be use. 
Unguarded  Assigned  4  4  16    Rotating ( Pedestal grinder ,grinder ) equipment shall  2  2  4  Safety 
Tools  worker    have the  guard   officer and 
 Pre‐Inspection shall be conducted by user  Supervisor 
 Periodically inspection ( Daily / Monthly / Quarterly 
)shall be conducted  
 Adequate PPE’s ( Ear defender ,Ear Plug ) Shall be use 
Electricity  Assigned  5  4  20    Electrical socket / Plug shall be rated IP 54   1  1  1  Safety 
worker     Inspected , double insulated electrical fittings /  officer and 
equipment shall be used  Supervisor 
 Proper isolation ,grounding must be provided with 
ELCB protection 
 TBT Shall be conducted prior to commencing any 
electrical activity 
 Close supervision shall be in place 
 Ensure that cables are protected from water ,hot ,& 
Sharp metals or  any materials that could damage the 
cable 
 Pre‐Inspection shall be carried out prior to applying 
the electrical equipment 
 Mandatory PPE’s shall be used  
 
Prepared by:  Reviewed by: Approved by  :
   
Signature:  Signature:  Signature: 
Ashique Thenath (Tech. Office Engineer)  Said Abdelaziz ( Elec. Project  Manager)   (SEC Safety  Manager) 
Date: 16/01/2019  Date: 16/01/2019 Date: 
 