Commissioning of GSU-1

Activity Expected Completion Date

Hand Rail accessories fixing on Luffing Boom 21.09.13


Rail Alignment on Fixed Boom and Luffing Boom 26.09.13
Rope Reeving for Trolley Travel drive
TROLLEY

limit swt instllation, Connection, FB to PLC


01.10.13
Cam limit Swt setting and FB to PLC

Operate Motor through Jystic from Cabin.

Rope reeving for Hold-Close Drive


HOLD/CLOSE

Adjust Cam limit Swt and take feedback to PLC 05.10.13

Operate Motor through Jystic

LT check with PCRD.


LONG TRAVEL

LT check with Rail Clamp.


07.10.13
Operate LT from Cabin.

Insatallation of Limit Swts for LT

Communication with PLC


FEEDER
VIBRO-

08.10.13
Operate from Cabin
MOVEMENT
CABIN

Operate from Cabin 10.10.13

Belt Laying, Jointing


SHUTTLE CONVEYOR

Control check of Shuttle conveyor

Limit Swt Install and Connection, FB Check 13.10.13


Trial of Shuttle conveyor from LCS and Cabin

Belt Weigher System Commission


WEIGHMENT
HOPPER

Hopper Weighment System Commission 14.10.13


DG

Commissioning of DG 15.10.13
19.09.13

Remarks
Commissioning of GSU-2

Activity Expected Completion Date

Charging of ISU 26.09.13

Charging of Hold – Close drive 27.09.13

Charging of Trolley travel drive 28.09.13

Charging of Boom Hoist drive 29.09.13

Charging of PLC 30.09.13

Rope Changing for Boom Hoist drive 30.09.13

Boom Lowering 02.10.13

Hand Rail accessories fixing on Luffing Boom 05.10.13


Rail Alignment on Fixed Boom and Luffing Boom 10.10.13
Rope Reeving for Trolley Travel drive
TROLLEY

limit swt instllation, Connection, FB to PLC


12.10.13
Cam limit Swt setting and FB to PLC
Operate Motor through Jystic from Cabin.

Rope reeving for Hold-Close Drive


HOLD/CLOSE

Adjust Cam limit Swt and take feedback to PLC 16.10.13

Operate Motor through Jystic

LT check with PCRD.


LONG TRAVEL

LT check with Rail Clamp.


18.10.13
Operate LT from Cabin.

Insatallation of Limit Swts for LT

Communication with PLC


FEEDER
VIBRO-

19.10.13
Operate from Cabin
MOVEMENT
CABIN

Operate from Cabin 22.10.13

Belt Laying, Jointing


E CONVEYOR

26.10.13
SHUTTLE CONVEYOR
Control check of Shuttle conveyor

Limit Swt Install and Connection, FB Check


26.10.13
Trial of Shuttle conveyor from LCS and Cabin

Belt Weigher System Commission


WEIGHMENT
HOPPER

Hopper Weighment System Commission 28.10.13


DG

Commissioning of DG 30.10.13