CONSTRUCTION OF LOAD CENTER 3 (LC-3) AT KING KHALED INTERNATIONAL AIRPORT (KKIA)


INSPECTION TEST PLAN FOR MECHANICAL WORKS
CONTRACTOR: SAUDI SERVICES ELECTRO MECHANICAL WORKS. CO. (SSEM) ITP Ref. No.: 085-ITP-M-PS-00 ISSUANCE: 00
(Close Joint Stock Company)
CONTRACT NO.: R-15-085-BF-0 REVISION: 00
TITLE: MECHANICAL WORKS Sec Title.: PLUMBING SYSTEM Date: Nov 2015

Inspection / Test Requirements Reference Documentation Method of Verification Demonstrated Evidence


Activity Activity Description
No. Test or Inspection Performed Stage / Frequency Test Required Code/Spec/Etc. Acceptance Criteria SSEM AECOM Report Checklist/Form
1.0 PLUMBING SYSTEM
1.1 Review of Document

Verifying Documents Manufacturer recommendation


1.1.1 Material Documents Technical Submittal SSEM CHECK Project Specification H RR QCP
ReferenceTechnical Submittal Specification /Standards

1.2 Material Inspection

Visual Inspection/Verify materials Manufacturer recommendation MR/MIR


1.2.1 Water Storage Tank After delivery at site SSEM CHECK Project Specification H W
comply Specification /Standards 085-IC-M-PS 00

Material test certificates, Material


Visual Inspection/Verify materials identification, Approved Material as per MR/MIR
1.2.2 Pipe After delivery at site SSEM CHECK Project Specification H W
comply Specifications/Approved Construction 085-IC-M-PS 00
Drawings

Valves, Fittings, Pipe Supports, Plumbing Visual Inspection/Verify materials Manufacturer recommendation MR/MIR
1.2.3 After delivery at site SSEM CHECK Project Specification H W
Fixtures and Trim, Etc. comply Specification /Standards IC-M-PS-00

1.3 Installation

Project Specification/Approved WIR


1.3.1 General Plumbing Visual Inspection After installation SSEM CHECK Project Specification H S
Drawings/Survey Verification 085-IC-M-PS 00

Washroom and Toilet Room: After completion of fit-up Manufacturer recommendation WIR
1.3.2 Visual Inspection SSEM CHECK Project Specification H S
a. installation of fixtures and piping alignment Specification /Standards 085-IC-M-PS 00

Installation of Plumbing Fixtures:


a. fixtures installed to provide access for
cleaning both the fixture and sorrounding area
Project Specification/Approved WIR
1.3.3 Visual Inspection After completion of installation SSEM CHECK Project Specification H S
b. Fixture set level and proper alignment to Construction Drawings 085-IC-M-PS 007
adjacent wall
c. Joints formed between fixtures and wall of
floors are watertight

LEGEND:
W - Witness Point H - Hold Point S - Surveillance RR - Review of Report Page 1 of 2 085-ITP-M-PS 007
Water Closets:
a. Fixture and flushing device
b.Elongated bowls for public
used (dwelling units closed-front seats)
Manufacturer recommendation
c. Water closet seats sized for the water closet
After completion of installation Specification /Standards/Approved WIR
1.3.4 bowl type and of nonabsorber material Visual Inspection SSEM CHECK Project Specification H W
Prior to Leak Test Construction Drawings/Method 085-IC-M-PS 007
d.installation corrosion resistant screws or bolts
Statements
e. Flush tank accessible for repair and
replacement
f. installation of Flushometer valves and tanks
g. Cold water supply installation

Urinals and Bidets: Manufacturer recommendation


a. Fixture and flushing device After installation of all flushing Specification /Standards/Approved WIR
1.3.5 Visual Inspection SSEM CHECK Project Specification H W
b. Surrounding material is waterfroofed and device/ all fittings and valves Construction Drawings/Method 085-IC-M-PS 007
nonabsorbent Statements
Showers, Bathtubs and Whirpool Tubes: a.
Fixture, faucet, shower and tub/shower
combination valve (balanced pressure,
thermostatic or combination thereof) has a Manufacturer recommendation
mean to limit temperature Specification /Standards/Approved WIR
1.3.6 Visual Inspection Prior to sterilization SSEM CHECK Project Specification H S
b. Hot and cold water supplied connection Construction Drawings/Method 085-IC-M-PS 007
c. hand held showers installation Statements
d. Flushometer valves and tanks

Lavatories and Sinks:


a. Fixture, faucet, and fixture fittings
b. Hot and cold water supplied connection
c. flexible hose spray and pull-out spout
d. sink faucet Project Specification/Approved
After completed installation of WIR
1.3.7 e. shut off valves supplied Visual Inspection SSEM CHECK Project Specification Construction Drawings/Method H W
plumbing fixtures and trim 085-IC-M-PS 007
f. Strainer, crossbar or stopper installed on Statements
waste outlet
g. Fixture strap, liquid seal, detection of leaks on
strap

Water Heaters and Storage Tanks: Manufacturer recommendation


a.Water heater After completed installation Specification /Standards/Approved WIR
1.3.8 Inspection/Test Requirements SSEM CHECK Project Specification H S
b. Cold waterline valve Prior to leak test Construction Drawings/Method 085-IC-M-PS 007
c. oulet temperature Statements
1.4 Testing

After complete installation of SSEM CHECK / Project Specification/Approved TR


1.4.1 Flushing , Cleaning and Disinfection Visual Inspection / Test Requirements Project Specification H W/S
piping system THIRD PARTY Construction Drawings 085-IC-M-PS 007

Manufacturer recommendation
After complete installation of SSEM CHECK / Specification/Approved Construction TR
1.4.2 Hydrostatic Test Inspection/Test Requirements Project Specification H W/RR
piping system THIRD PARTY Drawings/Method Statement/Testing 085-IC-M-PS 007
Procedure

GACA - General Authority of Civil


ABBREVIATIONS: N/A - NOT APPLICABLE W - WITNESS POINT S - SURVEILLANCE AECOM - Engineer
Aviation

SSEM - Saudi Services for Electro


Note: H - HOLD POINT RR - REVIEW OF REPORT
Mechanical Works. Co.

LEGEND:
W - Witness Point H - Hold Point S - Surveillance RR - Review of Report Page 2 of 2 085-ITP-M-PS 007