Construction Productivity norms

Norm /
Sl # Vehicle/Equipment Act.no Commodities UOM Remarks
M.day
1 Mason Block Masonry - Normal Sqm 10

Block Masonry - Reinforced Sqm 8

Concrete Cum 30

Screed Sqm 20

Plastering-External Sqm 10 Including preparation

Plastering-Internal Sqm 12 Including preparation

Rip-Rap Works Sqm 20 Mortar Rip-Rap

Terrazo Tiling Sqm 12

Ceramic Tiling Sqm 6

Marble tiling Sqm 3

Stone Cladding Sqm 2.5

Interlock Tiling Sqm 15

Plain Cement Tiling Sqm 20

Kerb fixing RM 25

2 Shuttering Carpenter Formwork-Footings, foundations, ground Sqm 8

Formwork-Columns, pedestals Sqm 6

Formwork-Beams and slabs Sqm 8

Formwork-Tie beams, arches, lintels Sqm 5

Formwork-Walls Sqm 8

Formwork-Circular, special shapes Sqm 4

Formwork- Making timber shutters Sqm 8

3 Steel Fixer Reinforcement-Cutting & Bending Kg 400

Reinforcement-Tying < 12mm Kg 250

Reinforcement-Tying > 12mm Kg 300

4 Painter Painting-Emulsion Sqm 15 Primer+2 coats

Epoxy Coating Sqm 10 Primer+2 coats

Painting-Texture/Special Sqm 10 Primer+2 coats

Painting-Enamel/Wood Sqm 10 Primer+2 coats

5 Welder DSS/SS Welding Inch dia 10

CS/LTCS Welding Inch dia 50 Flow line