TRF PUNCH LIST (STAR 1)

S.no Description

1 Plant communication to be done

The sheaves of deflector sheave arrangement is mismatching with


2
trolley ropes in the operation of boom hoist so that should modify

3 Approach should provide to roller girder

4 Canopy should provide to all out door panels

5 Canopy should provide to all out door motors


6 Tray should arrange under rope drums

7 Covering sheet should provide on cable trays

8 Approach should provide to EOT

9 Approach, walkway &handrail should provide on discharge trolley

10 Return belt of shuttle conveyor is touching with structure


Hand rail at hopper gate and safety ring to monkey ladder to
11
approach hopper gate should provide

12 Dust wall should be widen for grab operation

Deflector sheave supporting arrangement is not withstanding the


13
load of spill plate so that should modify

14 Additional support should provide to spill plate(chain)

15 Ehouse1 AC openings should close


16 Proper approach to panel walkway in Ehouse1 should provide

17 Protection sheets should provide for power outlets in all panels

18 Proper alignment should provide to boom hoist thruster brake

19 The cabin gate should modify

20 Main trolley hoist sheave casting problem


21 Trolley rope touching with equalizer beam in fixed boom end

22 Cabin view should provide in operator cabin

23 Gratings should locked with clamps

24 Hand rail should locked with nut and bolt

25 Hand rail should provide in Luffing boom end


26 Dust suppression system to be commission

27 Hopper weighing system to be commission

28 Belt weighing system to be commission

29 D G system to be commission