WAPCOS LIMITED
(A Govt. of India Undertaking-Ministry of Water Resources, River Development & Ganga Rejuvenation)
Project Office, Vadodara
rd
304, 3 Floor, Saket Complex, Opp. Dr. Kadam’s Eye Hospital,
Nr. Urmi Char Rasta, Akota, Vadodara-390 020
Email: wapcosbaroda@yahoo.com
Prepared By Verify By
Above/Below in % 1.39%
Expected Date of
31/05/2019
Completion
% Work completed as
95 %
on date
Page 1
Monthly Progress Report-FP-127 Gotri LIG
FP No.-127 TP No.-60Gotri
Total
Sr. Carpet
Description No. of Unit Area ( In
Area
No. Sqmt)
(Sq.mt.)
1
Area of Plot - 15068.00 -
2 100 DU’s + 4968.00 +
L.I.G.-2 BHK :
16 Shopping Unit - 108.00
Block--A (P+13)
= 5076
3 100 DU’s + 4968.00 +
L.I.G.-2 BHK :
16 Shopping Unit - 108.00
Block--B (P+13)
= 5076
4 104 DU’s
L.I.G.-2 BHK :
5166.72
Block--C(P+13)
5
L.I.G.-2 BHK : 104 DU’s
5166.72
Block--D(P+13)
6 L.I.G.-2 BHK :
104 DU’s
Block--E (P+13) 5166.72
7 L.I.G.-2 BHK :
104 DU’s
Block--F (P+13) 5166.72
8 L.I.G.-2 BHK :
104 DU’s
Block--G (P+13) 5166.72
7 Aanganwadi Area 0
8 Parking
Commercial parking
4694 + 288
Residential Parking
= 4982
Total Parking
Page 2
Monthly Progress Report-FP-127 Gotri LIG
Sr. Name of Cleaning PCC &RCC Back Filling Slab Masonry Doors &
No. Structure and upto plinth work/ Windows
Excavation Beam RCC wall
Block No.
1 Completed Completed 100 % 100% 100 % 90%
A
Block No.
2 Completed Completed 100% 100% 96 % 85%
B
3 Block No. C Completed Completed 100 % 100 % 100 % 100%
Block No.
4 Completed Completed 100 % 100 % 100 % 100%
D
5 Block No. E Completed Completed 100 % 100 % 100 % 100%
6 Block No. F Completed Completed 100 % 100 % 100 % 100%
Block No.
7 Completed Completed 100 % 100% 100 % 100%
G
Page 3
Monthly Progress Report-FP-127 Gotri LIG
Page 4
Monthly Progress Report-FP-127 Gotri LIG
Total Actual
Sr. Balance
Scope Progress % %
Item Description work (No.
No ( No. of (No. of Completed Balance
of Block)
Blocks) Blocks)
27 Flooring Work(8th floor) 7 7 0 100 % 0%
28 Flooring Work(9th floor) 7 7 0 100 % 0%
29 Flooring Work(10th floor) 7 7 0 100 % 0%
30 Flooring Work(11th floor) 7 7 0 100 % 0%
31 Flooring Work(12th floor) 7 7 0 100 % 0%
32 Flooring Work(13th floor) 7 7 0 100 % 0%
33 Door/Window/Ventilator 7 5 2 74.43 % 25.57%
34 Plumbing Work (1st floor) 7 5 2 74.43 % 25.57%
35 Plumbing Work (2nd floor) 7 5 2 74.43 % 25.57%
36 Plumbing Work (3rd floor) 7 5 2 74.43 % 25.57%
37 Plumbing Work (4th floor) 7 5 2 74.43 % 25.57%
38 Plumbing Work (5th floor) 7 5 2 74.43 % 25.57%
39 Plumbing Work (6th floor) 7 5 2 74.43 % 25.57%
40 Plumbing Work (7th floor) 7 5 2 74.43 % 25.57%
41 Plumbing Work (8th floor) 7 5 2 74.43 % 25.57%
42 Plumbing Work (9th floor) 7 5 2 74.43 % 25.57%
43 Plumbing Work (10th floor) 7 5 2 74.43 % 25.57%
44 Plumbing Work (11th floor) 7 5 2 74.43 % 25.57%
45 Plumbing Work (12th floor) 7 5 2 74.43 % 25.57%
46 Plumbing Work (13th floor) 7 5 2 74.43 % 25.57%
47 Electric Work 7 5 2 74.43 % 25.57%
48 Water Proofing and China 7 7 0 100 % 0%
Mosaic
49 Land Scaping - - - 80% 20%
50 Road Work - - - 90 % 10%
Page 5
Monthly Progress Report-FP-127 Gotri LIG
-
5 Compound Wall
-
6 Three Phase Electricity
-
7 Mix Design
-
8 Bore work
-
9 Field Lab
-
10 Batching Plant
-
11 Labour colony
-
12 Office Const.
-
13 Toilet Blocks for worker
4.0 FINANCIAL PROGRESS
Sr. Progress
Type of Structure Value ( in Lac)
No. Achieved
1 All Block 8867.04 6123.91
2 Others - -
Page 6
Monthly Progress Report-FP-127 Gotri LIG
Sr.
AMOUNT –Rs. DATE OF APPROVAL REMARK
No.
1 1,05,72,500/- 13/07/2016
2 1,37,49,600/- 01/09/2016 -
3. 3,21,77,400/- 13/10/2016
4. 2,20,64,700/- 27/10/2016
5 2,60,27,300/- 18/11/2016
6 2,09,81,100/- 09/02/2017
7 2,67,51,800/- 19/02/2017
8 2,69,71,200/- 08/03/2017
9. 4,11,41,700/- 31/03/2017
10. 4,33,78,000/- 05/04/2017
11. 2,39,69,865/- 10/04/2017
12. 2,40,33,833/- 10/05/2017
13 3,20,16,444/- 10/06/2017
14 3,54,77,302/- 10/07/2017
15 2,95,26,126/- 10/08/2017
16 3,03,29,721/- 10/10/2017
17 2,99,48,849/- 10/12/2017
18 1,63,64,311/- 10/01/2018
19 2,11,18,100/- 10/03/2018
20 2,45,78,700/- 10/04/2018
21 1,60,64727/- 31/05/2018
22 1,01,65,436/- 21/06/2018
23 1,10,15,303/- 15/07/2018
24 1,01,70,100/- 23/08/2018
25 1,47,12,800/- 11/10/2018
26 1,90,84,500/-
Total 61,23,91,500/-
Page 7
Monthly Progress Report-FP-127 Gotri LIG
Actual Achieved
Financial Progress in Rs. Time Allowed( Financial
Sr.
Required in Time From date of Progress in Rs. Remark
No.
Allowed Start) Lacs in Time
Allowed
4 Full - - -
7.0 RESOURCES
DESIGNATION NAME
Contractors In charge Nilesh Gandhi
Consultant Site In charge Engineer Rajput. L. G.
Site Engineer Nirav Prajapati
Resources
Sr.
Resources Available Required to Remark
No.
Achieve Mile stone
1 Material Yes -
Page 8
Monthly Progress Report-FP-127 Gotri LIG
Sr.
Critical Issues/ Hindrances Action Taken
No.
NIL NIL
FP No.-127 TP No.-60Gotri
Name of
Sr. No Observation/Inspection Note Action Status
Block
NIL NIL NIL
Page 9
Monthly Progress Report-FP-127 Gotri LIG
TOWER A B C D E F G TOTAL
Tot F.S.I 6557.26 6557.26 6300.32 6300.32 6300.32 6300.32 6300.32 44616.12
Page 10
Monthly Progress Report-FP-127 Gotri LIG
Landscap
Page 11
Monthly Progress Report-FP-127 Gotri LIG
Page 12