PLATE NO 1 FOUNDATION STRUCTURES

Components: footing pad, footing tie, wall footing, pedestal

Volume of Soil for Excavation

Column Footing

Footing 1, F1 (n1=9 units)


𝑉𝑜𝑙𝑢𝑚𝑒 1, 𝑉𝐸𝐹1 = 𝑥1 𝑦1 𝑑1 𝑛1 = (1.2)(1.2)(1.5)(9) = 19.44 𝑚3

Footing 2, F2 (n2=2 units)


𝑉𝑜𝑙𝑢𝑚𝑒 2, 𝑉𝐸𝐹2 = 𝑥2 𝑦2 𝑑2 𝑛2 = (2.7)(1.2)(1.5)(2) = 9.72 𝑚3

Footing 3, F3 (n3=2 units)


𝑉𝑜𝑙𝑢𝑚𝑒 3, 𝑉𝐸𝐹3 = 𝑥3 𝑦3 𝑑3 𝑛3 = (3.2)(1.2)(1.5)(2) = 11.52 𝑚3

Footing 4, F4 (n4=1 unit)


𝑉𝑜𝑙𝑢𝑚𝑒 4, 𝑉𝐸𝐹4 = 𝑥4 𝑦4 𝑑4 𝑛4 = (2.1)(1.2)(1.5)(1) = 3.78 𝑚3

𝑇𝑜𝑡𝑎𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 , 𝑉𝐸𝐹𝑇 = 𝑉𝐸𝐹1 + 𝑉𝐸𝐹2 + 𝑉𝐸𝐹3 + 𝑉𝐸𝐹4 = 19.44 + 9.72 + 11.52 + 3.78
𝑉𝐸𝐹𝑇 = 44.46 𝑚3

Wall Footing

𝑇𝑜𝑡𝑎𝑙 𝐿𝑒𝑛𝑔𝑡ℎ 𝑊𝑎𝑙𝑙 𝐹𝑜𝑜𝑡𝑖𝑛𝑔 1, ∑𝐿𝑊𝐹1 = 2.88 + 2.88 + 2.88 + 2.17 = 19.44 𝑚3
∑𝐿𝑊𝐹1 = 10.81 𝑚

𝑇𝑜𝑡𝑎𝑙 𝐿𝑒𝑛𝑔𝑡ℎ 𝑊𝑎𝑙𝑙 𝐹𝑜𝑜𝑡𝑖𝑛𝑔 2, 𝐿𝑊𝐹2 = 1.18 + 1.00 + 1.74 + 2.93 + 4.03 + 3.61 + 2.22 + 1.43 +
1.72 + 3.74 + 1.74 + 3.21 + 0.29 + 1.15 + 2.88 + 1.21 +
+ 2.88 + 1.21 + 2.88 + 1.84
∑𝐿𝑊𝐹2 = 38.80 𝑚

𝑉𝑜𝑙𝑢𝑚𝑒 𝐸𝑥𝑐𝑎𝑣𝑎𝑡𝑖𝑜𝑛 𝑊𝑎𝑙𝑙 𝐹𝑜𝑜𝑡𝑖𝑛𝑔 1, 𝑉𝐸𝑊𝐹1 = (𝑥1 )(∑𝐿𝑊𝐹1 )(𝑑1 ) = (0.4)(10.81)(0.35)


𝑉𝐸𝑊𝐹1 = 1.51 𝑚3

𝑉𝑜𝑙𝑢𝑚𝑒 𝐸𝑥𝑐𝑎𝑣𝑎𝑡𝑖𝑜𝑛 𝑊𝑎𝑙𝑙 𝐹𝑜𝑜𝑡𝑖𝑛𝑔 2, 𝑉𝐸𝑊𝐹2 = (𝑥2 )(∑𝐿𝑊𝐹2 )(𝑑2 ) = (0.4)(38.80)(0.35)


𝑉𝐸𝑊𝐹2 = 5.34 𝑚3

𝑇𝑜𝑡𝑎𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 𝐸𝑥𝑐𝑎𝑣𝑎𝑡𝑖𝑜𝑛 𝑊𝑎𝑙𝑙 𝐹𝑜𝑜𝑡𝑖𝑛𝑔, 𝑉𝐸𝑊𝐹𝑇 = 𝑉𝐸𝑊𝐹1 + 𝑉𝐸𝑊𝐹2 = 1.51 + 5.43
𝑉𝐸𝑊𝐹𝑇 = 6.94 𝑚3

Footing Tie Beam


Not applicabledue above Natural Grade Line (NGL).

𝑇𝑜𝑡𝑎𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑆𝑜𝑖𝑙 𝐸𝑥𝑐𝑎𝑣𝑎𝑡𝑒𝑑 , 𝑉𝐸𝑇 = 𝑉𝐸𝐹𝑇 + 𝑉𝐸𝑊1 + 𝑉𝐸𝑊2 + 𝑉𝐸𝑊3


= 44.46 + 38.80 + 1.51 + 6.94
𝑉𝐸𝑇 = 𝑉𝐸𝐹𝑇 + 𝑉𝐸𝑊𝐹1 + 𝑉𝐸𝑊𝐹2 + 𝑉𝐸𝑊3 = 51.40 𝑚3
VOLUME OF CONCRETE

Column footing

Footing 1, F1 (n1=9 units)


𝑉𝑜𝑙𝑢𝑚𝑒 1, 𝑉𝐶𝐹1 = 𝑥1 𝑦1 𝑑1 𝑛1 = (1.2)(1.2)(0.3)(9) = 3.89 𝑚3

Footing 2, F2 (n2=2 units)


𝑉𝑜𝑙𝑢𝑚𝑒 2, 𝑉𝐶𝐹2 = 𝑥2 𝑦2 𝑑2 𝑛2 = (2.7)(1.2)(0.3)(2) = 1.94 𝑚3

Footing 3, F3 (n3=2 units)


𝑉𝑜𝑙𝑢𝑚𝑒 3, 𝑉𝐶𝐹3 = 𝑥3 𝑦3 𝑑3 𝑛3 = (3.2)(1.2)(0.3)(2) = 2.30 𝑚3

Footing 4, F4 (n4=1 unit)


𝑉𝑜𝑙𝑢𝑚𝑒 4, 𝑉𝐸𝐹4 = 𝑥4 𝑦4 𝑑4 𝑛4 = (2.1)(1.2)(1.5)(1) = 0.76 𝑚3

𝑇𝑜𝑡𝑎𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 , 𝑉𝐶𝐹𝑇 = 𝑉𝐶𝐹1 + 𝑉𝐶𝐹2 + 𝑉𝐶𝐹3 + 𝑉𝐶𝐹4 = 3.89 + 1.94 + 2.30 + 0.76
𝑉𝐶𝐹𝑇 = 8.89 𝑚3

Wall footing

𝑉𝑜𝑙𝑢𝑚𝑒, 𝑉𝐶𝑊𝐹 = 𝑥𝑡𝐿𝑊𝐹𝑇


𝑇𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑤𝑎𝑙𝑙 𝑓𝑜𝑜𝑡𝑖𝑛𝑔, 𝐿𝑊𝐹𝑇 = 76.15 𝑚

𝑉𝑜𝑙𝑢𝑚𝑒, 𝑉𝐶𝑊𝐹 = (0.40)(0.15)(76.15) = 4.569 𝑚3

Footing Tie Beam

𝑉𝑜𝑙𝑢𝑚𝑒, 𝑉𝐹𝑇𝐵 = 𝑥𝑦𝐿 𝑇𝐵 = (1.2)(1.2)(0.3)(9) = 80.66 𝑚3


𝑇𝑜𝑡𝑎𝑙 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓𝑓𝑜𝑜𝑡𝑖𝑛𝑔 𝑡𝑖𝑒 𝑏𝑒𝑎𝑚, 𝐿𝐹𝑇𝐵 = 𝑚

𝑉𝑜𝑙𝑢𝑚𝑒, 𝑉𝐹𝑇𝐵 = (0.20)(0.30)(80.66) = 4.84 𝑚3

𝑇𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒, 𝑉𝐶𝑇 = 𝑉𝐶𝐹𝑇 + 𝑉𝐶𝑤𝐹 + 𝑉𝐹𝑇𝐵 = 8.89 + 4.569 + 4.84
𝑉𝐶𝑇 = 18.299 𝑚3

Materials: (Class A Mixture)

𝐶𝑒𝑚𝑒𝑛𝑡: 𝑉𝐶𝑇 × 9 = 18.299 × 9 = 164.691


≈ 165 𝐵𝑎𝑔𝑠 − 40 𝑘𝑔 𝑃𝑜𝑟𝑡𝑙𝑎𝑛𝑑 𝐶𝑒𝑚𝑒𝑛𝑡

𝑆𝑎𝑛𝑑: 𝑉𝐶𝑇 × 0.5 = 18.299 × 0.5 = 9.15 𝑚3


≈ 10 𝑚3

𝐺𝑟𝑎𝑣𝑒𝑙: 𝑉𝐶𝑇 × 1.0 = 14.51 × 1.0 = 18.299 𝑚3


≈ 19 𝑚3
VOLUME OF BACKFILL

Column footing

𝑇𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑐𝑜𝑙𝑢𝑚𝑛, 𝑉𝐶𝑇 = 0.35 × 0.25 × 0.45 × 19 = 0.75 𝑚3

𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑏𝑎𝑐𝑘𝑓𝑖𝑙𝑙, 𝑉𝐵𝐹𝐶 = 𝑉𝐸𝐹𝑇 − 𝑉𝐶𝐹𝑇 − 𝑉𝐶𝑇 = 44.46 − 8.89 − 0.75


𝑉𝐵𝐹𝐶 = 34.82 𝑚3

Wall Footing

𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑏𝑎𝑐𝑘𝑓𝑖𝑙𝑙, 𝑉𝐵𝐹𝑊𝐹 = 𝑉𝐸𝑊𝐹 − 𝑉𝐶𝑊𝐹 = 6.94 − 4.569


𝑉𝐵𝐹𝑊𝐹 = 2.371 𝑚3

Footing Tie Beam

No volume of backfill for footing tie beam since no excavation was made.

𝑇𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑏𝑎𝑐𝑘𝑓𝑖𝑙𝑙, 𝑉𝐵𝐹𝑇 = 𝑉𝐵𝐹𝐶 + 𝑉𝐵𝐹𝑊𝐹 = 34.82 + 2.371


𝑉𝐵𝐹𝑇 = 37.191 𝑚3

METAL REINFORCEMENT

Footing 1, F1 (n1=9 units)


𝑥1 = 1.20 𝑚 𝑦1 = 1.20 𝑚

Net Length of one cut bar (x and y – axes)


𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ, 𝐿 = 𝑥1 − 2(0.075) = 1.20 − 2(0.075) = 1.05 𝑚

No. of cut bars = 9 + 9 = 18

𝑇𝑜𝑡𝑎𝑙 𝑁𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠, 𝐶𝑇 = 𝑛𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠 × 𝑛1 = 18 × 9 = 162 𝑢𝑛𝑖𝑡𝑠

Use 6 m steel bar

6𝑚 6
𝑃𝑖𝑒𝑐𝑒𝑠, 𝑃 = = = 5.71 𝑠𝑎𝑦 5 𝑝𝑖𝑒𝑐𝑒𝑠
𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ 1.05

𝐶𝑇 162
𝑁𝑜. 𝑜𝑓 𝑝𝑖𝑒𝑐𝑒𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟 𝑜𝑓 6 𝑚 𝑙𝑒𝑛𝑔𝑡ℎ, 𝑁 = = = 32.4 𝑠𝑎𝑦 5 𝑝𝑖𝑒𝑐𝑒𝑠
𝑃 5
≈ 33 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Footing 2, F2 (n2 = 2 units)


𝑥2 = 2.70 𝑚 𝑦2 = 1.20 𝑚
For x – axis matting bars:

Net Length of one cut bar


𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ, 𝐿𝑥 = 𝑥2 − 2(0.075) = 2.70 − 2(0.075) = 2.55 𝑚

No. of cut bars =9 + 9 = 18

𝑇𝑜𝑡𝑎𝑙 𝑁𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠, 𝐶𝑇 = 𝑛𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠 × 𝑛2 = 18 × 2 = 36 𝑢𝑛𝑖𝑡𝑠

Use 6 m steel bar

6𝑚 6
𝑃𝑖𝑒𝑐𝑒𝑠, 𝑃 = = = 2.35 𝑠𝑎𝑦 2 𝑝𝑖𝑒𝑐𝑒𝑠
𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ 2.55

𝐶𝑇 36
𝑁𝑜. 𝑜𝑓 𝑝𝑖𝑒𝑐𝑒𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟 𝑜𝑓 6 𝑚 𝑙𝑒𝑛𝑔𝑡ℎ, 𝑁 = = = 18
𝑃 2
≈ 18 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

For y – axis matting bars:

Net Length of one cut bar


𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ, 𝐿𝑦 = 𝑦2 − 2(0.075) = 1.20 − 2(0.075) = 1.05 𝑚

No. of cut bars =9 pcs

𝑇𝑜𝑡𝑎𝑙 𝑁𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠, 𝐶𝑇 = 𝑛𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠 × 𝑛2 = 9 × 2 = 18𝑝𝑐𝑠

Use 6 m steel bar

6𝑚 6
𝑃𝑖𝑒𝑐𝑒𝑠, 𝑃 = = = 5.71 𝑠𝑎𝑦 5 𝑝𝑖𝑒𝑐𝑒𝑠
𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ 1.05

𝐶𝑇 18
𝑁𝑜. 𝑜𝑓 𝑝𝑖𝑒𝑐𝑒𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟 𝑜𝑓 6 𝑚 𝑙𝑒𝑛𝑔𝑡ℎ, 𝑁 = = = 3.6
𝑃 5
≈ 4 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Footing 3, F3 (n3 = 2 units)


𝑥3 = 3.20 𝑚 𝑦2 = 1.20 𝑚

For x – axis matting bars:

Net Length of one cut bar


𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ, 𝐿𝑥 = 𝑥3 − 2(0.075) = 3.20 − 2(0.075) = 3.05 𝑚

No. of cut bars = 20 pcs

𝑇𝑜𝑡𝑎𝑙 𝑁𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠, 𝐶𝑇 = 𝑛𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠 × 𝑛3 = 20 × 2 = 40 𝑝𝑐𝑠


Use 6 m steel bar

6𝑚 6
𝑃𝑖𝑒𝑐𝑒𝑠, 𝑃 = = = 1.96 𝑠𝑎𝑦 1 𝑝𝑖𝑒𝑐𝑒
𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ 3.05

𝐶𝑇 40
𝑁𝑜. 𝑜𝑓 𝑝𝑖𝑒𝑐𝑒𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟 𝑜𝑓 6 𝑚 𝑙𝑒𝑛𝑔𝑡ℎ, 𝑁 = = = 40
𝑃 1
≈ 40 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

For y – axis matting bars:

Net Length of one cut bar


𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ, 𝐿𝑦 = 𝑦3 − 2(0.075) = 1.20 − 2(0.075) = 1.05 𝑚

No. of cut bars =9 pcs

𝑇𝑜𝑡𝑎𝑙 𝑁𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠, 𝐶𝑇 = 𝑛𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠 × 𝑛2 = 9 × 2 = 18 𝑝𝑐𝑠

Use 6 m steel bar

6𝑚 6
𝑃𝑖𝑒𝑐𝑒𝑠, 𝑃 = = = 5.71 𝑠𝑎𝑦 5 𝑝𝑖𝑒𝑐𝑒𝑠
𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ 1.05

𝐶𝑇 18
𝑁𝑜. 𝑜𝑓 𝑝𝑖𝑒𝑐𝑒𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟 𝑜𝑓 6 𝑚 𝑙𝑒𝑛𝑔𝑡ℎ, 𝑁 = = = 3.6
𝑃 5
≈ 4 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Footing 4, F4 (n4= 1 unit)


𝑥4 = 1.20 𝑚 𝑦2 = 2.0 𝑚

For x – axis matting bars:

Net Length of one cut bar


𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ, 𝐿𝑥 = 𝑥4 − 2(0.075) = 1.20 − 2(0.075) = 1.05 𝑚

No. of cut bars = 10 pcs

𝑇𝑜𝑡𝑎𝑙 𝑁𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠, 𝐶𝑇 = 𝑛𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠 × 𝑛3 = 10 × 1 = 10 𝑝𝑐𝑠

Use 6 m steel bar

6𝑚 6
𝑃𝑖𝑒𝑐𝑒𝑠, 𝑃 = = = 5.71 𝑠𝑎𝑦 5𝑝𝑐𝑠
𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ 1.05

𝐶𝑇 10
𝑁𝑜. 𝑜𝑓 𝑝𝑖𝑒𝑐𝑒𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟 𝑜𝑓 6 𝑚 𝑙𝑒𝑛𝑔𝑡ℎ, 𝑁 = = =2
𝑃 5
≈ 2 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟
For y – axis matting bars:

Net Length of one cut bar


𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ, 𝐿𝑦 = 𝑦4 − 2(0.075) = 2.00 − 2(0.075) = 1.85 𝑚

No. of cut bars =9 pcs

𝑇𝑜𝑡𝑎𝑙 𝑁𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠, 𝐶𝑇 = 𝑛𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠 × 𝑛2 = 9 × 1 = 9 𝑝𝑐𝑠

Use 6 m steel bar

6𝑚 6
𝑃𝑖𝑒𝑐𝑒𝑠, 𝑃 = = = 3.24 𝑠𝑎𝑦 3 𝑝𝑖𝑒𝑐𝑒𝑠
𝑁𝑒𝑡 𝐿𝑒𝑛𝑔𝑡ℎ 1.05

𝐶𝑇 9
𝑁𝑜. 𝑜𝑓 𝑝𝑖𝑒𝑐𝑒𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟 𝑜𝑓 6 𝑚 𝑙𝑒𝑛𝑔𝑡ℎ, 𝑁 = = =3
𝑃 3
≈ 3 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

TIE WIRES

For F1 (n1 = 9)

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑥 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠)(𝑦 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠) = 9 × 9 = 81

Use 0.40 m length of tie wire.

𝐼 × 0.40 𝑚 81 × 0.40
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = ×𝑛 = ×9
53 𝑚/𝑘𝑔 53

𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = 5.5 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

For F2 (n2 = 2)

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑥 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠)(𝑦 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠) = 18 × 9 = 162

Use 0.40 m length of tie wire.

𝐼 × 0.40 𝑚 162 × 0.40


𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = ×𝑛 = ×2
53 𝑚/𝑘𝑔 53

𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = 2.45 𝑘𝑔


≈ 2.50𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

For F3 (n3 = 2)

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑥 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠)(𝑦 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠) = 20 × 9 = 180


Use 0.40 m length of tie wire.

𝐼 × 0.40 𝑚 162 × 0.40


𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = ×𝑛 = ×2
53 𝑚/𝑘𝑔 53

𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = 2.72 𝑘𝑔


≈ 3.0𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

For F4 (n4 = 1)

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑥 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠)(𝑦 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠) = 10 × 9 = 90

Use 0.40 m length of tie wire.

𝐼 × 0.40 𝑚 90 × 0.40
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = ×𝑛 = ×1
53 𝑚/𝑘𝑔 53

𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = 0.68 𝑘𝑔


≈ 0.75 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

WALL FOOTING

𝑇𝑜𝑡𝑎𝑙 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑊𝑎𝑙𝑙 𝐹𝑜𝑜𝑡𝑖𝑛𝑔, 𝐿𝑤 = 7.65 + 4.75 + 5.11 + 2.56 + 5.13 + 5.17 + 3.64 + 4.77 + 1.81
+ 12.56 + 2.11 + 3.64 + 1.68 + 4.1 + 2.77 + 4.4 × 2 + 4.25
+ 0.82 + 3.62 × 2 + 2.3 + 4.1 + 3.6 + 1.2 × 3 + 1.3 + 1.35
+ 1.2 + 3
𝐿𝑤 = 104.60 𝑚

𝑝𝑐𝑠 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠 𝑥 𝐿𝑤 2 × 104.60


𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁𝑀 = = = 34.87
6 𝑚/𝑏𝑎𝑟 6
≈ 35 𝑝𝑐𝑠 12 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

For cut bars

𝐿𝑤 104.60
𝑃𝑐𝑠 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠 = = = 348.67
𝑠𝑝𝑎𝑐𝑖𝑛𝑔 0.30
≈ 349

Use 6 m long steel bar

𝑁𝑒𝑡 𝑙𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟, 𝐿𝐶 = 0.4 − 2(0.075) + 0.15 𝑚 = 0.40 𝑚

6
𝑁𝑜. 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠 𝑝𝑒𝑟 6 𝑚 = = 15
0.4
349
𝑃𝑐𝑠 𝑜𝑓 𝑐𝑢𝑡 𝑏𝑎𝑟𝑠 = = 23.27
15
≈ 24 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

TIE WIRES

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠)(𝑐𝑢𝑡 𝑏𝑎𝑟𝑠) = 2 × 349 = 698

Use 0.40 m length of tie wire.

𝐼 × 0.40 𝑚 698 × 0.40


𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = ×𝑛 =
53 𝑚/𝑘𝑔 53

𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = 5.27 𝑘𝑔


≈ 5.50 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒

FOOTING TIE BEAM

At m = 3.15 m, n = 3

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4

4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 3.15 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 3 = 7.5
6 𝑚/𝑏𝑎𝑟 6
≈ 8 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 8 + 8 + 8 + 2 = 26 pcs

𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1


= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚

𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
26 × 0.78
= × 3 = 10.14
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 11 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 26 = 104

𝐼 × 0.40 × 𝑛 104 × 0.40 × 3


𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 2.35
53 𝑚/𝑘𝑔 53
𝑁 ≈ 2.50 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

At m = 2.16 m, n = 1

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4

4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 2.16 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 3 = 1.85
6 𝑚/𝑏𝑎𝑟 6
≈ 2 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 8 + 8 + 5 = 20 pcs

𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1


= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚

𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
21 × 0.78
= × 1 = 2.73
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 3 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 20 = 100

𝐼 × 0.40 × 𝑛 100 × 0.40 × 1


𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 0.604 𝑘𝑔
53 𝑚/𝑘𝑔 53
𝑁 ≈ 0.75 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

At m = 3.50 m, n = 5

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4

4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 3.50 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 5 = 13.75
6 𝑚/𝑏𝑎𝑟 6
≈ 14 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 28 pcs

𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1


= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚
𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
28 × 0.78
= × 5 = 18.2
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 19 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 28 = 112

𝐼 × 0.40 × 𝑛 112 × 0.40 × 5


𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 4.23
53 𝑚/𝑘𝑔 53
𝑁 ≈ 4.25 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

At m = 4.98 m, n = 2

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4

4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 4.98 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 2 = 7.36
6 𝑚/𝑏𝑎𝑟 6
≈ 8 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 24 + 11 = 35 pcs

𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1


= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚

𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
35 × 0.78
= × 2 = 9.1
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 10 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 35 = 140

𝐼 × 0.40 × 𝑛 140 × 0.40 × 2


𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 2.11
53 𝑚/𝑘𝑔 53
𝑁 ≈ 2.25 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

At m = 4.0 m, n = 1

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4


4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 2.6 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 1 = 2.15
6 𝑚/𝑏𝑎𝑟 6
≈ 3 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 24 pcs

𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1


= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚

𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
24 × 0.78
= × 1 = 3.12
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 4 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 24 = 96

𝐼 × 0.40 × 𝑛 96 × 0.40 × 1
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 0.72
53 𝑚/𝑘𝑔 53
𝑁 ≈ 0.75 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

At m = 3.45 m, n = 1

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4

4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 3.45 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 1 = 2.3
6 𝑚/𝑏𝑎𝑟 6
≈ 3 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 27 pcs

𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1


= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚

𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
27 × 0.78
= × 1 = 3.51
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 4 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟
Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 27 = 108

𝐼 × 0.40 × 𝑛 108 × 0.40 × 1


𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 0.82
53 𝑚/𝑘𝑔 53
𝑁 ≈ 1.0 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

At m = 1.5 m, n = 2

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4

4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 1.5 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 2 = 2.83
6 𝑚/𝑏𝑎𝑟 6
≈ 3 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 16 pcs

𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1


= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚

𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
16 × 0.78
= × 2 = 4.16
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 5 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 16 = 64

𝐼 × 0.40 × 𝑛 64 × 0.40 × 2
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 0.97
53 𝑚/𝑘𝑔 53
𝑁 ≈ 1.0 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

At m = 5.0 m, n = 1

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4

4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 5 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 1 = 3.75
6 𝑚/𝑏𝑎𝑟 6
≈ 4 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 36 pcs

𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1


= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚

𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
36 × 0.78
= × 1 = 4.68
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 5 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 36 = 144

𝐼 × 0.40 × 𝑛 144 × 0.40 × 1


𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 1.09
53 𝑚/𝑘𝑔 53
𝑁 ≈ 1.25 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

At m = 1.0 m, n = 1

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4

4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 1.0 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 1 = 1.08
6 𝑚/𝑏𝑎𝑟 6
≈ 2 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 10 pcs

𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1


= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚

𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
10 × 0.78
= × 1 = 1.3
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 2 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 10 = 40


𝐼 × 0.40 × 𝑛 40 × 0.40 × 1
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 0.30
53 𝑚/𝑘𝑔 53
𝑁 ≈ 0.50 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

At m = 4.0 m, n = 5

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4

4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 4 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 4 = 12.33
6 𝑚/𝑏𝑎𝑟 6
≈ 13 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 31 pcs

𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1


= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚

𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
31 × 0.78
= × 5 = 20.15
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 21 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 31 = 124

𝐼 × 0.40 × 𝑛 124 × 0.40 × 5


𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 4.68
53 𝑚/𝑘𝑔 53
𝑁 ≈ 4.75 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

At m = 1.90 m, n = 1

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4

4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 1.9 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 1 = 1.68
6 𝑚/𝑏𝑎𝑟 6
≈ 2 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 18 pcs


𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1
= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚

𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
18 × 0.78
= × 1 = 2.34
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 3 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 18 = 72

𝐼 × 0.40 × 𝑛 72 × 0.40 × 1
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 0.54
53 𝑚/𝑘𝑔 53
𝑁 ≈ 0.75 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

At m = 1.85 m, n = 1

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4

4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 1.85 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 1 = 1.65
6 𝑚/𝑏𝑎𝑟 6
≈ 2 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 18 pcs

𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1


= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚

𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
18 × 0.78
= × 1 = 2.34
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 3 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 18 = 72

𝐼 × 0.40 × 𝑛 72 × 0.40 × 1
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 0.54
53 𝑚/𝑘𝑔 53
𝑁 ≈ 0.75 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

At m = 1.70 m, n = 1

𝑁𝑜. 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑛𝑚 = 4

4 at 0.05 m, 4 at 0.10 m, 4 at 0.15 m, rest at 0.20 m O.C.

(𝑛𝑚 )(𝑚) + ℎ𝑜𝑜𝑘 4 × 1.70 + 2.5


𝑃𝑐𝑠 𝑜𝑓 𝑚𝑎𝑖𝑛 𝑏𝑎𝑟𝑠, 𝑁 = ×𝑛 = × 1 = 1.55
6 𝑚/𝑏𝑎𝑟 6
≈ 2 𝑝𝑐𝑠 16 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

𝑃𝑐𝑠 𝑜𝑓 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑛𝑆 = 8 pcs

𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = [𝑥 − 2(0.04)](2) + [𝑦 − 2(0.04)](2) + 0.1


= [0.2 − 0.08](2) + [0.3 − 0.08](2) + 0.1
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝐼𝑆 = 0.78 𝑚

𝑛𝑠 × 𝐼𝑠
𝑃𝑐𝑠 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟𝑠 𝑓𝑜𝑟 𝑠𝑡𝑖𝑟𝑟𝑢𝑝𝑠, 𝑁𝑆 = ×𝑛
6 𝑚/𝑏𝑎𝑟
8 × 0.78
= × 1 = 1.04
6 𝑚/𝑏𝑎𝑟
𝑁𝑆 ≈ 2 𝑝𝑐𝑠 10 𝑚𝑚𝜙 𝑥 6 𝑚 𝑠𝑡𝑒𝑒𝑙 𝑏𝑎𝑟

Tie Wire

𝑁𝑜. 𝑜𝑓 𝑐𝑜𝑛𝑛𝑒𝑐𝑡𝑖𝑜𝑛𝑠, 𝐼 = (𝑛𝑚 )(𝑛𝑠 ) = 4 × 8 = 32

𝐼 × 0.40 × 𝑛 32 × 0.40 × 1
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑡𝑖𝑒 𝑤𝑖𝑟𝑒, 𝑁 = = = 0.24
53 𝑚/𝑘𝑔 53
𝑁 ≈ 0.25 𝑘𝑔 𝑁𝑜. 16 𝐺. 𝐼. 𝑊𝑖𝑟𝑒

SUMMARY OF MATERIALS

𝑇𝑜𝑡𝑎𝑙 𝑒𝑥𝑐𝑎𝑣𝑎𝑡𝑒𝑑 𝑠𝑜𝑖𝑙: 51.4 𝑚3

𝑇𝑜𝑡𝑎𝑙 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑏𝑎𝑐𝑘𝑓𝑖𝑙𝑙: 37.19𝑚3

𝑃ℎ𝑝 265.00
𝐶𝑒𝑚𝑒𝑛𝑡: 165 𝑏𝑎𝑔𝑠 40 𝑘𝑔 𝑃𝑜𝑟𝑡𝑙𝑎𝑛𝑡 𝐶𝑒𝑚𝑒𝑛𝑡 × = 𝑃ℎ𝑝 43, 725.00
𝑏𝑎𝑔
𝑃ℎ𝑝 1300.00
𝑆𝑎𝑛𝑑: 10 𝑚3 × = 𝑃ℎ𝑝 4, 334.00
3 𝑚3

𝑃ℎ𝑝 1600.00
𝐺𝑟𝑎𝑣𝑒𝑙: 19𝑚3 × = 𝑃ℎ𝑝 10, 134.00
3 𝑚3
𝑆𝑡𝑒𝑒𝑙 𝐵𝑎𝑟𝑠:

𝑃ℎ𝑝 285.00
16 𝑚𝑚Ø × 6𝑚: 170 𝑝𝑐𝑠 × = 𝑃ℎ𝑝 48, 450.00
𝑝𝑐

𝑃ℎ𝑝 160.00
12 𝑚𝑚Ø × 6𝑚: 35 𝑝𝑐𝑠 × = 𝑃ℎ𝑝 5, 600.00
𝑝𝑐

𝑃ℎ𝑝 109.00
10 𝑚𝑚Ø × 6𝑚: 106 𝑝𝑐𝑠 × = 𝑃ℎ𝑝 11, 554.00
𝑝𝑐

𝑃ℎ𝑝 60.00
𝑁𝑜. 16 𝐺𝐼 𝑇𝑖𝑒 𝑊𝑖𝑟𝑒: 40 𝑘𝑔 𝑥 = 𝑃ℎ𝑝 2, 400.00
𝑘𝑔

𝑇𝑜𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 = 𝑃ℎ𝑝 126, 197.00