Matrix Excelcon Sdn Bhd

Project Title : CADANGAN PEMBANGUNAN 51 UNIT KEDAI PEJABAT YANG MENGANDUNGI :


1) KEDAI PEJABAT 2 TINGKAT PT NO : 27806 - 27854 = 49 UNIT
2) KEDAI PEJABAT 2½ TINGKAT PT NO : PT27805, PT27855 = 2 UNIT
3) BANGUNAN PENCAWANG ELEKTRIK = 1 UNIT
PUSAT KOMERSIAL KOTA GADONG PERDANA(KOTA GADONG PERDANA BIZ),
KOTA GADONG PERDANA, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS

Scope Of Works : Softlandscape Works At Tiara Sendayan BIZ(Galleria Unit)


Developer : Matrix Concepts (N/S) Sdn Bhd
Main Contractor : Matrix Excelcon Sdn Bhd
Sub Contractor : Evergreen Nursery
Date : __________________

Final Inspection / Handover Checklist for Landscape Works


Comments
Actual Site
No Item / Description T.Dia C.T.H O.H P.Dist Drawing Qty Remarks
Qty
A B C

A Tree / Palm
1 Ficus Lyrata 65mm N/A N/A N/A 11 nos 11 nos
2 Wodyetia Bifurcata N/A 1.5m N/A N/A nos 2 nos
3 Neomarica Longfolia N/A N/A 300mm N/A 1125 nos 1125 nos

B Other Works
Supply Machines for the Purpose of
1 35 nos
Planting Tress

Additional Comments : __________________________________________________________________________________________


__________________________________________________________________________________________
__________________________________________________________________________________________

Note : A : Approved
B : Rejected
C : Approved With Comments

* All RC works & M&E works to be inspected & verified by relevant engineer.
* All M&E Works & equivalents works is mandatory for testing & commissioning & functionable as per client requirement.

Requested By : Prepared By : Verified By :

____________________ ____________________ ______________________________


Sub Contractor Main Contractor Client / Architectural Consultant
Name : Name : Name :
Matrix Excelcon Sdn Bhd
Project Title : PROPOSED HARD AND LANDSCAPE FOR :
PROPOSED MIXED DEVELOPMENT AT TIARA SENDAYAN WITH APPROXIMATELY
294.54 ACRES AT LOT PT23760 H.S(D) 455372(TIARA SENDAYAN COMMON STAGE 1)
MUKIM LABU, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS
UNTUK TETUAN MAJLIS AGAMA ISLAM NEGERI SEMBILAN(MAINS)

Scope Of Works : Softlandscape Works At Tiara Sendayan Common(JKR road)


Developer : Matrix Concepts (N/S) Sdn Bhd
Main Contractor : Matrix Excelcon Sdn Bhd
Sub Contractor : Yong Hoo Pottery
Date : __________________

Final Inspection / Handover Checklist for Landscape Works


Actual Site Comments
No Item / Description T.Dia C.T.H O.H P.Dist Drawing Qty Remarks
Qty A B C
A Trees
1 Roystonea Oleraceae N/A 1.5 N/A 6m c/c 30 nos 80 nos
2 Roystonea Oleraceae N/A 1.4 N/A 6m c/c 30 nos - nos
3 Roystonea Oleraceae N/A 1.3 N/A 6m c/c 20 nos - nos

B Shrub
1 Loropetalum chinensis N/A N/A 450mm 400mm c/c 350 nos 800 nos

Additional Comments : __________________________________________________________________________________________


__________________________________________________________________________________________
__________________________________________________________________________________________

Note : A : Approved
B : Rejected
C : Approved With Comments

* All RC works & M&E works to be inspected & verified by relevant engineer.
* All M&E Works & equivalents works is mandatory for testing & commissioning & functionable as per client requirement.

Requested By : Prepared By : Verified By :

____________________ ____________________ ______________________________


Sub Contractor Main Contractor Client / Architectural Consultant
Name : Name : Name :
Matrix Excelcon Sdn Bhd
Project Title : PROPOSED HARD AND LANDSCAPE FOR :
PROPOSED MIXED DEVELOPMENT AT TIARA SENDAYAN WITH APPROXIM
294.54 ACRES AT LOT PT23760 H.S(D) 455372(TIARA SENDAYAN COMMON ST
MUKIM LABU, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS
UNTUK TETUAN MAJLIS AGAMA ISLAM NEGERI SEMBILAN(MAINS)

Scope Of Works : Softlandscape Works At Tiara Sendayan Common(Entrance)


Developer : Matrix Concepts (N/S) Sdn Bhd
Main Contractor : Matrix Excelcon Sdn Bhd
Sub Contractor : Evergreen Nursery

Final Inspection / Handover Checklist for Landscape Works

No Item / Description T.Dia C.T.H O.H P.Dist

A Shrub
1 Eugenia Oleina N/A N/A 400mm N/A
2 Turnera Ulmifolia N/A N/A 400mm N/A
3 Loropetalum Chinese N/A N/A 400 N/A

B Others
1 Roots Barriers(9m length)

Additional Comments : ___________________________________________________________________


____________________________________________________________________
____________________________________________________________________

Note : A : Approved
B : Rejected
C : Approved With Comments

* All RC works & M&E works to be inspected & verified by relevant engineer.
* All M&E Works & equivalents works is mandatory for testing & commissioning & functionable as per clie
Requested By : Prepared By :

____________________ ____________________
Sub Contractor Main Contractor
Name : Name :
DAYAN WITH APPROXIMATELY
SENDAYAN COMMON STAGE 1)
BILAN DARUL KHUSUS
SEMBILAN(MAINS)

Entrance)

Date : __________________

Comments
Actual Site
Drawing Qty Remarks
Qty
A B C

300 nos 138 nos


420 nos 300 nos
500 nos 316 nos

18 rolls

_______________________________________________
______________________________________________
______________________________________________

ing & functionable as per client requirement.


Verified By :

______________________________
Client / Architectural Consultant
Name :
Matrix Excelcon Sdn Bhd
Project Title : PROPOSED HARD AND LANDSCAPE FOR :
PROPOSED MIXED DEVELOPMENT AT TIARA SENDAYAN WITH APPROXIM
294.54 ACRES AT LOT PT23760 H.S(D) 455372(TIARA SENDAYAN COMMON ST
MUKIM LABU, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS
UNTUK TETUAN MAJLIS AGAMA ISLAM NEGERI SEMBILAN(MAINS)

Scope Of Works : Softlandscape Works At Tiara Sendayan Common(Roadside)


Developer : Matrix Concepts (N/S) Sdn Bhd
Main Contractor : Matrix Excelcon Sdn Bhd
Sub Contractor : Evergreen Nursery

Final Inspection / Handover Checklist for Landscape Works

No Item / Description T.Dia C.T.H O.H P.Dist

A Trees
1 Ormosia Pinnata 75mm N/A N/A N/A
2 Eugenia Polyantha 75mm N/A N/A N/A
3 Fragrea Fragrans 75mm N/A N/A N/A

B Shrub
1 Acalypha Siamensis N/A N/A 300mm N/A
2 Carmona Retusa N/A N/A 300mm N/A
3 Ficus Nitida N/A N/A 300mm N/A

C Others
1 Roots Barriers(9m length)
Supply machines for purpose of
2
planting tress

Additional Comments : ___________________________________________________________________


____________________________________________________________________
____________________________________________________________________

Note : A : Approved
B : Rejected
C : Approved With Comments

* All RC works & M&E works to be inspected & verified by relevant engineer.
* All M&E Works & equivalents works is mandatory for testing & commissioning & functionable as per clie

Requested By : Prepared By :

____________________ ____________________
Sub Contractor Main Contractor
Name : Name :
DAYAN WITH APPROXIMATELY
SENDAYAN COMMON STAGE 1)
BILAN DARUL KHUSUS
SEMBILAN(MAINS)

Roadside)

Date : __________________

Comments
Actual Site
Drawing Qty Remarks
Qty
A B C

32 nos 49 nos
74 nos 68 nos
71 nos 42 nos

2250 nos 3020 nos


1795 nos 3450 nos
1795 nos 3200 nos

42 rolls

159

_______________________________________________
______________________________________________
______________________________________________
ing & functionable as per client requirement.

Verified By :

______________________________
Client / Architectural Consultant
Name :
Matrix Excelcon Sdn Bhd

PROPOSED MIXED DEVELOPMENT AT TIARA SENDAYAN WITH APPROX


294.54 ACRES AT LOT PT23760 H.S(D) 455372(TIARA SENDAYAN COMMON
MUKIM LABU, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSU
UNTUK TETUAN MAJLIS AGAMA ISLAM NEGERI SEMBILAN(MAINS)

Scope Of Works : Softlandscape Works At Tiara Sendayan Common(Central Park)


Developer : Matrix Concepts (N/S) Sdn Bhd
Main Contractor : Matrix Excelcon Sdn Bhd
Sub Contractor : Evergreen Nursery

Final Inspection / Handover Checklist for Landscape Works

T.Dia/Diam
No Item / Description C.T.H O.H P.Dist
eter

A Trees
1 Alstonia Angustifolia 125 - 150mm N/A 6 - 7m -
2 Andira Inermis 65mm 4.0m -
3 Xanthosthemon Chrysanthus 65mm 4.0m 6.0m
4 Caesalpinia Ferrea 65mm 4.5m -
5 Eugenia Polyantha 65mm 4.0m -
6 Bucida Molineti 55 - 60mm 4.5m 8.0m
7 Leptospermum Brachyandrum 65mm 4.0m -
8 Lagerstroemia Floribunda 75mm 4.5m -
9 Peltophorum Pterocarpum 65mm 4.0m -
10 Samanea Saman 75mm 4.5m -
11 Fragrea Fragrans 62.5mm 4.5m 8.0m

B Shrub
1 Acalypha Siamensis 9 dia. Beg 0.30m 0.30m
2 Costus Angustifolius 12 dia. Beg 0.35m 0.30m
3 Costus Speciosus 12 dia. beg 0.35m 0.30m
4 Eugenia Oleina 24 dia. Beg 1.30m 0.50m
5 Justica Gendarussa 9 dia. Beg 0.30m 0.30m
6 Loropetalum Chinensis Var. rubrum 9 dia. Beg 0.30m 0.30m
7 Neomarica Longifolia 9 dia. Beg 0.30m 0.30m
8 Althernanthera "Red" 9 dia. Beg 0.15m 0.15m
9 Tecomaria Capiensis 9 dia. Beg 0.30m 0.30m
10 Tabernaemontana Divaricata 'Dwarft' 9 dia. Beg 0.20m 0.30m
C Aquatic Plant
1 Acrostichum Aureum 9 dia. Beg 0.50m 0.40m
2 Cyperus Papyrus 9 dia. Beg 0.60m 0.40m
3 Thypa Angustifolia 9 dia. Beg 0.50m 0.40m
4 Thalia Geniculata 9 dia. Beg 0.50m 0.40m

D Bamboo
1 Thyrsostachys Siamensis(in canes of 3-5) 24 dia. Beg 3.00m 0.50m

E Turfing
1 Axonopus Compressus Close Turfing
2 Zoysia Matrella Close Turfing

Additional Comments : ________________________________________________________________


__________________________________________________________________
__________________________________________________________________

Note : A : Approved
B : Rejected
C : Approved With Comments

* All RC works & M&E works to be inspected & verified by relevant engineer.
* All M&E Works & equivalents works is mandatory for testing & commissioning & functionable as per

Requested By : Prepared By :

____________________ ____________________
Sub Contractor Main Contractor
Name : Name :
AYAN WITH APPROXIMATELY
ENDAYAN COMMON STAGE 1)
ILAN DARUL KHUSUS
EMBILAN(MAINS)

Central Park)

Date : __________________

Comments
Actual Site
Drawing Qty Remarks
Qty
A B C

2 nos 2 nos
15 nos 15 nos
20 nos 20 nos
40 nos 40 nos
30 nos 30 nos
32 nos 32 nos
10 nos 10 nos
62 nos 62 nos
40 nos 40 nos
6 nos 6 nos
52 nos 52 nos

133 nos 133 nos


473 nos 473 nos
440 nos 440 nos
208 nos 208 nos
579 nos 579 nos
162 nos 162 nos
400 nos 400 nos
1289 nos 1289 nos
656 nos 656 nos
739 nos 739 nos
622 nos 622 nos
563 nos 563 nos
736 nos 736 nos
619 nos 619 nos

508 nos 508 nos

3124 m² 3124 m²
22500 m² 22500 m²

______________________________________________
_____________________________________________
_____________________________________________

g & functionable as per client requirement.

Verified By :

______________________________
Client / Architectural Consultant
Name :
Matrix Excelcon Sdn Bhd
Project Title : CADANGAN LANDSKAP BAGI CADANGAN PERUMAHAN DI TIARA SEND
SELUAS 294.64 EKAR DI ATAS LOT PT23760 H.S(D) 155372 TIARA SENDAYAN
MUKIM LABU, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS

Scope Of Works : Softlandscape Works At Tiara Sendayan Precinct 9 Show Unit & Priority Area
Developer : Matrix Concepts (N/S) Sdn Bhd
Main Contractor : Matrix Excelcon Sdn Bhd
Sub Contractor : Evergreen Nursery

Final Inspection / Handover Checklist for Landscape Works

No Item / Description T.Dia C.T.H O.H P.Dist

A Trees
1 Busida Buseras 65mm N/A N/A N/A
2 Ficus Lyrata 65mm N/A N/A N/A

B Shrub
1 Excoecaria Cochinchinensis N/A N/A 500mm N/A
2 Eugenia Oleina N/A N/A 600mm N/A
3 Murraya Paniculata N/A N/A 500mm N/A
4 Tabernaemontana Corymbosa N/A N/A 450mm N/A
5 Hymenocalis Littoralis N/A N/A 400mm N/A
6 Acalypha Siamensis N/A N/A 450mm N/A

C Turfing
1 Zoysia Matrella N/A N/A N/A N/A

C Others
1 Roots Barriers(9m length)
Supply machines for purpose of
2
planting tress

Additional Comments : ___________________________________________________________________


____________________________________________________________________
____________________________________________________________________

Note : A : Approved
B : Rejected
C : Approved With Comments

* All RC works & M&E works to be inspected & verified by relevant engineer.
* All M&E Works & equivalents works is mandatory for testing & commissioning & functionable as per clie

Requested By : Prepared By :

____________________ ____________________
Sub Contractor Main Contractor
Name : Name :
UMAHAN DI TIARA SENDAYAN DENGAN LOT
155372 TIARA SENDAYAN
MBILAN DARUL KHUSUS)

Show Unit & Priority Area

Date : __________________

Comments
Actual Site
Drawing Qty Remarks
Qty
A B C

29 nos 29 nos
10 nos 10 nos

990 nos 990 nos


165 nos 165 nos
710 nos 710 nos
30 nos 30 nos
40 nos 40 nos
100 nos 100 nos

45 rolls

29 rolls

32

_______________________________________________
______________________________________________
______________________________________________

ing & functionable as per client requirement.

Verified By :

______________________________
Client / Architectural Consultant
Name :
Matrix Excelcon Sdn Bhd
Project Title : PROPOSED DEVELOPMENT OF 253 UNITS DOUBLE STOREY TERRACE HOUSES (TYPE A1 & A2) ON PT 11842 – PT 12094,
1 UNIT TNB SUB-STATION ON PT 12597 AND 1 UNIT PONDOK RUKUN TETANGGA WITH APPROXIMATELY 32.94 ACRES
(PART OF LAND FORMERLY KNOWN AS LOT 1118) AT SURIAMAN 2, BANDAR SRI SENDAYAN, DAERAH SEREMBAN,
NEGERI SEMBILAN DARUL KHUSUS

Scope Of Works : Hardlandscape Works At Priority Area


Developer : BSS Development Sdn Bhd
Main Contractor : Matrix Excelcon Sdn Bhd

Date : __________________

Final Inspection / Handover Checklist for Landscape Works


Comments
No Item / Description Remarks
A B C

A RC Walkway in broom brush finish

B RC Manhole Cover in broom brush finish

C Tree House

D Basketball court

E Futsal court

F Parcourse ( 4 sets )

G Concrete bench ( 7 nos )

H Reflexology path

Additional Comments : __________________________________________________________________________________________


__________________________________________________________________________________________
__________________________________________________________________________________________

Note : A : Approved
B : Rejected
C : Approved With Comments

* All RC works & M&E works to be inspected & verified by relevant engineer.

Prepared By : Verified By :

____________________ ________________________
Main Contractor Client / Architectural Consultant
Name : Name :
Matrix Excelcon Sdn Bhd
Project Title : CADANGAN PEMBANGUNAN SKIM PERUMAHAN DI ATAS LOT 912 SELUAS 194.437 EKAR (78.69 Ha. ),
DAN JALAN MASUK UTAMA DI ATAS LOT 33745, ARA SENDAYAN DI MUKIM RASAH, DAERAH SEREMBAN,
NEGERI SEMBILAN DARUL KHUSUS.

Scope Of Works : RC Foundation Works


Developer : BSS Development Sdn Bhd
Main Contractor : Matrix Excelcon Sdn Bhd
Sub Contractor : Tajukmas Construction Sdn Bhd
Date : __________________

Final Inspection / Handover Checklist for Landscape Works


Comments
No Item / Description Remarks
A B C

A Main Signage Ara

1 Size : 1750 mm x 850 mm 20300mm, 500 mm x 950 mm x


24804mm
2 Concrete Finish level (Evenness)

Additional Comments : __________________________________________________________________________________________


__________________________________________________________________________________________
__________________________________________________________________________________________

Note : A : Approved
B : Rejected
C : Approved With Comments

Requested By : Prepared By : Verified By :

____________________ ____________________ ________________________


Sub Contractor Main Contractor Client / Architectural Consultant
Name : Name : Name :
Matrix Excelcon Sdn Bhd
Project Title : CADANGAN PEMBANGUNAN SKIM PERUMAHAN DI ATAS LOT 912 SELUAS 194.437 EKAR (78.69 Ha. ),
DAN JALAN MASUK UTAMA DI ATAS LOT 33745, ARA SENDAYAN DI MUKIM RASAH, DAERAH SEREMBAN,
NEGERI SEMBILAN DARUL KHUSUS.

Scope Of Works : Signage Lighting


Developer : BSS Development Sdn Bhd
Main Contractor : Matrix Excelcon Sdn Bhd
Sub Contractor : OTT Electrical Engineering
Date : __________________

Final Inspection / Handover Checklist for Landscape Works


Comments
No Item / Description Remarks
A B C

A Main Signage Ara


1 Flood Light : 20 nos warm light , 15W
2 LED RGB buried light : 3 nos , 12W
3 Electrical Junction Box : 1 nos
4 Testing & Commissioning

Additional Comments : __________________________________________________________________________________________


__________________________________________________________________________________________
__________________________________________________________________________________________

Note : A : Approved
B : Rejected
C : Approved With Comments

Requested By : Prepared By : Verified By :

____________________ ____________________ ________________________


Sub Contractor Main Contractor Client / Architectural Consultant
Name : Name : Name :