Area wise Qty

S.no Description UOM Quantity


1 Manual Excavation cum 4.53
2 Machine Escavation cum 86.15
3 Hard Rock excavation cum 79.68
4 Disposal cum 90.68
5 Blinding concrete cum 20.16
6 Reinforcement MT 0.78
7 Anchor Bolts MT 0.05
8 Post Dril Anchor Bolts Nos 372
9 Sleeves M 1126
10 RCC cum 10.4
11 Grouting cum 0.81
12 Cable trench Excavation cum 8400.66
13 Concrete Paving Sqm 3173.5
14 Asphalt paving Sqm 575
15 Interlock paving Sqm 88.33